Provincial Engineer's Office Farmhouse Building, Antonio Luna ST., CDOC Tel No. 721007
Provincial Engineer's Office Farmhouse Building, Antonio Luna ST., CDOC Tel No. 721007
Effectivity of Contract : March 29, 2019 Suspension Order Date : March 29, 2019
Target Completion Date : May 14, 2019 Resumption Date : May 13, 2019
Revised Completion Date : June 24, 2019
Actual Date Completed : October 24, 2019
Project Cost : Php 3,953,720.86
Pursuant to the provisions of Section 68 of the Republic Act No. 9184 and its
Implementing Rules and Regulations (IRR), the amount of liquidated damages shall be at least
equal to one-tenth of one percent (0.1%) of the cost of the unperformed portion of every day
of delay. Once the cumulative amount of the liquidated damages reaches ten percent (10%)
of the amount of the contract, the procuring entity shall rescind the contract, without
prejudice to other courses of action and remedies open to it.
Approved by:
MARIO V. BATAR
Provincial Engineer