Professional Documents
Culture Documents
Prefi: Name Location of Rebars Clas S Name of Rebars Start# Comments
Prefi: Name Location of Rebars Clas S Name of Rebars Start# Comments
Prefi: Name Location of Rebars Clas S Name of Rebars Start# Comments
MAIN PART s
X21 CLASSES
SHEARWALLS U BARS X21 "X" should be adjusted based on the level the element is located at.
BOTTOM INNER X22 BOTTOM BAR First floor (ground) will be on the 100 series, 2nd Floor on the 200 series
BOTTOM OUTER X23 BOTTOM BAR and so on.
TOP INNER X24 TOP BAR COMPONENT
1
SLAB TOP OUTER X25 TOP BAR Top and bottom bars are placed using the Slab Reinforcement Tool.
SIDES BOTTOM X26 SIDE&OPENING BAR Set appropriate spacings, splice length and maximum total rebar length
SIDES TOP X27 SIDE&OPENING BAR (usually 40'-0" maximum)
OPENINGS BOTTOM X28 SIDE&OPENING BAR
OPENINGS TOP X29 SIDE&OPENING BAR
CAST IN PLACE - SUPER STRUCTURE
DOWELS DOWEL
1
COLUMNS LINKS X85 STIRRUP COMPONENT
X86
X87
X88
DOWEL X89
SW
WALL
1
TIES IN CORNER X95 TIE If shear wall is not continued up, choose number based on level at bottom
SHEARWALL
TIES INSIDE X96 TIE of the shear wall.
STIRRUP IN CORNERS?? X97 STIRRUP COMPONENT
X98
DOWEL X99 DOWEL
1
BEAM X34 COMPONENT
STIRRUPS 1 X35 STIRRUP Rebar in beam (90)
STIRRUPS 2 X36 STIRRUP
STIRRUPS 3 X37 STIRRUP
SIDEBARS X38 SIDE