Daily Progress Report: Mtr. 4690 Mtr. Mtr. 4690
Daily Progress Report: Mtr. 4690 Mtr. Mtr. 4690
: PRJ 200
Daily Progress Report REV.No.: 00
Eff.Date: 01.02.2018
Client : Adani Gas Ltd Pipe Dia & Thickness :12" & 7.9mm Date: 08-11-2019
Contractor : Tolani Projects Pvt Ltd Pipe Specification :API 5L Gr-X-42M
TPIA : TUV India Location :Riico road to Hindustan zinc Puliya, chittorgarh
PROGRESS Qty Executed
Weekly Last
Sr Total Qty
No
Activity UOM
(Scope)
Planing Week
Today’s Previous Cumulat. Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Total
Progress
Repair Segment - 16 16 0 0 0 0 0 0 0
8 Trenching Mtr. 4690 72.66 2522.72 2595.38 96.65 0.00 217.95 72.66 72.66 459.92 529.61
9 Lowering Mtr. 4690 72.66 ### 2528.85 96.65 0.00 217.95 24.22 72.66 411.48 529.61
14 Backfilling Nos. 73.86 2,163.32 2237.18 0 96.83 145.08 96.87 73.86 412.64 411.85
Manpower Machinery
Welding Supervisor
Warning Mat 20 KM
ANY PROBLEMS :
DPR as on 08.11.2019