EASTIMATE

Project Name - DPR of Widening & Strengthening of Alipingal-Khaira Road 12.64 KM

SL No. Description Length Rate per KM Amount in


( In KM) In Rs. Rs.
01s To carryout survey , Investigation , Soil Test 12.64 16,000.00 2,02,240.00
& preparation of DPR showing all physical Features
like Trees ,Nallah , River , Railway Line , Canal ,
Stream, Electric pole for the required . Submitted
the DPR as per Engineer-in-Charge
( Intermediate Lane )
02 Mobilization for collection of CBR from Field to
Lab For different test like (A) Grain size analysis 12.64 5,478.00 69,241.92
(B) Liquid Limit & Plastic Limit (C) Free Soil Index
(D)CBR Test (E) Collection of UDS for preparation
Of detail report required for strengthening the
Existing road to be submitted in 4 sets (insoft as
Well as hard copies ) for calculation of CBR from
Alipingal to Khaira road Updatation of Inventory
Data for road bridge & Culvert in (0-Ram) data
Base at Jagatasingpur

Total Rs = 2,71,481.92
Add 1% Contigency Rs = 2,714.81
Total Rs = 2,74,196.73
Add 18% GST Rs = 49,355.41
Grand total Rs = 3,23,552.14
Or Say Rs = 3,23,552.00
Rupees in Words ( Three lakhs Twenty three thousand Five hundred Fifty two only )