Professional Documents
Culture Documents
35
35
35
Dr. T. Ananthapadmanabha *
Dr. K. Parthasarathy**
K.Nagaraju***
G.V. Venkatachalam ****
* The National Institute of Engineering, Mysore.
** Power Research and Development Consultants Private Limited, Bangalore.
***The Bapuji Institute of Engineering and Technology. Davangere.
**** Karnataka Power Transmission Corporation Limited, Davanagere
INDIAN INSTITUTE OF TECHNOLOGY, KHARAGPUR 721302, DECEMBER 27-29, 2002 275
TABLE-1
The membership functions for the power and suitability The node with highest suitability value is the best node for
indices are created for ranking. Therefore portions of the capacitor installation.
membership function for the power and suitability indices are
equally spaced. The use of FES determines the nodes by In the Second Part optimum capacitor sizing is carried in the
finding a compromise between the possible loss reduction following steps
from capacitor installation and voltage levels. 1. After determining the suitable node for the capacitor
installation, a small capacitor unit (Commercially
The following example will demonstrate the available) is installed at that node.
max_prod inferencing membership of FES. Ex: A given node 2. The peak power loss voltage drops at each node are
has a power loss index 0.7 and voltage drop of 0.3 from the calculated by installing the capacitor.
FES inferencing it can be seen that, this node has a medium 3. The benefits due to reduction in the power demand (KP),
and high medium power loss index and low normal voltage. released in feeder capacity (KF), reduced annual energy
Following rules are fired from the decision matrix. losses (KE) and cost of installation of capacitor (KC) are
calculated.
(1) If power loss index is Medium AND voltage is High 4. The nets savings due to installation of capacitor is given
Normal then suitability is medium. by NS=KP+KF+KE-KC
(2) If power loss index is High Medium AND voltage is 5. Another capacitor unit installed at the same location and
High Normal then suitability is net savings are calculated as described above.
High Medium. 6. This procedure is repeated for maximum net savings.
To aggregate the output of the two rules, the Mamadani Also voltage constraint is checked for each iteration
max_prod inferencing technique is applied so that the (During no load conduction). If the voltage exceeds the
resulting membership function is de fuzzyified and suitability prescribed level then the installation of that capacitor
value is 0.68. unit is rejected
Solutions Algorithm
Mainly consist of two steps
Step1 Determine power loss and voltage drop at each node and to Determine the suitable node for
capacitor placement using fuzzy expert system
Step2 Size the capacitor for achieving maximum financial benefits
X= Inductance of the circuit Qc then, new reactive power of the line up to the chosen node
Cos θ = P.F. of the segment is Q2. That is Q2 = Q-QC
The annual energy losses can be calculated as below The new P.F = P
Annual energy losses = PPL x LLR x 8760 units
Where P2 + Q22
P.P.L = Peak Power losses in KW
L.L.F = Loss load Factor = 0.2 (LF) x 0.8 (LF)2 Released KVA = ∆KF = S– P2 + Q22
Where L.F = Load Factor = Average load Where S = apartment power (original)
Peak load By knowing the releasing feeder capacity the benefits due
or released feeder capacity can be calculated. Improvement in
= Annual energy sent out P.F. results in improvement in voltage profile causing
peak load x 8760 reduction in current, which in turn reduces the peak power
Finally the voltage regulation of the feeder is given by loss, and reduction in annual energy losses. The savings of
% VR = ES –Er x 100 energy (units) due to additions of this capacitor can be
11 calculated by deducing the annual energy losses due to
Where installation of capacitor from the Annual energy losses of the
Es = Supply end voltage of the segment in KV. original system. Thus by knowing the savings of energy due
Er = Receiving end voltage of the segment in KV. to capacitor placement , benefits due to energy savings can be
After calculating the above, peak power loss and calculated.
voltage drop at each node are represented by fuzzy
membership function. The node at which max peak power Benefits due to Reduced demand
loss occurs will have the value 1 and the max voltage drop Benefits due to Reduced demand KP = ∆KP x CKP
node will have the value 1.The peak power losses and voltage x iKP
drop at each node were calculated and are linearly normalized Where
in to a [0,1] range . It is advisable to install the ∆KP = Reduced demand (KW)
capacitor at the node with high peak power loss [so as to CKP = Cost of generation / KW (Taken as
reduce max power loss] and the high voltage drop [so as to Rs 10,000/KW)
improve the voltage profile to the maximum extent]. The IKP = Annual rate for generation cost.
voltage drop and power loss indices are the inputs and the out (Taken as 0.2)
put consequent is the suitability capacitor placement by Benefits due to released feeder capacity
applying the rules as indicated in the table 1 .The consequent Benefits due to released feeder capacity KF = ∆KF x
obtained for each node is recorded and nodes are ranked CKF x iKF
according to the suitability value. The node having the high Where
suitable value will be best location for the capacitor ∆KF = released feeder capacity
installation. CKF = Cost of the feeder / KVA (Taken as
Rs 1,41,090/KM)
Step 2 IKF = Annual rate of cost of feeder (Taken
The best suitable node was determined in the as 0.2)
previous step. The optimal capacitor size to be placed at the
chosen node to be determined for most economic savings in Benefits due to savings in energy
this step. Benefits due to savings in energy KE = ∆KE x r
Where ∆ KE = savings in energy
In this step a 200KVAR capacitor unit (least rated
∆KE= (Annual energy losses before installing the
commercially available unit) is placed at the chosen node
capacitor) –
and varies parameters are calculated due to addition of the
(Annual energy losses after installing the
capacitor. The net savings function NS, maximized by this
capacitor.)
capacitor sizing algorithm is given by
r = Rate of energy in Rs / Unit. (Taken as Rs 3/unit)
NS = KP + KF+ KE – KC
Where
KP = Benefits due to released demand (KW)
KF = Benefits due to released feeder capacity
Cost of installation of capacitor
(KVA)
KC= ∆KC x ICKC x iKC
KE = Benefits due to saving in energy (KWH)
Where
KC = Cost of installation of the capacitor.
∆KC = No. of 200 KVAR capacitor units
Commercially available 200KVAR capacitor unit is installed ICKC = Cost of each 200 KVAR capacitor (Taken
at the chosen node by adding this unit, reactive power of the as Rs 40,000/200kvar)
line will be altered. Let the system reactive power (up to the iKC = Annual rate of cost of capacitor (Taken as
chosen node from sending end) be Q, and capacitor added be 0.2)
INDIAN INSTITUTE OF TECHNOLOGY, KHARAGPUR 721302, DECEMBER 27-29, 2002 277
2
Thus the net savings due to the addition of the Er= Es + Es + Qc x L
capacitor is calculated. 2 2 1000
Further another 200KVAR capacitor is installed at
the same node and net savings due to this is calculated. This Where
procedure is repeated up to the size that there is no additional QC= Installed capacitor in KVAR
net savings. L = Length of the line from sending end
Es = Supply end voltage in KV.
Checking the constraint for voltage Limit volition
The voltage of all sections shall be below the This constraint is checked before proceeding to the
statutory upper limit at light load condition. The voltage at next steps. If the % VR is > 6% then the installation of the
the section of installation of capacitor may go beyond the capacitor is rejected.
prescribed limit at light loads. This constraint has to be
checked before proceeding to the installation of capacitor System Studied
unit. The described method is applied to 11 KV, 21 bus
The approximate voltage due to installation of the radial distribution system as shown below.
capacitor at no load is given by
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
After calculation of the node voltage and power loss indices, the FES determines that node 11 has a high power loss and
normal voltage level. The defuzzifide suitability index indicated at node 11 is the most suitability location for capacitor
installation. The optimum size of capacitor is found to be 1200 KVAR. The comparison of savings and voltage due to various
size of capacitor are as followings.
278 NATIONAL POWER SYSTEMS CONFERENCE, NPSC 2002
CONCLUSIONS