PROGRESS REPORT -II

NAME OF WORK : Proposed construction of Farm House in .No.329/2


At -Muchandi Tal.- Jat , Dist.- Sangli

Name of Owner : Shri.- BABU APPARAYA PATIL .

I visited the above mentioned site and work done is as given bellow.

Sr.No. DESCRIPTION OF ITEAM STAGE OF WORK AMOUNT

1] Work done as per Previous Progress Report. Rs.1,043,797.00

2] R.C.C. Slab RS 1,29,754.80

2] Plastering ( Internal ) RS 69,020.56

Total Rs.12,42,571.56

Say Rs. 12,42,571.00

[Rs. Tollv Lakh, Fortetwo Thousand, Five Hundred Seventyone Only.]

Respected sir,

Above work is carried out as per drawing and designs. Progress of work is satisfactory.

Thanking you.

Yours Faithfully

Date : 04 / 06 /2018
Shri A.M. ATHANI

D.C.E.

 Consulting Civil Engineer.


 Supervise. I
 Valuer & Surveyer.
 Re.NO.S/I 198.

PROGRESS REPORT -III

NAME OF WORK : Proposed construction of Farm House in .No.329/2


At -Muchandi Tal.- Jat , Dist.- Sangli

Name of Owner : Shri.- BABU APPARAYA PATIL .

I visited the above mentioned site and work done is as given bellow.

Sr.No. DESCRIPTION OF ITEAM STAGE OF WORK AMOUNT

1] Work done as per Previous Progress Report. Rs. 12,42,571.00

2] Plastering ( External ) RS 1,48,539.20

2] Flooring RS 71,932.50

Total Rs-14,63,042.70

Say Rs- 14,63,042.00

[Rs. Fourteen Lakh, sixtythree Thousand, Fourtytwo Only.]

Respected sir,

Above work is carried out as per drawing and designs. Progress of work is satisfactory.

Thanking you.

Yours Faithfully

Date :- 30/ 06 /2018


Shri A.M. ATHANI

D.C.E.

 Consulting Civil Engineer.


 Supervise. I
 Valuer & Surveyer.
 Re.NO.S/I 198.

PROGRESS REPORT -IV

NAME OF WORK : Proposed construction of Farm House in .No.329/2


At -Muchandi Tal.- Jat , Dist.- Sangli

Name of Owner : Shri.- BABU APPARAYA PATIL .

I visited the above mentioned site and work done is as given bellow.

Sr.No. DESCRIPTION OF ITEAM STAGE OF WORK AMOUNT

1] Work done as per Previous Progress Report. Rs. 14,63,042.00

2] Coloring ( Internal & External ) RS 23,655.78

3] Sanitary fitting RS 74,335.02

4] Electrical fitting RS 29,734.01

Total Rs-15,90,766.81

Say Rs- 15,90,767.00

[Rs. Fifteen Lakh, Ninty Thousand, Seven hundred Sixty seven Only.]

Respected sir,

Above work is carried out as per drawing and designs. Progress of work is satisfactory.

Thanking you.

Yours Faithfully

Date :- 01/ 02 /2019

You might also like