LIQUIDATED DAMAGES COMPUTATION FOR THE PROJECT COMPLETION OF ROAD

IMPROVEMENT OF PANGAYAWAN TO G.PELAEZ GITAGUM PROVINCIAL ROAD LAGUINDINGAN,


MISAMIS ORIENTAL

Effectivity of Contract : March 29, 2019 Suspension Order Date : March 29, 2019
Target Completion Date : May 14, 2019 Resumption Date : May 13, 2019
Revised Completion Date : June 24, 2019
Actual Date Completed : October 24, 2019
Project Cost : Php 3,953,720.86
Pursuant to the provisions of Section 68 of the Republic Act No. 9184 and its
Implementing Rules and Regulations (IRR), the amount of liquidated damages shall be at least
equal to one-tenth of one percent (0.1%) of the cost of the unperformed portion of every day
of delay. Once the cumulative amount of the liquidated damages reaches ten percent (10%)
of the amount of the contract, the procuring entity shall rescind the contract, without
prejudice to other courses of action and remedies open to it.

Remaining Works Unperformed:


ITEM DESCRIPTION QUANTITY UNIT UNIT COST TOTAL COST
Portland Cement
311(2) 48.91 cu. m. 5,658.77 ₱ 276,760.46
Concrete Pavement

Delay in Calendar days = Revised Completion Date – Actual Completion Date


= June 24, 2019 – October 24, 2019
= 122 Calendar Days
Negative Slippage = 7%

Liquidated Damages = 0.1% x cost of unperformed portion x delay in calendar


days
= (1/10 of 1%) x Cost of Remaining Works x Days delayed
= 0.001 x 276,760.46 x 122 Days delayed
= ₱ 33,764.78

Prepared by: Noted by:

JOEL A. OBINA PAUL JOEL S. WAGA JR.


Project Engineer Construction Division Chief

Approved by:

MARIO V. BATAR
Provincial Engineer