Professional Documents
Culture Documents
1373025555653-Delhi Gurgaon Toll Road - Sanjay Aggarwal
1373025555653-Delhi Gurgaon Toll Road - Sanjay Aggarwal
Sanjay Aggarwal
Dy Chief Materials Manager
Northern Railway
Page 1 of 41
Contents
Project Description 1
PPP Structure of the Project 3
Current Status 6
Financing Information 7
Process Analysis 8
Risk Allocation Framework 13
Post facto VfM analysis 31
Key Learning and Observations 33
Conclusion 36
Page 2 of 41
Declaration
I declare that the project Report on “Delhi Gurgaon
Toll Road”is submitted by me on completion of
course on “PPP in Infrastructure Sector”to the
Indian Railways Institute of Transport Management,
Lucknow. My report may be used by Indian
Railways/IRITM for official purposes.
Date: 14.6.2013
Place : Lucknow (Sanjay Aggarwal)
Dy CMM, Northern Railway
Page 3 of 41
Project Description
The National Highways Authority of India (NHAI), under the Ministry of Road
connecting the four metro cities of New Delhi, Mumbai, Chennai and Kolkata).
NH-8 connecting Delhi to Gurgaon into a 6/8 lane access controlled divided
carriageway.
The then existing 4 lane, 27.7 km section of NH-8 between Delhi and Gurgaon
Passenger Car Units (PCUs)/day in 2000) and non-segregation of traffic that led
pollution.
Construction Ltd to design, finance, construct, operate & maintain the facility
Concessionaire is allowed to collect toll from the users of the project facility
during the operation period to recover his investment and the expressway is
period.
Page 4 of 41
This was the first BOT project in India to have been awarded on negative grant
consideration of robust traffic projections, the selected bidder offered to pay Rs.
The expressway was commissioned in January 2008 after much delay primarily
owing to issues in land acquisition and changes in the scope of work. It carries
Page 5 of 41
PPP Structure of the Project
The project was awarded to the consortium of Jaiprakash Industries Ltd and DS
years. The selected concessionaire offered to pay Rs. 61.06 crore upfront as
The Concessionaire was required to design, construct, operate and maintain the
A Special Purpose Vehicle called the Delhi Gurgaon Super Connectivity Ltd
(formerly Jaypee DSC Ventures Ltd.), was created for execution of the project.
1.2%.
The SPV entered into a fixed time-fixed price Engineering, Procurement &
• NHAI was responsible for undertaking land acquisition and providing the Right
NHAI.
• The shifting of utilities and related expenses was the responsibility of NHAI.
• A loan facility, in case of the revenue falling short of subsistence revenue level,
was made available by NHAI at the State Bank of India Prime Lending Rate.
• The Concessionaire was required to comply with the all the requirements
agencies.
• The Concessionaire was obliged to enter into a state support agreement with
Page 7 of 41
• A performance security was to be paid by the Concessionaire on or before the
date of the Agreement for its due and faithful obligation during the Construction
Period.
Concessionaire is entitled to collect toll from the users of the expressway during
the operation period. The toll is notified by the MoRTH and there is an annual
revision linked to the extent of variation in the WPI. The toll has to be shared
with NHAI if more than 130,000 PCUs are tolled on the expressway.
Page 8 of 41
Current Status
The expressway has been operational since January 2008 and it carries more
than 180,000 PCUs per day, which is much higher than the traffic estimates for
the project by 13,000 to 15,000 PCUs per day. The substantially higher number
of vehicles using the facility has often led to a queuing up of vehicles at the toll
plazas.
and 3 toll-plazas. Smart tags have been introduced to enable cashless automatic
payment.
Page 9 of 41
Financing Information
The funding for the project at the time of financial closure (9 May 2003) is
PARTICULARS AMOUNT
Rs. 200 crore of the debt was provided by the Housing and Urban Development
Mysore (Rs. 30 crore), Punjab National Bank (Rs. 30 crore), Srei International
Finance (Rs. 25 crore) and Jammu & Kashmir Bank (Rs. 15 crore). The SPV
also issued non convertible debentures amounting to Rs. 50 crore to LIC and
The actual cost of the project was eventually Rs. 1,175 crore. The project cost
Limited (EPC contractor) and from the amount received from NHAI (Rs.
Page 10 of 41
Process Analysis
Inception
The plan for an expressway connecting Gurgaon and Delhi was initiated in the
late 1990s and a detailed project report was prepared for the same.
National Highways connecting the four metros under the prestigious Golden
as well as import-export traffic to and from the ports on the Arabian Sea.
and Gurgaon into 8/6 lane access controlled expressway as it was the busiest
part of the highway. It was estimated that the expressway would reduce the
travel time between the Delhi and Gurgaon from about 65 minutes to around 20
minutes.
NHAI was finding itself constrained to fund the estimated Rs. 555 Crore for the
expressway. The risk of cost escalation during the period of construction was
Page 11 of 41
also a cause for concern. Malaysia's Construction Industry Development Board
(CIDB) was initially proposed to take up this project under the memorandum of
However, this proposal sought a grant of Rs. 120 crore from NHAI and was
thus rejected.
The Government of India, at the time, was keen to promote public private
Procurement
The MoRT&H invited pre-qualification bids in 2001. The project was initially
towards the cost of construction for enhancing the viability of the highway
project. However, considering the robust traffic projections, bids were received
with negative grants. In April 2002, the consortium of Jaiprakash Industries and
was the L2 bidder, had quoted Rs 55 crore as the negative grant. Other bidders
were Gamuda Malaysia, IJM Malaysia and Larsen & Toubro (L&T).
Page 12 of 41
Development
The erstwhile Jaypee DSC Ventures Ltd. (now known as Delhi Gurgaon Super
Connectivity Ltd.), the SPV incorporated by the Concessionaire for the project,
In June 2004, Jaiprakash Industries, despite being the lead promoter, sold its
The project development, however, soon ran into issues over approvals, land
acquisition and additions to the scope of work which was largely due to the
environment traversing two states besides having access to both the domestic
and the international airport and sensitive defence establishments along its
route. There were more than 15 government agencies/civic bodies such as the
Delhi Jal Board, the Ministry of Defence, GAIL, BPCL, Delhi Development
by the development of this highway that had to grant various approvals for the
project. This became a complex and time consuming process during the
construction period.
Page 13 of 41
Being in a thickly populated environment, land acquisition became a problem
impacting delivery. This was in fact one of the core obligations of NHAI and
the State Government under the tripartite State Support Agreement entered into
with the concessionaire. NHAI and other agencies involved with this project put
in a great deal of effort to hasten the process. However, there were certain small
parcels of land which were difficult to acquire. In addition, court cases, removal
of trees, shifting of religious structures and the massive number of utilities that
Another major reason for delay in project completion was the change in the
scope of work. There were substantial changes in the original design that were
sought by NHAI and the government keeping in mind future requirements and
entire project length, 9 structures had significant design modifications. Since the
structures were closely spaced, the entire alignment of the project was affected
which necessitated the change of scope and the scheduled project completion
date had to be revised. Demands made by bodies like HUDA and DDA
regarding other connected projects also played a role in the delay. The
provisional change of scope order was finalised and issued to the concessionaire
in July 2005 just days before the original scheduled completion date.
Moreover, with the high density of traffic on the route and the requirement of a
Page 14 of 41
approximately 300 meters (As per the Indian Roads Congress Provisions), the
partial opening of expressway had to be held back for safety reasons even if
Delivery
Exit
The concession period is for 20 years and the projected end date is 11 January
Page 15 of 41
Risk allocation framework
y Period Bearer
acquisition damages of if it
failed to
provide RoW
within the
specified time.
Delays in land
acquisition
resulted in an
increase in the
acquisition cost
for the
government.
They also
Page 16 of 41
resulted in loss
of potential
revenue
accruing to the
Concessionaire
due to delays in
commencement
of operations.
risks Concessionaire
was required to
achieve
financial
closure within
agreement
beyond which
an additional
period of 90
Page 17 of 41
days was
allowed subject
to an advance
weekly
payment of Rs.
1,00,000 per
week as
damages by the
Concessionaire
for delay in
achieving
financial
closure.
Government
was expected to
provide ‘best
effort’ support,
the obligation
was the
Page 18 of 41
Concessionaire’
s.
With multiple
stake holders
involved such
as GoH,
GoNCTD,
DDA, HUDA,
Ministry of
Defence, AAI,
of approvals
was slow.
substantial
changes in the
to escalation in
cost as well as
Page 19 of 41
time over-run.
This meant
revenue loss to
the
Concessionaire
as the
concession
altered.
Risk Concessionaire
failed to
complete the
project
construction by
the scheduled
completion
date, the
agreement
prescribed
Page 20 of 41
weekly
damages at the
rate of 0.01% of
cost.
The
construction of
the expressway
to inordinate
delays in land
acquisition and
changes in the
scope of work.
primarily borne
by the
Concessionaire
and more
specifically by
DS
Page 21 of 41
Constructions
Ltd. as it was
contractor for
change in
scope, NHAI
to contribute the
increased
investment
requirement.
Risk the
concessionaire
NHAI as the
concession
Page 22 of 41
authority has set
stringent
performance
standards and
obligations to
be met.
ut primarily
manifests in
terms of lack of
tollable traffic
in a typical
BOT project is
sector.
However, it has
proven to be
non-existent in
the particular
Page 23 of 41
traffic has so far
been much
projected and is
only expected
to grow.
factor could be
that of the
possibility of a
competing road
facility allowed
to be
constructed by
NHAI,
GoNCTD or
GoH either on
reaching
170,000/day
(continuous for
Page 24 of 41
180 days) or
expiry of 20
years,
whichever is
earlier.
However, this
risk is also
sufficiently
mitigated
through the
allowance of an
increase in the
concession
period (equal to
of years by
which
commissioning
of such
competing road
precedes expiry
Page 25 of 41
of Concession
provision of toll
for the
competing
facility to be
kept higher
(133% of per
km fee) than
that applicable
for the
expressway.
Risks ut result of
adverse
movements in
interest rates,
exchange rates,
private sector is
Page 26 of 41
expected to
manage them
through
appropriate
financial
management
techniques.
risk e condition of
sector assets on
transfer is with
the private
operator.
As per the
agreement, a
joint inspection
shall be
conducted, not
less than 30
Page 27 of 41
months or more
than 36 months
prior to the
expiry of the
concession
period. 2 years
prior to the
expiry, an
amount
equivalent to
for a traffic
volume of
10,000
PCUs/day for
or higher based
on certification
from the
Independent
Consultant
Page 28 of 41
shall be
retained in an
escrow account
for renewal
works.
re event of e Concessionaire
default, NHAI
will pay a
termination
payment equal
to 90% of the
any insurance
claims.
default during
operations
Page 29 of 41
period, NHAI
will pay a
termination
payment equal
due, 120% of
subordinated
debt, 150% of
the equity
subscribed in
negative grant
amount.
Beyond 3 years
from appointed
amount will be
adjusted for
changes in the
Wholesale
Page 30 of 41
this adjusted
amount will be
reduced by
7.5percent
every year
OTHER RISKS
amendments to the
concession agreement so
Similarly, if a change in
Page 31 of 41
crore for the
in the concession
agreement.
closure, before
commencement of
project completion
Page 32 of 41
extended.
of operations, the
extended.
Page 33 of 41
Post facto VfM (Value for Money)analysis
One of the limitations to this analysis is the lack of access to the feasibility
report for the project with which to draw quantitative comparisons. Secondly,
the expressway has been in operation for short period, thus limiting the possible
state-of-the-art facility which was procured on a negative grant basis. It has also
into the Agreement. Moreover, the facility will revert back to the Government
through this PPP model has been sufficiently remunerative for the Government
The following table presents the brief analysis of some of the efficiencies
achieved:
Page 34 of 41
Average Travel Time from Delhi 65 Minutes 25 minutes
to Gurgaon
4 Lane - 22.7
Km
Intersections Intersections
2. Risk of Time and Cost Overruns largely borne by the Private Sector: The
change and time overruns. While NHAI contributed to the increase in cost due
to a scope change, the promoters funded a large portion of the cost overrun by
would have typically been retained by the public sector under public
procurement.
Page 35 of 41
Key Learning and Observations
for providing substantial area of land, prior to actually acquiring the land. Due
to the thickly populated surrounding areas of the expressway, there were certain
pockets of land that were difficult to acquire. This exposed the government to
the risk of not providing the land within reasonable time impacting the overall
such as these were addressed before the project procurement stage itself to
2. Support from Stakeholders for the project: For a project of this magnitude, it
ensure smooth implementation. Public support for land acquisition and road
involvement among the public and reduce resistance leading to delays and other
government agencies made demands for changes in the project alignment and
Page 36 of 41
3. Approvals from multiple entities: More than 15 government agencies/civic
bodies etc., that were affected in one way or other by the development of this
highway, had to grant various approvals for the project. This became a complex
and time consuming process during the construction period. The government
could have provided a single window clearance for a project of this magnitude.
the biggest risk to the viability of a typical toll road project, the risk is
existing highway since traffic flow is more or less established. The Delhi
Gurgaon section of NH-8 has been one of the busiest sections in the country and
to that extent had the advantage of bankable traffic and therefore possible
revenues.
1998 at the time of the project procurement. Thus, the actual traffic volume
unexpected high number of vehicles led to heavy queuing at the toll booths and
delays in traversing the stretch. This appeared to have defeated the very purpose
of the expressway to reduce travel time, fuel cost and congestion making the
Page 37 of 41
6. Fee sharing requiring efficient contract management: The contract has a
provision for sharing of fee realised through toll beyond a threshold daily traffic
level. However, such an approach places greater onus on the government for
and ensure that audited results reflect the true performance of the expressway.
Page 38 of 41
Conclusion
Currently this toll road is handling around 2,00,000 vehicles per day which are
likely to increase to more than 5,00,000 by 2023. The capacity of the road itself
is insufficient to handle such kind of traffic. Hence both the toll road as well toll
In order to solve the congestion and larger public interest, there is no option but
to built parallel connecting routes which are not permitted as of now due to
concessionaire agreement.
Further, the economic cost of the congestion due to congestion due to wastage
will be around 5 crores per month which is increasing on daily basis. The
entity cannot be larger than overall public interest. Sentiments of the investors
may be affected to some extent, however again overall public interest can’t be
ignored.
NHAI also needs to be more careful in planning and estimation of the traffic.
As per TOI reports, 32 lane toll plaza can be bought by paying around 300
option.
Page 39 of 41
Page 40 of 41
References
1. Planning Commission Website
2. Ministry of Finance Website
3. Reports of Times of India
4. Reports of Hindustan Times
5. Reports of Indian Express
Page 41 of 41