This document provides a method statement for installing windows at a proposed 6-lot commercial and hotel development project. It details 4 tasks for installing 324 meters of reinforced concrete lintels, fabricating and installing 197 aluminum window frames of various types, and supplying and installing the windows. The tasks will require machinery like vibrators, bending machines, drills, and hand tools operated by 5-6 general laborers over a total duration of 15-13 days.
This document provides a method statement for installing windows at a proposed 6-lot commercial and hotel development project. It details 4 tasks for installing 324 meters of reinforced concrete lintels, fabricating and installing 197 aluminum window frames of various types, and supplying and installing the windows. The tasks will require machinery like vibrators, bending machines, drills, and hand tools operated by 5-6 general laborers over a total duration of 15-13 days.
This document provides a method statement for installing windows at a proposed 6-lot commercial and hotel development project. It details 4 tasks for installing 324 meters of reinforced concrete lintels, fabricating and installing 197 aluminum window frames of various types, and supplying and installing the windows. The tasks will require machinery like vibrators, bending machines, drills, and hand tools operated by 5-6 general laborers over a total duration of 15-13 days.
TITLE OF PROJECT: CADANGAN MEMBANGUNKAN 6 LOT BANGUNAN KEDAI PEJABAT 5 TINGKAT YANG MENGANDUNGI 5 UNIT KEDAI PEJABAT 2 TINGKAT DAN 1 UNIT HOTEL BUDGET 84 BILIK DI ATAS LOT 39918-39923, MEDAN GOPENG, MUKIM HULU KINTA, PERAK DARUL RIDZUAN UNTUK TETUAN KOPERASI PERUMAHAN MELAYU PERAK BERHAD PREPARED BY: NOR NAJWA BINTI ABD RAHMAN DATE: 15/4/2019 ELEMENT: WINDOW PAGE NO: 1/4
NO TASK QUANTITY SEQUENTIAL MACHINERY/ MANPOWER/ OUTPUT DURATION
DIAGRAM TOOL LABOUR
1. Vibrated reinforced concrete 324 m 1 Vibrator 1 General = 1hr/m3 x 2 Day
Grade 30, 125mm x 250mm Machine Labor 10.13m3 depth as described lintel reinforcement with and 10.13hr/m including 4 no’s 3 = 10.13m3/8 hr = 1.27 days 24 CENTURY CONSTRUCTION SDN. BHD. METHOD STATEMENT FORM TITLE OF PROJECT: CADANGAN MEMBANGUNKAN 6 LOT BANGUNAN KEDAI PEJABAT 5 TINGKAT YANG MENGANDUNGI 5 UNIT KEDAI PEJABAT 2 TINGKAT DAN 1 UNIT HOTEL BUDGET 84 BILIK DI ATAS LOT 39918-39923, MEDAN GOPENG, MUKIM HULU KINTA, PERAK DARUL RIDZUAN UNTUK TETUAN KOPERASI PERUMAHAN MELAYU PERAK BERHAD PREPARED BY: NOR NAJWA BINTI ABD RAHMAN DATE: 15/4/2019 ELEMENT: WINDOW PAGE NO: 2/4
NO TASK QUANTITY SEQUENTIAL MACHINERY/ MANPOWER/ OUTPUT DURATION
DIAGRAM TOOL LABOUR 2. 12mm and 10mm diameter mild steel bar reinforcement hooked at both ends with 6mm 2 Bending 5 General = 3.0 per 15 Days diameter mild steel bar Machine Labors hr x 197 reinforcement. nos 3 Cutter a. Aluminium frame 100 nos = 689.5 hr/ casement window size window b. Aluminium frame 24 nos sliding window = 591 / 8 c. Aluminium frame 30 nos hr casement window d. Aluminium frame top 34 nos = 73.8 hung window days / 5 e. Aluminium frame 2 nos labors window = 14.7 f. Frameless fixed 2 nos days tempered glass 1 nos g. Aluminium frame fixed window 4 nos h. Aluminium frame fixed window 24 CENTURY CONSTRUCTION SDN. BHD. METHOD STATEMENT FORM TITLE OF PROJECT: CADANGAN MEMBANGUNKAN 6 LOT BANGUNAN KEDAI PEJABAT 5 TINGKAT YANG MENGANDUNGI 5 UNIT KEDAI PEJABAT 2 TINGKAT DAN 1 UNIT HOTEL BUDGET 84 BILIK DI ATAS LOT 39918-39923, MEDAN GOPENG, MUKIM HULU KINTA, PERAK DARUL RIDZUAN UNTUK TETUAN KOPERASI PERUMAHAN MELAYU PERAK BERHAD PREPARED BY: NOR NAJWA BINTI ABD RAHMAN DATE: 15/4/2019 ELEMENT: WINDOW PAGE NO: 3/4
NO TASK QUANTITY SEQUENTIAL MACHINERY/ MANPOWER/ OUTPUT DURATION
DIAGRAM TOOL LABOUR 3. Supply and fix the following aluminium window frame with 3 Drill Machine 5 General = 3.0 per 15 Days minimum 8mm thick sheet 2 Measuring Labours hr x 197 glass panel, complete with all Tape nos necessary 100 nos a. Aluminium frame = 689.5 2 Spirit Level casement window size 24 nos hr/ b. Aluminium frame sliding window window 30 nos c. Aluminium frame = 591 / 8 casement window 34 nos hr d. Aluminium frame top hung = 73.8 window 2 nos days / 5 e. Aluminium frame window labors 2 nos f. Frameless fixed tempered glass = 14.7 1 nos days g. Aluminium frame fixed window 4 nos h. Aluminium frame fixed window 24 CENTURY CONSTRUCTION SDN. BHD. METHOD STATEMENT FORM TITLE OF PROJECT: CADANGAN MEMBANGUNKAN 6 LOT BANGUNAN KEDAI PEJABAT 5 TINGKAT YANG MENGANDUNGI 5 UNIT KEDAI PEJABAT 2 TINGKAT DAN 1 UNIT HOTEL BUDGET 84 BILIK DI ATAS LOT 39918-39923, MEDAN GOPENG, MUKIM HULU KINTA, PERAK DARUL RIDZUAN UNTUK TETUAN KOPERASI PERUMAHAN MELAYU PERAK BERHAD PREPARED BY: NOR NAJWA BINTI ABD RAHMAN DATE: 15/4/2019 ELEMENT: WINDOW PAGE NO: 4/4
NO TASK QUANTITY SEQUENTIAL MACHINERY/ MANPOWER/ OUTPUT DURATION
DIAGRAM TOOL LABOUR 4. Supply and installation of window. 3 Drill Machine 6 Labors = 2.5 per 13 Days 100 nos 2 Measuring hr x 197 a. Aluminium frame casement Tape nos window size b. Aluminium frame sliding 24 nos = 492.5 hr/ window 2 Spirit Level 30 nos window c. Aluminium frame casement window = 492.5 / 8 34 nos hr d. Aluminium frame top hung window 2 nos = 61.5 e. Aluminium frame window days / 5 f. Frameless fixed tempered 2 nos labors glass g. Aluminium frame fixed 1 nos = 12.3 window days h. Aluminium frame fixed 4 nos window