Demonstration 1

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Demonstration- 1

Before After
Installation Recovery Recovery
-36 16
Tower 3 Light Fixtures TF
Recovery Plan
Total Working Total Recovery
Level Area Duration
Duration Pattern Duration Days
20 Office 7
11
20 Corridor 4
19 Office 7
11 Parallel 7 4
19 Corridor 4
18 Office 7
11 Parallel 7 4
18 Corridor 4
17 Office 7
11 Parallel 7 4
17 Corridor 4
16 Office 7
11 Parallel 7 4
16 Corridor 4
15 Office 7
11 Parallel 7 4
15 Corridor 4
14 Office 7
11 Parallel 7 4
14 Corridor 4
13 Office 7
13 Corridor 4
11 Parallel 7 4 52
12 Office 7
11 Parallel 7 4
12 Corridor 4
11 Office 7
11 Parallel 7 4
11 Corridor 4
10 Office 7
11 Parallel 7 4
10 Corridor 4
9 Office 7
11 Parallel 7 4
9 Corridor 4
8 Office 7
11 Parallel 7 4
8 Corridor 4
7 Office 7
11 Parallel 7 4
7 Corridor 4
6 Office 7
11
6 Corridor 4
5 Office 7
11
5 Corridor 4
4 Office 7
11
4 Corridor 4
3 Office 7
11
3 Corridor 4
2 Office 7
11
2 Corridor 4

You might also like