I visited the above mentioned site and work done is as given bellow.
Total Rs.12,42,571.56
Respected sir,
Above work is carried out as per drawing and designs. Progress of work is satisfactory.
Thanking you.
Yours Faithfully
Date : 04 / 06 /2018
Shri A.M. ATHANI
D.C.E.
I visited the above mentioned site and work done is as given bellow.
2] Flooring RS 71,932.50
Total Rs-14,63,042.70
Respected sir,
Above work is carried out as per drawing and designs. Progress of work is satisfactory.
Thanking you.
Yours Faithfully
D.C.E.
I visited the above mentioned site and work done is as given bellow.
Total Rs-15,90,766.81
[Rs. Fifteen Lakh, Ninty Thousand, Seven hundred Sixty seven Only.]
Respected sir,
Above work is carried out as per drawing and designs. Progress of work is satisfactory.
Thanking you.