TECHNICAL BUILDING- WEEKLY PLAN-South Section

SIM-HHR-01-00
Shut No of
Work
Track down of Man Machine/Equipme Activity
Day Date Location permit Shift Activity Power Notes
Occupation power for nt Name Status
Week type W T S
OCS
TRUCK; LOADER;
Sun 14.05.2017 ISR 10 Out of Track No Permit No 7:00-16:00 EARTHWORKS 3 1 1 ROLLER COMPACTOR; Not Started Team Leader : Rizwan Sakhawak. Tel. 0582867949
WATER TRUCK
20
TRUCK; LOADER;
Mon 15.05.2017 ISR 10 Out of Track No Permit No 7:00-16:00 EARTHWORKS 3 1 1 ROLLER COMPACTOR; Not Started Team Leader : Rizwan Sakhawak. Tel. 0582867949
WATER TRUCK
20

TRUCK; LOADER;
Tue 16.05.2017 ISR 10 Out of Track No Permit No 7:00-16:00 EARTHWORKS 3 1 1 ROLLER COMPACTOR; Not Started Team Leader : Rizwan Sakhawak. Tel. 0582867949
WATER TRUCK
20

TRUCK; LOADER;
Wed 17.05.2017 ISR 10 Out of Track No Permit No 7:00-16:00 EARTHWORKS 3 1 1 ROLLER COMPACTOR; Not Started Team Leader : Rizwan Sakhawak. Tel. 0582867949
WATER TRUCK
20

TRUCK; LOADER;
Thu 18.05.2017 ISR 10 Out of Track No Permit No 7:00-16:00 EARTHWORKS 3 1 1 ROLLER COMPACTOR; Not Started Team Leader : Rizwan Sakhawak. Tel. 0582867949
WATER TRUCK
20