ID ID Task Name Duration Start Finish: Mar Apr May Jun Jul Aug Sep Oct Nov QTR 2, 2020 QTR 3, 2020 QTR 4, 2020

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ID ID Task Name Duration Start Finish Qtr 2, 2020 Qtr 3, 2020 Qtr 4, 2020

Mar Apr May Jun Jul Aug Sep Oct Nov


1 1 Phase 1 (Planning and Design LoRawan Gateway) 30 days Mon 02-03-20 Fri 10-04-20
2 2 Kick-Off Meeting 1 day Mon 02-03-20 Mon 02-03-20
3 3 Technical specifications determined 5 days Tue 03-03-20 Mon 09-03-20 Administrative Assistant ;Project Manager ;Senior Writers ;System Analysts ;Systems Consultant ;Vice Presid
4 4 Design plan developed 23 days Tue 10-03-20 Thu 09-04-20
8 8 Administrative Preparation 22 days Tue 10-03-20 Wed 08-04-20
12 12 Phase 2 (Preparation for installation) 60 days Mon 13-04-20 Fri 03-07-20
13 13 Preliminary Preparation 7 days Mon 13-04-20 Tue 21-04-20
14 14 Preliminary Design Review 5 days Mon 13-04-20 Fri 17-04-20
15 15 Preliminary Design Approval 2 days Mon 20-04-20 Tue 21-04-20
16 16 Equipment ordering 3 days Wed 22-04-20 Fri 24-04-20 Administrative Assistant
17 17 System Prototype 15 days Mon 27-04-20 Fri 15-05-20
22 22 Prototype Configuration 5 days Mon 18-05-20 Fri 22-05-20 Programmers ;Senior Testers ;System Analysts ;Tester
23 23 Prototype Testing 2 days Mon 25-05-20 Tue 26-05-20 Senior Testers ;Tester
24 24 Prototype Analysis 5 days Wed 27-05-20 Tue 02-06-20
28 28 System Software Configuration 23 days Wed 03-06-20 Fri 03-07-20
30 30 Phase 3 (Installation) 30 days Mon 06-07-20 Fri 14-08-20
31 31 Site Installation : Kota Jayapura 25 days Mon 06-07-20 Fri 07-08-20
48 48 Site Installation : Kabupaten Jayapura 25 days Mon 06-07-20 Fri 07-08-20
64 64 Site Installation : Kabupaten Keerom 25 days Mon 06-07-20 Fri 07-08-20
75 75 Documentation set-up for all sites 5 days Mon 10-08-20 Fri 14-08-20 Site Engineer;Chief Editor ;Senior Writers ;W
76 76 Phase 4 ( Installation follow - up) 15 days Mon 10-08-20 Fri 28-08-20
77 77 Testing and Commissioning di Kota Jayapura 5 days Mon 10-08-20 Fri 14-08-20 Programmers ;Site Engineer;Tester
78 78 Testing and Commissioning di Kabupaten Jayapura 5 days Mon 10-08-20 Fri 14-08-20 Programmers ;Site Engineer;Tester
79 79 Testing and Commissioning di Kabupaten Keerom 5 days Mon 10-08-20 Fri 14-08-20 Programmers ;Site Engineer;Tester
80 80 User Orientation 7 days Mon 17-08-20 Tue 25-08-20
85 85 Post-installation Review 4 days Wed 26-08-20 Mon 31-08-20 Project Manager ;System Analysts ;Sys
86 86 System Acceptance 1 day Tue 01-09-20 Tue 01-09-20 Project Manager ;Vice President - Man
87 87 Phase 5 (Masa Garansi) 60 days Wed 02-09-20 Tue 24-11-20
88 88 Maintenance 60 days Wed 02-09-20 Tue 24-11-20 Adm

Page 1

You might also like