Professional Documents
Culture Documents
IEAR of 800 KV HVDC Bipole Link Raigarh - Pugalur
IEAR of 800 KV HVDC Bipole Link Raigarh - Pugalur
IEAR of 800 KV HVDC Bipole Link Raigarh - Pugalur
FOR
± 800 kV RAIGARH-PUGALUR HVDC BIPOLE
LINK
Southern Region is facing a huge power deficit which is mainly due to (i)
delay/deferment of anticipated generation projects and (ii) non-availability of gas for
existing gas projects in Southern Region. Presently, maximum power demand of
Southern region is about 39,000 MW and faces a deficit of about 3400 MW in spite of
import capacity of about 4920 MW from NEW grid. As per 18th EPS of CEA the
expected power demand of Southern region by the end of XII and XIII plan would be
about 57,200 MW and 82,200 MW respectively. Envisaged generation addition in
Southern region may not meet the requirement and hence power transfer requirement
to Southern Region is expected to increase. Therefore, in view of large deficit and
requirement of transmission system to meet future demands, the implementation of
HVDC link has been proposed with a capacity of 6000 MW. Further, considering
conservation of RoW problem in Kerala and dispersal of power beyond Pugalur,
establishment of VSC based 2000 MW HVDC link between Pugalur and North Trichur
(Kerala) has also been proposed. As decided during the Joint meeting of the Standing
Committee on Power System Planning of Southern Region meeting and Western
Region held on 20th April, 2015, the project shall be built as three separate schemes as
follows:
Southern Region is facing a huge power deficit which has arisen mainly due to – (i)
delay/deferment of anticipated generation projects (for example - Krishnapattam UMPP
(4000 MW), Cheyyur UMPP(4000 MW), Udangudi TPS, IPP projects in Nagapatanam/
Cuddalore area (3000 to 4000 MW), Kundankulam APP (2000MW), Kalpakkam PFBR
(500 MW), East coast project in Srikakulam (1320 MW), Gas based projects in Vemagiri
(about 3000 MW) etc.) and (ii) non-availability of gas for existing gas projects in
Southern Region.
The current maximum power demand of Southern region is about 39,000 MW. As per
18th EPS of CEA, the expected power demand of Southern region by the end of XII and
XIII plan would be about 57,200MW and 82,200MW respectively. Hence power transfer
requirement to Southern Region is expected to increase in coming years.
Therefore, to facilitate the import of power into Southern region and considering the long
distance, it has been proposed that power be transferred over HVDC system along with
the associated A.C Transmission system at 400 kV level. Accordingly, ±800 KV 6000
MW HVDC link with terminals at Raigarh & Pugalur along with VSC based 2000 MW
HVDC link between Pugalur and North Trichur (Kerala) has been proposed. As decided
IEAR for ± 800 kV HVDC Raigarh-Pugalur Bipole Link 1
during the Joint meeting of the Standing Committee on Power System Planning of
Southern Region and Western Region held on 20th April, 2015 the scheme is to be
implemented as three separate schemes.
The present report deals with transmission line to be implemented under Scheme-1 i.e.
± 800 kV Raigarh– Pugalur HVDC Bipole link with 6000 MW capacity. The proposed
system would help in direct supply to Tamil Nadu and Kerala relieving the tie line flow
from NEW grid to Southern region and tie line flow between S1-S2. HVDC with its
control features shall provide flexibility during operation and help in controlling the
power flow on parallel AC lines and provide damping as and when need arises.
The proposed project activities include the survey for finalizing the route alignment and
construction of above bipole line. Lattice towers are erected on designated places using
normal excavation and foundations, thereafter conductors are strung across these using
manual/stringing machines.
The schematic showing the proposed transmission system covered under the subject
IEAR is placed as Exhibit - I.
2.0 The proposed bipole link between Raigarh & Pugalur is a Multi-State one and will pass
through the States of Chhattisgarh, Maharashtra, Andhra Pradesh, Telangana and
Tamil Nadu. The basic environmental settings of these States are delineated below:
2.1 CHHATTISGARH
Chhattisgarh, the 26th State of India, was carved out of Madhya Pradesh on
November 1, 2000. Located in central India it covers an area of 135,191 sq km.
Chhattisgarh is bordered by Bihar, Jharkhand and Uttar Pradesh in the north, Andhra
Pradesh in the south, Orissa in the east and Madhya Pradesh in the west. The State
lies at 17°47'N to 24°06'N latitude and 80°15'E to 84°24'E longitude.
Physiographically, the State can be divided into many divisions. The Indo-Gangetic
plain in the state is very fertile. The Satpura Range, Vindhyachal Mountain Range and
the Maikal Range from the hilly terrain of Chhattisgarh. The Chhota Nagpur Plateau is
another important topographical division of Chhattisgarh. The general land use pattern
of the state is given in Table-2.1:
Climate:
The climate of Chhattisgarh is mainly tropical. It is hot and humid because of its
proximity to the Tropic of Cancer. During the summer which prevails April to middle of
June, the temperature varies from 40°C to 42.5°C. The winter season is mainly felt in
Chhattisgarh during months of December and January and temperature drops up to 10
to 15 °C. Monsoon is experienced during the end of June or July to last week of August.
Rainfall: Rainfall in this state is mainly brought by South West monsoonal winds. The
annual rainfall varies from 1,100 mm to 1,700 mm.
Soil:
The soil of the State is rich and is known for its red color. The soil is in the riverine
plains. The higher areas of the state have light colored soil and the areas adjoining the
river valleys have smooth fertile soil.
The State accounts for more than 13 per cent of India's total mineral production.
Twenty-three per cent of the country's iron- ore deposits, 14 per cent of the dolomite
deposits, and 6.6 per cent of the limestone deposits are found here. It has also 18
percent of coal reserves of the country, and the State is ranked third after Jharkhand
and Orissa. Important minerals and their places of occurrence are given below:
The important rivers of the state are the Mahanadi, the Indravati and the Godavari,
which drains most of the state along with their many tributaries. The other rivers are
Rihand, Sukha, Hasdo, Arpa, Shivnath, Mand, Eb, Jonk, Pary, Kelo, Udanti.
Ecological Resources:
The forest cover of the State based on the Indian State of Forest Report, 2015 is 55,586
Sq. km. which constitutes 44.21% of the geographic area. Out of these 3513 sq. km is
very dense forest and 28,226 sq. km constitutes moderately dense forest and 10,941
sq. km is open forest. As per recorded data, the forest area of the State is 59,772 sq.
km. Reserve Forests constitutes 43.13%, Protected Forests 40.21% and Unclassified
Forests 16.65 %. Further, 7.82% of India's forests are in Chhattisgarh, and 44% of the
State's land is under forests. Identified as one of the richest bio-diversity habitats, has
the densest forests in India, and rich wildlife. Over 200 non-timber forest products, with
tremendous potential for value addition are produced in the state.
The forests are the main source of supply of fodder and fuel and subsistence for the
poorest sections of the people and tribal population in the interior under-developed
areas of the state. The State forest can be broadly classified in to 2 forest type groups:
There are 3 National Parks (NP) and 11 Wildlife Sanctuaries covering an area of
2899.08 km2 and 3760.29 km2 respectively. Thus a total of 6659.37 km2 area
constituting 4.92 % of the State’s geographical area under the protected area network.
The State constitutes of 20.795 million as per the census of 2001 with a population
density of 154 per square kilometer. Agriculture is the main occupation of the people of
Chhattisgarh where nearly 80% of the population is engaged in cultivation. The major
crop grown in Chhattisgarh is paddy especially in the central plains of the State,
popularly known as rice bowl of central India. Apart from paddy other crops grown here
are oilseeds, wheat, coarse grains, groundnut, maize and pulses. The soil of the state is
suitable for the cultivation of horticultural plants guava, mango, banana etc. and a
various types of vegetables. Forests cover nearly 44% of the total area of the state. It is
also rich in mineral resources and about 20 percent of the country’s steel and cement
are produced here. So forest products and mining are the other sources of income. It
has large supply of power which can be easily transmitted to any of the four grids of
India. About 90 percent of the villages in Chhattisgarh have been electrified.
2.2 MAHARASHTRA
Maharashtra, with an area of 307, 713 Sq. km, is the third largest State of the country,
constituting 9.36% of the total geographic area. It lies between latitude 150 35’ and 220
02’ N and longitude 720 36’ and 800 54’ E.
Physiographically, the state can be divided into five regions viz. Deccan Plateau,
Central Highland, Eastern Chotanagpur Plateau, Eastern Ghat and Coastal plain.
Except around Mumbai, and along the eastern limits, the State of Maharashtra presents
a monotonously uniform, flat-topped skyline. This topography of the state is the
outcome of its geological structure. The state area, barring the extreme eastern
Vidarbha region, parts of Kolhapur and Sindhudurg, is practically co-terminus with the
Deccan Traps. The general land use pattern of the State is given in Table 2.2.
Table-2.2 Land use Pattern of Maharashtra
Climate:
The state enjoys a tropical monsoon climate; the hot scorching summer from March
onwards yields to the rainy monsoon in early June. The rich green cover of the
monsoon season persists during the mild winter that follows through an unpleasant
October transition, but turns into a dusty, barren brown as the summer sets in again.
Rainfall: The average annual rainfall varies between 160-200 cms. However, seasonal
rains from the western sea-clouds are very heavy and the rainfall is over 400 cm. on the
Sahyadrian crests. The Konkan on the windward side is also endowed with heavy
rainfall, declining northwards. East of the Sahyadri, the rainfall diminishes to a meagre
70 cm. in the western plateau districts, with Solapur-Ahmednagar lying in the heart of
the dry zone.
Soil:
The soils of Maharashtra are residual, derived from the underlying basalts. In the semi-
dry plateau, the regur (black-cotton soil) is clayey, rich in iron, but poor in nitrogen and
organic matter; it is moisture-retentive. The higher plateau areas have Pather soils,
which contain more gravel. In the rainy Konkan, and the Sahyadri Range, the same
basalts give rise to the brick-red
laterite soil.
Mineral Resources:
Water Resources:
Water is the most precious natural resource of the state, greatly in the demand, and
most unevenly distributed. The major rivers like the Krishna, Bhima, Godavari, Tapi-
Purna and Wardha-Wainganga through its Fluvial action has further aided in the
Ecological Resources:
The recorded forest area of the state is 61,579 km2 which is 20.01% of the
geographical area. The Reserved Forests constitute 84.46%, Protected Forests 10.93%
and Unclassed Forests 8.61% of the recorded forest area. There are six forest types in
the state, viz. Tropical Semi Evergreen, Tropical Moist Deciduous, Tropical Dry
Deciduous, and Tropical Thorn, Subtropical Broadleaved hill and Littoral and Swamp
forests. Maharashtra has 6 National Parks and 42 Wildlife Sanctuaries covering an area
of 8878.04 km2 which constitutes 2.88% of the state's geographical area. There are six
Tiger Reserves, namely, Melghat, Tadoba-Andhari, Sahyadri, Nawegaon-Nagzira, Bor
and Pench covering an area of 2,274.99 km2.
The proposed bipole link shall pass through 2 districts namely Gadchiroli & Chandrapur
districts having forest cover 70.06 % & 35.59 % respectively. However, in spite of taking
due care during route selection, involvement of approx. 338.34 ha forest could not be
avoided. The details of forest resources available in the subprojects districts are as
follows:
Maharashtra’s major industries are chemicals and allied products, textiles, electrical and
non-electrical machinery and petroleum and allied products. Other important industries
are pharmaceuticals, engineering goods, machine tools, steel and iron castings and
plastic ware. The development of offshore oil fields at Mumbai High and the nearby
basins have contributed greatly for the industrial development of the state.
Andhra Pradesh has a geographic area of 160,204 sq. km., which constitutes 8.37% of
the total area of the country. It is situated in the tropical zone and lines between 12 0 40’
and 19050’ N latitude and 760 45’ and 840 40’ E longitude. It is bordered
by Telangana in the north-west, Chhattisgarh in the north, Odisha in the north-
east, Karnataka in the west, Tamil Nadu in the south and the water body of Bay of
Bengal in the east.
Physiographically, the state can be divided into 3 distinct regions viz. (i) the
mountainous region having Nallamalai and Erramalai Hills of the Rayalaseema and the
Eastern Ghats (ii) the plateau having an altitude of 100 m to 800m and (iii) the deltas of
rivers and the sea coast. The general land use pattern of the state is given in Table 2.3.
Climate:
Climate of the State is hot and humid with temperatures ranging from 15 0C to 450C.
Annual rainfall rages from 1,100 to 1,250 mm in the north, reducing to about 500 mm in
the south. The north-eastern areas along the coastline are periodically lashed by
cyclones. Anantapur has a semi-arid climate, with hot and dry conditions for most of the
year. Summers start in late February and peak in May with average high temperatures
around 37 °C range. Anantapur gets pre-monsoon showers starting as early as March,
mainly through north-easterly winds blowing in from Kerala. Monsoon arrives in
September and lasts until early November with about 250 mm (9.8 in) of precipitation. A
Minerals:
Andhra Pradesh is listed top in the deposit and production of mica in India. Minerals
found in the state include limestone, reserves of oil and natural gas, manganese,
asbestos, iron ore, ball clay, fire clay, gold diamonds, graphite, dolomite, quartz,
tungsten, steatitic, feldspar, silica sand. The minerals found in Anantapur district are
Barytes, Calcite, China Clay, Corundum, Dolomite, Felspar, Granite, Iron Ore
(Hematite& Magnetite), Limestone, Ochre, Pyriphyllite, Quartz/Silica, Steatite, Diamond.
Soil:
The State is endowed with a wide variety of soils having less fertile coastal sands to
highly fertile and productive deltaic alluviums of major river basins developed from
different parent materials. . The major soil groups are red and laterites (66%), black (25
%), alluvial (5 %) and coastal (3 %) soils.
Water Resources:
Surface Water: The major rivers of the state are Godavari, Krishna and Pennar, which
pass through the Deccan Plateau and drain into the Bay of Bengal. Nearly 75% of the
state area is covered by the river basins of the Godavari, Krishna and Pennar and their
tributaries. There are 17 smaller rivers like the Sarada, Nagavali and Musi, as well as
several streams.
Ecological Resources:
The recorded forest area is 37,258 sq. km, which constitutes 23.25% of the geographic
area of the State. Reserved forest constitutes 31,959 sq. km (85.77%), protected forest
5,069 sq. km (13.60%) and un-classed forest 230 sq. km. (0.61%). However, total forest
IEAR for ± 800 kV HVDC Raigarh-Pugalur Bipole Link 10
cover in state is 24,424 sq. km comprising of 374 sq. km. very dense forest, 13,093 sq.
km moderately dense forest and 10,424 sq. km. The forests are the main source of
supply of fodder and fuel and subsistence for the poorest sections of the people and
tribal population in the interior under-developed areas of the state. The five forest types
occurring in the state are Tropical Dry Deciduous, Tropical Thorn, Tropical Moist
Deciduous, Tropical Dry Evergreen, and Littoral and Swamp forests.
Protected Areas: There are 13 Wildlife Sanctuaries and 2 National Parks in the State.
The largest Tiger Reserve of the country, Nagarjunasagar-Srisailam spread over 0.36
million ha and the Kolleru Wildlife sanctuary which is a Ramsar site are located in this
State.
The proposed bipole link shall pass through 4 districts namely Kurnool, Kadapa,
Ananthpur & Chittorr districts having forest cover ranging from 3.6% to 26.66%.
However, in spite of taking due care during route selection, involvement of approx.
69.65 ha. forest area could not be avoided. The details of forest resources available in
the subprojects districts are as follows:
District Geographical ( Area in Sq. km) % Forest
Area (km2) Very Dense Mod. Dense Open Total cover
forest forest forest
Kurnool 17658 73 1486 550 2109 11.94
Kadapa 15359 8 2447 1640 4095 26.66
Ananthpur 19130 0 144 545 689 3.6
Chittorr 15151 0 1249 1325 2574 16.99
Source: Indian State of Forest Report 2015
Human and Economic Development:
Andhra Pradesh economy is mainly based on agriculture and livestock. Rice is the
major food crop and staple food of the state. It is an exporter of many agricultural
products and is also known as "Rice Bowl of India". The state is also a largest producer
of eggs in the country and hence, it is nicknamed as "Egg Bowl of Asia". Fisheries
contribute 10% of total fish and over 70% of the shrimp production of India.
The industrial sector of the state includes some of the key sectors
like Pharma, Automobile, Textiles etc. Sricity located in Chittoor district is an integrated
business city which is home to many renowned firms like PepsiCo, Isuzu
Motors, Cadbury India, Kellogg's, Colgate-Palmolive, Kobelco etc. The PepsiCo firm
has its largest plant in India at Sri City. The state is also emerging in information
technology and biotechnology. The development of IT in Tier-II and Tier-III cities
like Vijayawada, Kakinada and Tirupati is also improving. In the fiscal year 2012–2013,
Vijayawada'sITrevenueswere 1,153million (US$18 million)crore. Tirupati with 693million
(US$11 million) and Kakinada with 615 million (US$9.6 million) stand next. For the
benefit of state i.e. after separating Telangana from Andhra, people of Andhra protested
for special status during the month of January in 2017.
2.4 TELANGANA
Telangana is one of the 29 states in India, located in southern India with a geographical
area of 112,077 sq. km., which was formed on 2 June 2014 as the youngest state in
India, from the northwestern part of the joint state of Andhra Pradesh. It lies between
north latitudes 150 48’ and 190 54’ and, east longitudes 770 12’ and 810 50’. It is the
twelfth largest state in India, and the twelfth most populated state in India. Its major
cities include Hyderabad, Warangal, Nizamabad and Khammam. The State is bounded
on the east and south by Andhra Pradesh, on the west by Karnataka and Maharashtra
States and on the north by Maharashtra, Madhya Pradesh, Chhattisgarh and Orissa
States.
Climate:
Telangana is a semi-arid area and has a predominantly hot and dry climate. Summers
start in March, and peak in May with average high temperatures in the 42 °C (108 °F)
range. The monsoon arrives in June and lasts until September with about 755 mm (29.7
inches) of precipitation. A dry, mild winter starts in late November and lasts until early
February with little humidity and average temperatures in the 22–23 °C (72–73 °F)
range.
Minerals:
Soil:
The State has a wide variety of soil viz., Red soil, Laterites and Black Cotton soil. About
60 percent of the state is occupied by red earths with loamy sub-soils covering entire
Nalgonda district, a major part of Mahabubnagar, Warangal, Karimnagar and
Nizamabad districts. Black cotton soil commonly occurs in Adilabad and Nizamabad
districts. Laterite soil occurs in western part of Ranga Reddy and Medak districts.
Water Resources:
Surface Water: Godavari and Krishna are the two principal rivers of the state
Telangana which drain into the Bay of Bengal through Andhra Pradesh. The river
IEAR for ± 800 kV HVDC Raigarh-Pugalur Bipole Link 13
Godavari with its tributaries Pranahita, Manjeera, Maneru, Indravati, Kinnerasani,
Pamuleru and Sileru, flows through the northern parts of the state into Bay of Bengal.
The River Krishna with its tributaries Tungabhadra, Vedhavati, Musi, Paleru and
Munneru flows through the southern parts of the State.
Ecological Resources:
Telangana has 26904 Km2 of notified forest land, which is 23.42% of the geographical
area. In terms of forest canopy density classes, the state has 511 Km2 of Very Dense
forest, 12,313 Km2 Moderately dense forests & 7,455 Km2 Open forest in 2015.
Protected Areas: Telangana has 5 National Parks and 9 Wildlife Sanctuaries covering
an area of 6708.38 km2 which constitutes 5.84% of the state's geographical area. There
are two Tiger Reserves namely Kawal and Amrabad covering an area of 3,059.66 km2.
The proposed bipole link shall pass through 6 districts namely Adilabad, Karimnagar,
Warangal, Ranga Reddy, Nalgonda & Mahaboob nagar districts having forest cover
ranging from 1.14% to 23.2%. However, in spite of taking all precaution during route
selection, involvement of approx. 20.53ha. forest area could not be achieved. The
details of forest resources available in the subprojects districts are as follows:
Rice is major food crop and staple food of the state. Other important crops are maize,
tobacco, mango, cotton and sugar cane. Agriculture has been the chief source of
income for the state's economy.
Several major manufacturing and services industries are in operation mainly around
Hyderabad. Automobiles and auto components industry, spices, mines and minerals,
textiles and apparels, pharmaceutical, horticulture, poultry farming are the main
industries in Telangana. In terms of services, Hyderabad is usually nicknamed as
Cyberabad due to its information technology foray and location of major software
industries in the city. Prior to secession, it contributed 10% to India's and 98% to Andhra
Pradesh's exports in IT and ITES sectors last 2013. With Hyderabad as in the front line
of Telangana's aims to promote information technology in India, the city boasts the
HITEC City as its premier hub. The state government is in the process of developing
Industrial Parks at different places, for specific groups of industries. The existing parks
are Software Park at Hyderabad, HITEC City for software units, Apparel Park at
Gundlapochampalli, Export Promotion Park at Pashamylaram, Bio-technology park at
Turkapally.
Tamil Nadu is situated on the south eastern side of the Indian peninsula. It is bounded
on the east by Bay of Bengal, in the south by the Indian Ocean, in the west by the
states of Kerala and Karnataka and in the north by the Karnataka and Andhra Pradesh.
Tamil Nadu has a geographic area of 130,058 sq. km, which constitutes 3.96% of the
land area of the country. It lies between 08°04’ N and 13°34’ N latitude and 76°14’E
and 80°21’E longitude.
Physiographically, the state can be divided into two natural divisions: the eastern
coastal plain and the hilly region along the north and the west. Along the whole length of
the western part, at a distance from the sea varying from 80 to 160 km runs the range of
the Western Ghats, a steep and rugged mass averaging 1220 meters above the sea
level and rising to 2440 metres at the highest point. The slopes of the Western Ghats
are covered with heavy evergreen forests. The Nilgiris and the Anamalai are the hill
groups with the maximum height. The general land use pattern of the state is given in
Table 2.5.
IEAR for ± 800 kV HVDC Raigarh-Pugalur Bipole Link 15
Table 2.5: Land use Pattern
Climate:
The climate of Tamil Nadu is characterized as tropical with little variation in summer and
winter temperatures. The hottest period is April-June, with the temperature rising up to
40°C. November-February is the coolest period with average temperature hovering
around 20°C. Tamil Nadu gets its rain from North-East Monsoons between October and
December. The average annual rainfall in Tamil Nadu ranges between 635-1905 mm.
The coastal region of Tamil Nadu becomes uncomfortably warm and humid during
summers; however, nights are cool and pleasant due to sea breezes.
Minerals:
Tamil Nadu is the leading holder of country's resources of vermiculite, magnetite,
dunite, rutile, garnet, molybdenum and ilmenite. The State accounts for the country's
81% lignite, 75% vermiculite, 69% dunite, 59% garnet, 52% molybdenum and 30%
titanium minerals resources. Important minerals and their places of occurrence are
given below:
Soil:
The major soil groups of Tamil Nadu are Red soil (62%), Black soil (12%), Laterite soil
(3%) and Coastal soil (7%). As per USDA system of soil classification, the soils of Tamil
Nadu are divided into six orders, out of which around 50% of total area of Tamil Nadu is
occupied by Inceptisol followed by Alfisols, which occupy 30% of total state area.
Vertisols cover around 7% of total state’s area, Entisols cover 6% and Ultisols cover 1%
of total area. Mollisols cover negligible area of Tamil Nadu.
Water Resources:
Surface Water: The total surface water potential of the state is 24864 Million Cubic
Metres (MCM). There are 17 major river basins in the State with 61 reservoirs and
about 41,948 tanks. Of the annual water potential of 46540 MCM, surface flows account
for about half. The rivers of the state flow eastward from the Western Ghats and are
entirely rain-fed. The 760 kms long Kaveri River is the longest river of Tamil Nadu. This
river is popularly called the "Ganga of the South" or the "Dakshina Ganga" and divides
the state in two halves. The other important rivers of the state are Palar, Cheyyar,
Ponniyar, Meyar, Bhavani, Amaravati, Vaigai, Chittar and Tamaraparni, Noyil, Suruli,
Gundar, Vaipar, Valparai and Varshali.
Groundwater: The utilizable groundwater recharge in the state is 22,423 MCM. The
current level of utilization expressed as net ground water draft of 13.558 MCM is about
60 percent of the available recharge, while 8875 MCM (40 percent) is the balance
available for use. Over the last five years, the percentage of safe blocks has declined
IEAR for ± 800 kV HVDC Raigarh-Pugalur Bipole Link 17
from 35.6 per cent to 25.2 percent while the semi-critical blocks have gone up by a
similar percentage. Over-exploitation has already occurred in more than a third of the
blocks (35.8 percent) while eight blocks (2 percent) have turned saline. The water level
data reveals that the depth of the wells ranges from an average of 0.93 metres in
Pudukottai district to 43.43 metres in Erode. According to the Central Groundwater
Board, there has been a general decline in groundwater level in 2003 due to the
complete de-saturation of shallow aquifers.
Ecological Resources:
Forest: The recorded forest area is 22,877 sq. km which constitutes 17.59% of the
geographic area of the State. According to legal status, Reserved Forests constitute
88.70%, Protected Forests constitute 7.79% and Un-classed Forests constitute 3.5% of
the total forest area. Tamil Nadu’s forests are largely deciduous and thorn types. In
terms of forest canopy density classes, the State has 2,814 sq. km of very dense forest,
8,069 sq. km of moderately dense forest and 6,482 sq. km of open forest.
Protected Areas: Tamil Nadu has 5 National Parks and 29 Wildlife Sanctuaries
covering an area of 6464.97 km2 which constitutes 4.97% of the state's geographical
area. There are four Tiger Reserves namely Kalakad-Mundanthurai, Anamalai,
Mudumalai and Sathyamangalam covering an area of 2968.08 km2.
The proposed bipole link shall pass through 6 districts namely Vellore, Krishnagiri,
Dharmapuri, Salem, Namakkal & Karur districts having forest cover ranging from 4.17%
to 34.09%. However, in spite of taking due care during route selection, involvement of
forest area 11.04 ha. approx. could not be avoided. The details of forest resources
available in the subprojects districts are as follows:
Tamil Nadu has achieved reasonable economic growth in past few years. With a
population of around 7, 21,47,030 as per 2011 census, it is one of the populous states
of India. The population density is 555 per square km, which is higher than the National
Average. The sex ratio of the state is healthy 996 females per 1000 males, which is
better than the corresponding National figure. People belonging to Schedule Castes
constitute around 20% of total population, whereas, share of people belonging to
Schedule Tribes is a miniscule 1.1%. The state enjoys a reasonably good literacy rate
of 80.09% which is better than National Average of 74.04%. The Human Development
Index of the state is 0.570, which also compares favorably with National Average of
0.467.
Agriculture is the main source of livelihood with around 5139832 ha of area under
cultivation. Paddy is the main crop. It is raised in three crops. The first crop is known as
'Kuruvali' ( the short term crop) with a duration of three and a half to four months from
June - July to Oct-Nov. The second crop called 'Thaladi' has duration of 5 to 6
months Oct -Nov to Feb -March. Third is 'Samba '(the long term) crop and has a
duration of almost 6 months from Aug to January. Chief sources of irrigation are the
rivers tanks and wells. Other major food crops are jowar, ragi, bajra, maize and pulses.
Cotton, sugarcane, coconut, tea and coffee as well as a number of horticultural
products like bananas and mangoes are cash crops while ground nuts, sesame, sun
flower are important oil seeds crops.
Major Industries in Tamil Nadu are cotton, heavy commercial vehicles, auto
components, railway coaches, power pumps, leather tanning industries, cement, sugar,
paper, automobiles and safety matches. Global auto majors Hyundai Motors, Ford,
Hindustan Motors and Mitsubishi have commenced production plants. Ashok Leyland
and TAFE have set up expansion plants in Chennai. The state is an important exporter
of tanned skin and leather goods, yarn, tea, coffee, spices, engineering goods, tobacco,
handicrafts and black granite. Tamil Nadu contributes to 60 per cent of the tannery
industry in India.
In recent times knowledge based industries like I.T. and Biotechnology have become
the thrust area in the industrial scene in Tamil Nadu. TIDEL, a software technology
park, has been established in Tharamani, Chennai. The software exports from the State
during the year 2012-13 is expected to be around Rs. 50,000 crores with an impressive
growth rate of more than 10%. Top I.T. and Telecom companies such as Nokia,
Motorola, Foxcon, Flextronic and Dell have commenced production. Handloom is
another important cottage industry. Silk sarees of Kancheepuram are famous all
over India. Cottage units produce cotton sarees, dhoties, towels and lungies.
"The State shall endeavour to protect and improve the environment and to
safeguard the forests and wildlife of the country". (Article 48A)
"It shall be the duty of every citizen of India to protect and improve the natural
environment including forests, lakes, rivers and wildlife and to have compassion
for living creatures”. {Article 51A (g)}
Article 21 of the constitution provides, “no person shall be deprived of his life or
personal liberty except according to procedure established by law”.
Article 21 is the heart of the fundamental rights and has received expanded meaning
from time to time after the decision of the Supreme Court in 1978. The Article 21
guarantee fundamental right to life – a life of dignity to be lived in a proper environment,
free of danger of disease and infection. Recently, Supreme Court has broadly and
liberally interpreted the Article 21, transgressing into the area of protection of
environment, and held the protection of environment and citizen’s right to live in eco-
friendly atmosphere as the basic right guaranteed under Article 21.
Thus the Indian Constitution has now two fold provision:
(a) On the one hand, it gives directive to the State for the protection and
improvement of environment.
(b) On the other hand the citizens owe a constitutional duty to protect and improve
natural environment.
Fifth Schedule
Special provisions have been extended to the Tribal Areas of 9 States including
Chattishgarh, Maharashtra, Andhra Pradesh, Telangana under the 5th Schedule
[Articles 244(1)] of the Constitution of India that provide several types of safeguards to
the tribal communities.
Fifth Schedule deals with administration and control of scheduled areas where tribal
communities are in a majority and Tribal Advisory Councils (TACs) are constitutional
When transmission projects pass through forest land, clearance has to be obtained from
relevant authorities under the Forest (Conservation) Act, 1980. This Act was enacted to
prevent rapid deforestation and environmental degradation. State governments cannot
de-reserve any forest land or authorize its use for any non-forest purposes without
approval from the Central government. POWERGRID projects, when involving forest
areas, undergo detailed review and approval procedures to obtain a Forest Clearance
certificate from Ministry of Environment Forest & Climate Change (MoEFCC), GoI
before starting any construction activity in designated forest area.
Environmental Clearances under Environment (Protection) Act,1986:
Since transmission line projects are environmentally clean and do not involve any
disposal of solid waste, effluents and hazardous substances in land, air and water they
are kept out of the purview of Environment (Protection) Act, 1986 (EPA). However,
amendment in the Environment (Protection) Act, 1986 on 7th May’ 1992 made it
necessary to obtain clearance from MoEFCC for power transmission projects in three
districts in the Aravalis (viz., Alwar in Rajasthan and Gurgaon & Nuh-Mewat in
Haryana). The Aravali range, in these areas, is heavily degraded; hence, any industrial
activity there becomes critical. Environment Impact Notification, 1994 & 2006 lays down
specific project categories that require clearance from MoEFCC Power transmission
projects are not included in this list.
MoEFCC vide its notification dated 17th July, 2000 under the section of 6, 8 and 25 of
the Environment (Protection) Act, 1986 has notified rules for regulation /control of
Ozone Depleting Substances under Montreal Protocol adopted on 16th September
1987. As per the notification certain control and regulation has been imposed on
manufacturing, import, export and use of these compound. POWERGRID shall follow
provisions of notification and phase out all equipments which uses these substances
and planning to become a CFC free organization in near future.
Batteries (Management and Handling) Rules, 2001:
MoEFCC vide its notification dated 16th May, 2001 under the section of 6, 8 and 25 of
the Environment (Protection) Act, 1986 has put certain restriction on disposal of used
batteries and its handling. As per the notification, it is the responsibility of bulk consumer
IEAR for ± 800 kV HVDC Raigarh-Pugalur Bipole Link 21
(POWERGRID) to ensure that used batteries are not disposed of, in any manner, other
than by depositing with the dealer/manufacturer/registered recycler/importer/
reconditioner or at the designated collection centres and to file half yearly return in
prescribed form to the concerned State Pollution Control Board.
Hazardous Wastes (Management, Handling & Transboundary Movement) Rules,
2008 :
Vide notification dated 24th September, 2008 under the EPA, 1986, MoEFCC notified
rules for environmentally sound management of hazardous wastes to ensure that the
hazardous wastes are managed in a manner which shall protect health and the
environment against the adverse affects that may result from such waste. The used
transformer oil has been declared as hazardous wastes vide this notification. As per the
notification, all used oil is to be auctioned/sold to registered recyclers only and file
annual return on prescribed form to the concerned State Pollution Control Board.
This act recognizes and vests the forest rights and occupation in forest land to forest
dwelling Scheduled Tribes and other traditional forest dwellers who have been residing
in such forests for generations but whose rights could not be recognized.
The definitions of forest dwelling schedule tribes, forestland, forest rights, forest villages,
etc. have been included in Section 2 of the Act. The Union Ministry of Tribal Affairs
(MoTA) is the nodal agency for implementation of the Act while field implementation is
the responsibility of the government agencies. Its implementation has also been linked
with forest clearance process under Forest (Conservation) Act, 1980 w.e.f. August 2009
by MoEFCC. POWERGRID shall abide by the provisions of the act if any portion of the
transmission line is passing through forest land, in occupation of the forest dwelling
IEAR for ± 800 kV HVDC Raigarh-Pugalur Bipole Link 22
scheduled tribes and other traditional forest dwellers for laying of transmission lines.
However, for linear projects including transmission lines obtaining of NoC from the gram
sabhas has been exempted for the requirement of FRA compliance as per MoEF
circular dated 5th February 2013.
ADB’s Safeguard Policy Statement (SPS), June 2009 describes Bank Policy and
operational procedures on three key safeguard areas viz. Environmental, Involuntary
resettlement and Indigenous People. With respect to environment it prescribes a set of
specific safeguard requirements that borrowers are expected to meet during operations
when addressing environment impacts and risks. Its objective is to ensure
environmental sustainability of projects through avoidance, minimization, mitigation
and/or compensation of adverse impacts on environment and to support the integration
of environmental considerations into the project decision-making process.
3.2 SOCIAL
The act has a provision for notifying transmission company under section 164 (B) to
avail benefits of eminent domain provided under the Indian Telegraph Act, 1885. MoP,
GoI vides gazette notification dated 23rd Dec’03 had already notified POWERGRID
under this section of said act. Therefore, for the purpose of placing of any wires, poles,
etc., POWERGRID has all the powers that the telegraph authority possesses. Thus,
POWERGRID can erect and construct towers without actually acquiring the land.
However, all damages due to POWERGRID activity are compensated at market rate.
Power transmission schemes are always planned in such a way that the power of
eminent domain is exercised responsibly.
This policy covers direct economic and social impacts both resulting from Bank-assisted
investment projects and are caused by the involuntary taking of land. To avoid or
minimize involuntary resettlement and, where this is not feasible, assist displaced
persons in improving or at least restoring their livelihoods and standards of living in real
terms relative to pre-displacement levels or to levels prevailing prior to the beginning of
project implementation, whichever is higher.
This policy contributes to the Bank's mission of poverty reduction and sustainable
development by ensuring that the development process fully respects the dignity,
human rights, economies, and cultures of Indigenous Peoples. The objective is to
design and implement projects in a way that fosters full respect for indigenous peoples
1
Ministry of Power, Govt. of India vide its notification dated 15 th Oct., 2015 has issued guidelines for payment of
compensation for damages in regard to RoW for transmission lines. Once the above guidelines are adopted by
respective States, compensation shall be paid as per the norms.
IEAR for ± 800 kV HVDC Raigarh-Pugalur Bipole Link 25
so that they receive culturally compatible social and economic benefits, and do not
suffer adverse effects during the development process. The project shall ascertain
broad community support for the project based on social assessment and free prior and
informed consultation with the affected Tribal community, if any.
For selection of optimum route, the following points are taken into consideration:
(i) The route of the proposed transmission lines does not involve any human
displacement/rehabilitation.
(ii) Any monument of cultural or historical importance is not affected by the route of the
transmission line.
(iii) The proposed route of transmission line does not create any threat to the survival of
any community with special reference to Tribal Community.
(iv) The proposed route of transmission line does not affect any public utility services
like playgrounds, schools, other establishments etc.
(v) The line route does not pass through any National Parks, Sanctuaries etc.
(vi) The line route does not infringe with area of natural resources.
In order to achieve this, POWERGRID undertakes route selection for individual
transmission line in close consultation with representatives of concerned Forest
Department and the Department of Revenue. Although under the law, POWERGRID
has the right of eminent domain yet alternative alignments are considered, keeping in
mind, the above-mentioned factors during site selection, with minor alterations often
added to avoid environmentally sensitive areas and settlements at execution stage.
As a rule, alignments are generally cited away from major towns, whenever
possible, to account for future urban expansion.
Similarly, forests are avoided to the extent possible, and when it is not possible, a
route is selected in consultation with the local Divisional Forest Officer, that causes
minimum damage to existing forest resources.
Alignments are selected to avoid wetlands and unstable areas for both financial
and environmental reasons.
Three different alignments (Map-2) were studied with the help of published data/maps
and walkover survey to arrive at most optimum route for detailed survey. The
comparative details of three alternatives in respect of the proposed line are as follows:
Andhra Pradesh
Andhra Pradesh & Andhra Pradesh &
& Telangana - Telangana - Telangana -
Adilabad, Adilabad, Adilabad,
Karimnagar, Karimnagar, Karimnagar,
Warangal, Ranga
Warangal, Ranga Warangal, Ranga
Reddy, Nalgonda,
Reddy, Nalgonda, Reddy, Nalgonda,
Mahaboob nagar,
Mahaboob nagar, Mahaboob nagar,
Kurnool, Kadapa,
Kurnool, Kadapa, Kurnool, Kadapa,
Ananthapur, Ananthapur, Ananthapur, Chittorr,
Chittorr, Chittorr,
Tamil Nadu Tamil Nadu Tamil Nadu
Vellore, Krishnagiri,
Vellore, Krishnagiri, Vellore, Krishnagiri,
Dharmapuri Dharmapuri Dharmapuri
Salem, Namakkal,
Salem, Namakkal, Salem, Namakkal,
Karur Thiruchirapalli, Thiruchirapalli, Karur
Karur
ii. House within RoW Very few to negligible Moderate Moderate
From the comparative analysis of three alternative routes, it is evident that Alternative-I
is found to be most suitable due to less forest area involvement and also passing
through mostly plain terrain with less numbers of river, railway and highway crossing as
compared to Alternative-II & III. This route involves minimum tree felling & lesser degree
of environmental impacts is anticipated. Hence, Alternative - I is considered as the most
optimum route and recommended for detailed survey.
(i) Resettlement
Land is required for a) construction of substations and b) erection of transmission lines.
In general requirement of land area for substation varies from 30 to 100 acres
depending upon voltage levels, no. of bays, topography of land and other technical
parameters.
The present scope of work covered under the subject IEAR doesn’t involve construction
of any new substations. Since no fresh land acquisition is involved, R & R will not be an
issue in the instant project
In respect of (b), no permanent acquisition is envisaged. Land for tower and right of way
is not acquired as agricultural activities can continue. A typical plan of transmission line
tower footing indicating the above position along with extent of damage and area of
influence are depicted in Fig.- 1 & 1 a respectively. As described earlier all measures
are undertaken by POWERGRID at the line routing stage itself to avoid settlements
such as cities, villages etc. It may be seen from the above description of proposed route
alignments and also keeping in mind that no permanent acquisition of land is involved
for tower foundation as per existing law, these subprojects don’t require any
resettlement of villagers. However, some temporary damages/ disturbances can
happen, which will be compensated as per the law of the land and applicable/prevailing
guidelines.
(ii) Land value depreciation
Based on past experience land prices are generally expected to rise in the areas
receiving power. Generally transmission lines pass through uninhabited area,
Transmission lines can serve as new access routes into previously inaccessible or
poorly accessible forests, thereby accelerating forest and wildlife loss. In such cases,
POWERGRID cannot take action itself, but local Forest Department personnel will
normally assess the dangers and take appropriate action, such as establishing guard
stations at the entrance to the forest etc. cost of which is borne by POWERGRID. Given
the already easy access and degraded conditions at the proposed subproject area, this
problem is not expected to be encountered. Nonetheless, POWERGRID staff will report
to the Forest Department any noticeable encroachment induced by the Projects
2
Environment Management Plan (EMP) is placed at Table -6.1
IEAR for ± 800 kV HVDC Raigarh-Pugalur Bipole Link 33
(v) Lines into other valuable lands
Impacts on agricultural land will be restricted to the construction phase and when large-
scale maintenance measures are required. The proposed transmission lines will pass
mostly through agricultural fields. As per existing law, land for tower and right of way is
not acquired and agricultural activities are allowed to continue after construction activity.
POWERGRID pays compensation for all damages as per the law of the land and
applicable/prevailing guidelines. Recently, MoP has issued guidelines for payment of
compensation toward damages in regard to RoW for transmission lines (Annexure-1).
However, the said compensation shall be paid to all affected farmers/land owners in
addition to normal tree and crop damage compensation, once it is adopted by
respective States.
In areas where transmission lines will traverse through agricultural land, compensation
will be paid to owners for any crop damage incurred as a result of construction activities.
POWERGRID field staff will consult affected villagers and local revenue dept. and
apprise them about the project and tower location, which shall be erected in the
agricultural land. Revenue dept. after evaluating the land loss due to construction
activity and crop damages based on productivity of land arrives at the compensation
cost which is paid to farmer. Agricultural activities will be allowed to continue following
the construction period. If bunds or other on-farm works are disturbed during
construction or maintenance, they will be restored to the owner's satisfaction following
cessation of construction or maintenance activities. In the event that private trees are
felled during construction or maintenance operations, compensation will be paid to the
owner in an amount determined by the estimated loss of products from the tree over an
eight year period (for fruit bearing trees). Agricultural lands under private ownership will
be identified, and in accordance with normal POWERGRID procedures compensation
will be paid to the affected villagers. The procedure for providing compensation is
described in Annexure-2. Budgetary provision of Rs. 84.30 Crores is made in the cost
estimate to meet these expenses.
(vi) Interference with other utilities and traffic
As per regulations enacted by Government of India, it is mandatory for POWERGRID to
seek clearance prior to construction from department of Railways, Telecommunications
and wherever necessary from aviation authorities that are likely to be affected by the
construction of transmission lines. The transmission lines affect nearby
telecommunication circuits by causing electrical interference. A standing committee -
Power Telecom Co-ordination Committee (P.T.C.C.) has been constituted by
Government of India to plan and implement the mitigating measures for the induced
voltage which may occur to nearby telecom circuit and suggest necessary protection
measures to be adopted. The committee suggests measures like rerouting of the
telecom circuits, conversion of overhead telecom circuits into cables etc. to minimize the
interference.
The cost of such measures is determined by the Committee on the basis of prevailing
norms and guidelines. Though the exact cost to mitigate the impacts of induction in
neighboring telecom circuits would vary from case to case, the cost on an average
works out to be Rs. 50,000/- per km. Provision to meet these expenses has been made
in the cost estimate for the same for transmission line proposed under the instant
scheme.
Wherever transmission line crosses the railways, clearance is taken from that
department. In general, the system is planned and executed in such a way that
adequate clearance is maintained between transmission lines on the one hand, and
IEAR for ± 800 kV HVDC Raigarh-Pugalur Bipole Link 34
railways, civil aviation and defense installations on the other. Wherever the
transmission lines pass near to airports, the towers beyond specified height are painted
in alternate orange and white stripes for easy visibility and warning lights are placed
atop these towers.
(vii) Interference with drainage pattern
As the transmission lines are constructed aerially and the blockage of ground surface is
limited to area of tower footings, which is very small, there is little possibility of affecting
drainage pattern. However, management measures as specified in EMP (refer clause -
5 & 12) like appropriate siting of towers shall be undertaken during detailed alignment
survey and design to avoid any incidence of flooding hazards of loss of agricultural
production due to interference with drainage patterns or irrigation channels. In the
infrequent instances where the natural flow/drainage is affected, flow will be trained and
guided to safe zones.
5.1 ENVIRONMENTAL PROBLEMS DUE TO DESIGN
(i) Escape of polluting materials
The equipments installed on lines and substations are static in nature and do not
generate any fumes or waste materials. However, detailed specification with respect to
equipment design has been included in tender document to avoid any incidence of land
and water contamination. Apart from this, solid waste like packing materials, cables,
aluminium conductor, sand, aggregate material, cements and steel generated during
construction is carefully handled and removed from site.
(ii) Explosion/fire hazards
During the survey and site selection for transmission lines, it has been ensured that
these are kept away from oil/gas pipelines and other sites with potential for creating
explosions or fires. Fires due to flashover from lines can be a more serious problem in
forest. However, adequate safety measures shall be taken to avoid such incidence and
has been included in EMP (refer clause - 15, 23 & 52). Besides, forest authorities also
incorporate measures like making fire lines to prevent spreading of fire in the affected
forest area. Apart from this, states of art safety instruments are installed in the
substations on both the ends so that line gets tripped within milliseconds in case of any
fault.
(iii) Erosion hazards due to inadequate provision for resurfacing of exposed area
The volume of soil excavated in the construction of transmission lines vary significantly
depending upon several factors including wind zone, type of towers, type of foundation,
topography of the land etc. It is estimated quantity of soil excavation for construction of
proposed ± 800KV line would be approximately 4,72,500 m3. However, most of these
excavated materials (about 80-90%) will be used for re-filling after construction work is
over and remaining materials will be disposed properly as detailed out in EMP(refer
clause - 25, 26 & 28). Moreover, the topsoil disturbed during the development of sites
will be stored properly and used to restore the top surface of the platform. Left over
infertile and rocky material will be dumped at carefully selected dumping areas and
used as fill for foundations and leveling. Further, excavation in the hilly areas is avoided
in rainy days. In hill slopes and erosion prone soils, internationally accepted engineering
practices including bio-engineering techniques, wherever, feasible shall be undertaken
to prevent soil erosion. Hence, possibility of erosion of exposed area due to construction
activity is negligible.
(iv) Environmental aesthetics
Since spacing between the towers in case of ± 800 kV transmission lines is approx. 400
meters, there will be no adverse affect on the visual aesthetics of the localities
POWERGRID will follow all applicable standards concerned with safety for transmission
and erection of Substation. These include IS: 5613 – recommendation on safety
procedures and practices in electrical work as per CEA (Measures relating to Safety
and Electric Supply) Regulation, 2010 notified in the Gazette on 20th Sept. 2010
(Annexure-3). Apart from this, safety precaution like barricading of work area with
reflective tape/illumination and placement of visible signage shall be undertaken to
avoid any unforeseen incident. Furthermore, speed restrictions are imposed on project
vehicles in project/habitation areas. Moreover, the construction activities associated with
transmission line projects are not so extensive and only limited excavation is involved in
tower foundations. As such, the volume of traffic and movement of construction vehicles
laden with construction materials is quite limited and don’t pose any safety hazards for
local population as well as increase in road accidents.
All health and safety issues and its management aspects are integral part of
project/contract specific safety plan (Annexure-4) which is also part of contract
condition. Various aspects such as work and safety regulations, workmen's
compensation, insurance are adequately covered under the General Conditions of
Contract (GCC), a part of bidding documents. Project is executed as per the approved
plan and is regularly monitored by dedicated Safety personnel. Moreover, for strict
compliance of safety standard/plan a special provision as a deterrent has been added in
the contract which provides for a heavy penalty of Rs.10 lakhs for each accidental death
and Rs1.0 lakh/each for any injury and is deducted from the contractor’s payment and
paid to the deceased/affected family (Annexure – 5).
POWERGRID maintains safety as a top priority and has framed guidelines/checklist for
workers’ safety as its personnel are exposed to live EHV apparatus and transmission
IEAR for ± 800 kV HVDC Raigarh-Pugalur Bipole Link 37
lines. These guidelines/checklists include work permits and safety precautions for work
on the transmission line and substation both during construction and operation
(Annexure-6) and is regularly monitored by site in-charge. In addition training is
imparted to the workers in fire fighting and safety measures. Standard safety tools like
helmet, safety belt, gloves etc. are provided to them in accordance to the provisions of
Safety Rules. First aid facilities will be made available with the labour gangs, and
doctors called in from nearby towns when necessary. The number of outside (skilled)
labourers will be quite small, of the order of 25-30 people per group and remaining
workforce of unskilled labourers will be comprised of mostly local people. As per
policy/norms preference shall be given to the eligible local labor having required skills a
specific clause has been incorporated in contract conditions (refer clause- 22.2.1 of
GCC) for compliance of same by Contractor. Workers are also covered by the statutory
Workmen (Compensation) Act. Regular health checkups are conducted for construction
workers. The construction sites and construction workers’ houses will be disinfected
regularly, if required. In order to minimize/checking of spread of socially transmitted
diseases e.g. HIV/AIDS etc. POWERGRID will conduct awareness building programs
on such issues for the construction workers.
From the above, it is evident that values of Electric and Magnetic Field are well within
the limits prescribed by ICNIRP for continuous exposure. Since, residential areas are
mostly avoided during routing of line, the chances of continuous exposure are remote
Complete project plan (i.e. its route and terminating point and substations, if any,
in between);
Design standards in relation to approved international standards;
Health impacts in relation to EMF;
Measures taken to avoid public utilities such as school, hospitals, etc.;
Other impacts associated with transmission lines and POWERGRID approach to
minimizing and solving them;
Trees and crop compensation process.
In the instant project also, many group meetings were organized (informally and
formally) in all villages where the interventions are likely to happen. Such consultation
culminated in public meeting organized at different locations as provided in Table- 5.3.
These meetings were attended by Gram Panchayat leaders/members, Village heads,
interested villagers/general public and representatives from POWERGRID. Village
women folk also actively participated in consultation. To ensure maximum participation,
prior intimation in local language was given and such notices were also displayed at
prominent places/panchayat office etc. During the public consultation details of line and
its importance were explained to the villagers by the officials of POWERGRID. The
consultation was arranged in interactive manner in local language and queries like
crop/land compensation, engagement employment opportunities, health & safety,
improvement of power scenario & infrastructure in region etc. were addressed. The
initiative was appreciated by the villagers and they assured their cooperation for
construction of the said lines. The process of such consultation shall continue during
different stage of project implementation and even during O& M stage. Details of above
public consultation meetings including public notice, list of participants, photographs and
public queries & answers are enclosed as Annexure -9.
5.6 CONCLUSIONS:
It is clear from the above assessment/studies that the project area is moderately rich in
natural forest resources as well as protected areas. Though careful route selection have
completely avoided protected areas but in spite of taking all precautions involvement of
some forest couldn’t be achieved in line route due to geographical constraint and
location of substations/load centers. However, the route is so aligned that it involves
minimum forest area, which will minimize vegetation loss and other environment
impacts. Moreover, with implementation of various management measures as listed in
EMP, it is envisaged that intensity of possible impacts shall be nullified to the extent
possible. Besides, implementation of such high voltage transmission line with a power
transfer capacity of 6000MW in a single corridor will have wide influence in minimizing
environmental and social impact through optimizing of RoW and conservation of
precious resources like forest and land. The above facts while on the one hand
underline the need for implementation of the subject project for overall development of
the area and on other hand suggests that a detailed EIA may not be necessary due to
negligible and manageable impact of transmission line.
Monitoring is a continuous process for POWERGRID projects at all the stages be it the
site selection, construction or maintenance.
The success of POWERGRID lies in its strong monitoring systems. Apart from the site
managers reviewing the progress on daily basis regular project review meetings are
held at least on monthly basis which is chaired by Executive Director of the region
wherein apart from construction issues the environmental aspects of the projects are
discussed and remedial measures taken wherever required. The exceptions of these
meetings are submitted to the Directors and Chairman & Managing Director of the
Corporation. The progress of various on-going projects is also informed to the Board of
Directors. Flow chart showing institutional arrangement for implementation ESPP is
placed as Exhibit-2. A three tier support structure has also been developed at
corporate, regional and site level with following functions for effective implementation of
environment and social safeguard measures.
6.1.1 Corporate Level
An Environmental Management Cell at corporate level was created within
POWERGRID in 1992 and subsequently upgraded to an Environment Management
Department (EMD) in 1993 and in 1997 it has been further upgraded to Environment &
Social Management Deptt. (ESMD) by incorporating social aspect of project. Briefly, the
ESMD's responsibilities are as follows:
Advising and coordinating RHQs and Site to carry out environmental and social
surveys for new projects;
Assisting RHQs and site to finalize routes of entire power transmission line
considering environmental and social factors that could arise en-route;
Help RHQs and Site to follow-up with the state forest offices and other state
departments in expediting forest clearances and the land acquisition process of
various ongoing and new projects;
Act as a focal point for interaction with the MoEFCC for expediting forest clearances
and follow-ups with the Ministry of Power;
Imparts training to POWERGRID’s RHQs & Site Officials on environment and social
issues and their management plan.
6.1.2 Regional Level
At its Regional Office POWERGRID has a Environmental and Social Management Cell
(ESMC) to manage Environmental and Social issues and to coordinate between ESMD
at the Corporate level and the Divisional Headquarters. The key functions envisaged for
ESMC are:
Advising and coordinating field offices to carry out environmental and social surveys
for new projects envisaged in the Corporate Investment Plan;
Assisting the ESMD and site to finalize routes of entire power transmission lines
considering the environmental and social factors that could arise en-route;
To follow-up forest clearances and land acquisition processes with state forest
offices and other state departments for various ongoing and new projects;
From above, it may be noted that POWERGRID is well equipped to implement and
monitor its environment and social management plans.
Any other measures like provision of bird guards, spike guards, barbed wire fencing or
any other arrangement for addressing the issues like bird hit/animal/elephant scratching
etc. shall be finalized only after detailed/ check survey and finalization of route
alignment. Since the detailed/ check survey is part of main package requirement of such
measures, its extent and estimated cost shall be incorporated in the revised cost
estimate proposal which is normally prepared for all projects as there is a considerable
time gap between planning and actual implementation. However, as per the preliminary
assessment such additional measures may not be required in the instant scheme as no
such impact are envisaged due to routing of lines far away from such sensitive areas.
The complainant will also be allowed to submit its complaint to local project official who
will pass it to GRC immediately but not more than 5 days of receiving such complaint.
The first meeting of GRC will be organized within 15 days of its constitution/disclosure
to formulate procedure and frequency of meeting. In case of any complaint, GRC
meeting shall be convened within 15 days. If Project level GRC not able to take decision
it may refer the complaint to corporate GRC for solution. GRC endevour will be to
pronounce its decision within 30-45 days of receiving grievances. In case
complainant/appellant is not satisfied with the decision of project level GRC they can
make an appeal to corporate GRC/District Collector or Court of law for solution.
The corporate level GRC shall function under the chairmanship of Director (Project) who
will nominate other members of GRC including one representative from corporate
ESMD who is conversant with the environment & social issues. The meeting of
Corporate GRC shall be convened within 7-10 days of receiving the reference from
project GRC or complainant directly and pronounce its decision within next 15 days.
Clause Project activity/ Potential Proposed mitigation Parameter to be Measurement & Institutional Implementation
No. stage Impact measures monitored frequency responsibility schedule
Pre-construction
1 Location of line Exposure to Setback of dwellings to line Tower location and Setback distances to POWERGRID Part of tower sitting
towers and line safety related route designed in alignment selection with nearest houses – once survey and detailed
alignment and risks accordance with permitted respect to nearest alignment survey
design level of power frequency dwellings and design
and the regulation of
supervision at sites.
2 Equipment Release of PCBs not used in Transformer design Exclusion of PCBs in POWERGRID Part of tender
specifications chemicals substation transformers or transformers stated in specifications for
and design and gases in other project facilities or tender specification – the equipment
parameters receptors equipment. once
(air, water, Processes, equipment and Process, equipment and Exclusion of CFCs POWERGRID Part of tender
land) systems not to use system design stated in tender specifications for
chlorofluorocarbons specification – once the equipment
(CFCs), including halon, Phase out schedule to Part of equipment
and their use, if any, in be prepared in case and process design
existing processes and still in use – once
systems should be phased
out and to be disposed of in
a manner consistent with
the requirements of the
Government
3 Transmission Exposure to Line design to comply with Electromagnetic field Line design POWERGRID Part of design
line design electromagne the limits of electromagnetic strength for proposed compliance with parameters
tic interference from power line design relevant standards –
interference lines once
4 Substation Exposure to Design of plant enclosures Expected noise Compliance with POWERGRID Part of detailed
location and noise to comply with noise emissions based on regulations - once siting survey and
design regulations. substation design design
Social Careful selection of site to Selection of substation Consultation with local POWERGRID Part of detailed
inequities avoid encroachment of location (distance to authorities -once siting survey and
socially, culturally and sensitive area). design
archaeological sensitive
areas (i.e. sacred groves,
3
In the instant case, no involuntary acquisition of land is involved. Hence this clause shall not be applicable.
IEAR for ± 800 kV HVDC Raigarh-Pugalur Bipole Link 47
Clause Project activity/ Potential Proposed mitigation Parameter to be Measurement & Institutional Implementation
No. stage Impact measures monitored frequency responsibility schedule
7 Line through Loss of Avoid siting of lines through Tower location and line Consultation with local POWERGRID Part of tower siting
protected area/ precious such areas by careful site alignment selection forest authorities - survey and detailed
precious ecological and alignment selection (distance to nearest once alignment survey
ecological area values/ (National Parks, Wildlife designated ecological and design
damage to Sanctuary, Biosphere protected/ sensitive areas)
precious Reserves/ Biodiversity
species Hotspots)
Minimize the need by using Tower location and line Consultation with local POWERGRID Part of tower siting
RoW wherever possible alignment selection authorities and design survey and detailed
engineers - once alignment survey
and design
8 Line through Damage to Study of earmarked Tower location and line Consultation with local POWERGRID Part of tower sitting
identified the Wildlife/ elephant corridors to avoid alignment selection. forest authorities – and detailed
Elephant Birds and such corridors, Adequate once. alignment survey &
corridor / also to line ground clearance, Fault design and
Migratory bird clearing by Circuit Breaker, Operation
Barbed wire wrapping on Minimum/maximum Monitoring – quarterly
towers, reduced spans etc., ground clearance basis
if applicable
Avoidance of established/ Tower location and line Consultation with local POWERGRID Part of tower siting
identified migration path alignment selection forest authorities - survey and detailed
(Birds & Bats). Provision of once alignment survey
flight diverter/ reflectors, and design
bird guard, elevated
perches, insulating jumper
loops, obstructive perch
deterrents, raptor hoods
etc4., if applicable
9 Line through Deforestation Avoid locating lines in forest Tower location and line Consultation with local POWERGRID Part of tower siting
forestland and loss of land by careful site and alignment selection authorities – once survey and detailed
biodiversity alignment selection (distance to nearest alignment survey
edge effect protected or reserved and design
forest)
4
As per International/National best practices and in consultation with concerned forest/wildlife Authority.
IEAR for ± 800 kV HVDC Raigarh-Pugalur Bipole Link 48
Clause Project activity/ Potential Proposed mitigation Parameter to be Measurement & Institutional Implementation
No. stage Impact measures monitored frequency responsibility schedule
Minimise the need by using
existing towers, tall towers Consultation with local
and RoW, wherever authorities and design
possible engineers – once
Measures to avoid invasion Intrusion of invasive Consultation with local
of alien species species forest authorities -
once
Obtain statutory clearances Statutory approvals from Compliance with
from the Government Government regulations – once for
each subproject
10 Lines through Loss of Use existing tower or Tower location and line Consultation with local POWERGRID Part of detailed
farmland agricultural footings wherever possible. alignment selection. authorities and design alignment survey
production/ engineers – once and design
change in
cropping Avoid sitting new towers on Tower location and line Consultation with local Part of detailed
pattern farmland wherever feasible alignment selection authorities and design sitting and
engineers – once alignment survey
/design
11 Noise related Nuisance to Substations sited and Noise levels Noise levels to be POWERGRID Part of detailed
neighbouring designed to ensure noise specified in tender equipment design
properties will not be a nuisance documents – once
12 Interference with Flooding Appropriate sitting of towers Tower location and line Consultation with local POWERGRID Part of detailed
drainage hazards/ loss to avoid channel alignment selection authorities and design alignment survey
patterns/ of agricultural interference (distance to nearest flood engineers – once and design
irrigation production zone)
channels
13 Escape of Environment Transformers designed with Equipment specifications Tender document to POWERGRID Part of detailed
polluting al pollution oil spill containment with respect to potential mention specifications equipment design
materials systems, and purpose-built pollutants – once /drawings
oil, lubricant and fuel
storage system, complete
with spill clean up
equipment.
19 Construction of Increase in Existing roads and tracks Access roads, routes Use of established POWERGRID Construction
roads for airborne dust used for construction and (length and width of new roads wherever (Contractor period
accessibility particles maintenance access to the access roads to be possible – every 2 through contract
line wherever possible. constructed) weeks provisions)
Increased New access ways restricted Access width (meters) Access restricted to POWERGRID Construction
land to a single carriageway single carriage –way (Contractor period
requirement width within the RoW. width within RoW – through contract
for temporary every 2 weeks provisions)
accessibility
20 Construction Safety of Coordination with local Periodic and regular No. of incidents- once POWERGRID Construction
activities local villagers communities for reporting /supervision of every week (Contractor period
construction schedules, safety arrangement through contract
Barricading the construction provisions)
area and spreading
awareness among locals
Local traffic Coordination with local Traffic flow (Interruption Frequency (time POWERGRID Construction
obstruction authority/ requisite of traffic) span)- on daily basis (Contractor period
permission for smooth flow through contract
of traffic provisions)
21 Temporary Overflows, Measure in place to avoid Temporary fill placement Absence of fill in POWERGRID Construction
blockage of reduced dumping of fill materials in (m3) sensitive drainage (Contractor period
utilities discharge sensitive drainage area areas – every 4 weeks through contract
provisions)
22 Site clearance Vegetation Marking of vegetation to be Vegetation marking and Clearance strictly POWERGRID Construction
removed prior to clearance, clearance control (area limited to target (Contractor period
and strict control on clearing in m2) vegetation – every 2 through contract
activities to ensure minimal weeks provisions)
clearance.
No use of herbicides and
pesticides
IEAR for ± 800 kV HVDC Raigarh-Pugalur Bipole Link 51
Clause Project activity/ Potential Proposed mitigation Parameter to be Measurement & Institutional Implementation
No. stage Impact measures monitored frequency responsibility schedule
23 Trimming Fire hazards Trees allowed growing up to Species-specific tree Presence of target POWERGRID Construction
/cutting of trees a height within the RoW by retention as approved by species in RoW (Contractor period
within RoW maintaining adequate statutory authorities following vegetation through contract
clearance between the top (average and max. tree clearance – once per provisions)
of tree and the conductor as height at maturity, in site
per the regulations. meters)
Loss of Trees that can survive Species-specific tree Presence of target POWERGRID Construction
vegetation pruning to comply should be retention as approved by species in RoW (Contractor period
and pruned instead of cleared. statutory authorities following vegetation through contract
deforestation clearance - once per provisions)
site
Felled trees and other Disposal of cleared Use or intended use of POWERGRID Construction
cleared or pruned vegetation as approved vegetation as (Contractor period
vegetation to be disposed of by the statutory approved by the through contract
as authorized by the authorities (area cleared statutory authorities – provisions)
statutory bodies. in m2) once per site
24 Wood/ Loss of Construction workers Illegal wood /vegetation Complaints by local POWERGRID Construction
vegetation vegetation prohibited from harvesting harvesting (area in m2, people or other (Contractor period
harvesting and wood in the project area number of incidents evidence of illegal through contract
deforestation during their employment, reported) harvesting – every 2 provisions)
(apart from locally weeks
employed staff continuing
current legal activities)
25 Surplus Runoff to Soil excavated from tower Soil disposal locations Acceptable soil POWERGRID Construction
earthwork/soil cause water footings/ substation and volume (m3) disposal sites – every (Contractor period
pollution, foundation disposed of by 2 weeks through contract
solid waste placement along roadsides, provisions)
disposal or at nearby house blocks if
requested by landowners
26 Substation Loss of soil Loss of soil is not a major Borrow area sitting (area Acceptable soil borrow POWERGRID Construction
construction issue as excavated soil will of site in m2 and areas that provide a (Contractor period
be mostly reused for estimated volume in m3) benefit - every 2 through contract
leveling and re-filling. weeks provisions)
However, in case of
requirement of excess soil
the same will be met from
30 Construction Noise Construction activities only Timing of construction Daytime construction POWERGRID Construction
schedules nuisance to undertaken during the day (noise emissions, [dB(A)] only – every 2 weeks (Contractor period
neighbouring and local communities through contract
50 Equipment Release of Processes, equipment and Process, equipment and Phase out schedule to POWERGRID Operations
specifications chemicals systems using system design be prepared in case
IEAR for ± 800 kV HVDC Raigarh-Pugalur Bipole Link 58
Clause Project activity/ Potential Proposed mitigation Parameter to be Measurement & Institutional Implementation
No. stage Impact measures monitored frequency responsibility schedule
and design and gases in chlorofluorocarbons (CFCs) still in use – once in a
parameters receptors , including halon, should be quarter
(air, water, phased out and to be
land) disposed of in a manner
consistent with the
requirements of the Govt.
51 Transmission Exposure to Transmission line design to Required ground Ground clearance - POWERGRID Operations
line electromagne comply with the limits of clearance (meters) once
maintenance tic electromagnetic
interference interference from overhead
power lines
52 Uncontrolled Fire hazard Periodic pruning of Requisite clearance Assessment in POWERGRID Operations
growth of due to growth vegetation to maintain (meters) consultation with
vegetation of tree/shrub requisite electrical forest authorities -
/bamboo clearance. once a year(pre-
along RoW No use of herbicides/ monsoon/post-
pesticides monsoon
53 Noise related Nuisance to Substations sited and Noise levels {dB(A)} Noise levels at POWERGRID Operations
neighbouring designed to ensure noise boundary nearest to
properties will not be a nuisance. properties and
consultation with
affected parties if any -
once
In exercise of the powers vested with Power Grid Corporation of India Limited
(POWERGRID) under Indian telegraph Act'1885, part 3, section 10 to 19 conferred under
section 164 of the Electricity Act 2003 through Gazette by India, extra ordinary dated 24th
Dec. 2003, has the authority to place and maintain transmission lines under over along or
across and posts in or upon, any immoveable property. As per the provisions of Indian
Telegraph Act1885 Part III Section 10 (b) which prohibits acquisition of any rights other
than that of use only, land for tower and right of way is not acquired and agricultural
activities are allowed to continue. However, as per clause 10 (d) of same act stipulates
that the user agency shall pay full compensation to all interested for any damages
sustained during the execution of said work. Accordingly, POWERGRID pays
compensation to land owners towards damages if any to trees or crop during
implementation of transmission project as well as during Operation and maintenance
phase. The procedure followed for such compensation is as follows:
i) All the trees which are coming within the clearance belt of ROW on either side of
the center line are identified and marked/numbered from one AP to the other and
documented.
ii) Type, Girth (Measured 1 m. above ground level), approximate height o the tree is
also noted for each tree
iii) Trees belonging o Govt., Forest, Highways and other local bodies may be
separately noted down or timely follow up with the concerned authorities for
inspection and removal.
iv) Cashew, Guava, Lemon and other hybrid trees which are not of tall growing
nature are not marked for cutting since these trees can be crossed using
standard tower extensions if required.
A notice under Indian Telegraph Act is served to the land owners informing that the
proposed transmission line is being routed through the property of the individual
concerned. The notice shall contain the particulars of the land, ownership details and the
details of the trees/crops inevitability likely to be damaged during the course of the
construction of the proposed transmission line and acknowledgement received from land
owner. A copy of said notice is further issued to the Revenue Officer, who has been
authorized by the State Govt. for the purpose of assessment/valuation and disbursement
of compensation to the affected parties.
The revenue officer shall further issue a notice of intimation to the concerned land owner
and inspect the site to verify the documents related to the proof of ownership and a
detailed Mahazar is prepared for the identified trees and crops inevitability damaged
during the course of the construction. For assessing the true value of timber yielding trees
help of forest officials is taken and for fruit bearing trees help of Horticulture department is
taken.
The Mahazar shall contain the land owner details type of tree/crop, its present age, variety,
yielding pattern etc. and the same is prepared at site in the presence of the land owner.
These Mahazars are further compiled and a random verification is conducted by the
concerned District Collector OR his authorized representative in order to ascertain the
assessment carried out by the revenue office is genuine and correct. After this process the
District collector issues a tree cutting permit to Power Grid Corporation to enable removal /
damage to the standing tree/crop identified in the line corridor.
Once the tree/crop is removed / damaged, POWERGRID shall issue a tree cutting/crop
damaged notice to the land owner with a copy to the Revenue Officer to process the
compensation payment. Based on the above the compensation payment is generated by
means of a computerized programme developed by the National Informatics Center
exclusively for this purpose. The detailed Valuation statement thus generated using this
programme is verified at various levels and approval of payment of compensation is
accorded by the concerned District Collectors.
On approval of compensation, the revenue officer shall further intimate the amount
payable to the different land owners and POWERGRID arranges the payment by way of
Demand Draft to the affected parties. The payment is further disbursed at the local village
office after due verification of the documents in presence of other witnesses.
Due to typical demography of Kerala state and presence of several orchards of Coconut
and Rubber, State government in consultation with Kerala State Electricity Board (KSEB)
have devised a formula for arriving the compensation which is as follows:
The constant factor is to arrive the net return component for the particular variety of tree in
line with the annuity ratio slab prescribed for the balance life of the tree. A sample
calculation sheet using the said formula to arrive at compensation towards trees / crop is
enclosed for ready reference.
SAFETY PLAN
[TO BE EXECUTED ON A NON JUDICIAL STAMP PAPER WORTH RS. TWENTY ONLY]
SAFETY PLAN
WHEREAS ......(abbreviated name of the Employer)........ has awarded to the Contractor the
aforesaid Contract vide its Notification of Award/Contract No. ……..……….... dated
....…………..and Amendment No. ..................... (applicable when amendments have been
issued) (hereinafter called the "Contract") in terms of which the Contractor is required to submit
‘Safety Plan’ along with certain documents to the Engineer In-Charge/Project Manager of the
Employer within Sixty (60) days of Notification of Award for its approval.
NOW THEREFORE, the Contractor undertakes to execute the Contract as per the safety plan
as follows:
1. THAT the Contractor shall execute the works as per provisions of Bidding Documents
including those in regard to Safety Precautions / provisions as per statutory requirements.
2. THAT the Contractor shall execute the works in a well planned manner from the
commencement of Contract as per agreed mile stones of work completion schedule so
that planning and execution of construction works goes smoothly and consistently through
out the contract duration without handling pressure in last quarter of the financial year/last
months of the Contract and the shall be finalized in association with EMPLOYER Engineer
In-charge/Project Manager from time to time as required.
3. THAT the Contractor has prepared the safe work procedure for each activity i.e.
foundation works including civil works, erection, stringing (as applicable), testing &
commissioning, disposal of materials at site / store etc. to be executed at site, which is
enclosed at Annexure – 1A (SP) for acceptance and approval of Engineer In-
charge/Project Manager. The Contractor shall ensure that on approval of the same from
Engineer In-charge/Project Manager , the approved copies will be circulated to Employer’s
personnel at site [Supervisor(s)/Executive(s)] and Contractor’s personnel at site [Gang
leader, supervisor(s) etc.] in their local language / language understood by gang.
Section IX. Contract Forms 9-150
THAT the Contractor has prepared minimum manpower deployment plan, activity wise as
stated above, which is enclosed at Annexure – 1B (SP) for approval of Engineer In-
charge/Project Manager.
4. THAT the Contractor shall ensure while executing works that they will deploy minimum
25% of their own experienced work force who are on the permanent roll of the company
and balance 75% can be a suitable mixed with the hired gangs / local workers / casual
workers if required. The above balance 75% work force should be provided with at least
10 days training by the construction agencies at sites and shall be issued with a
certificate. No worker shall be engaged without a valid certificate. Hired gang workers
shall also follow safe working procedures and safety norms as is being followed by
company’s workmen. It should also be ensured by the contractor that certified fitters who
are climbing towers / doing stringing operations can be easily identifiable with a system
like issue of Badge / Identification cards (ID cards) etc. Colour identification batches
should be worn by the workers. Contractor has to ensure that inexperience workers /
unskilled workers should not be deployed for skilled job.
5. THAT the Contractor’s Gang leader / Supervisor / Senior most member available at every
construction site shall brief to each worker daily before start of work about safety
requirement and warn about imminent dangers and precautions to be taken against the
imminent dangers (Daily Safety Drill). This is to be ensured without fail by Contractor and
maintain record of each gang about daily safety instructions issued to workers and put up
to EMPLOYER site In-charge for his review and record.
6. THAT the Contractor shall ensure that working Gangs at site should not be left at the
discretion of their Gang Leaders who are generally hired and having little knowledge about
safety. Gang leader should be experienced and well versed with the safe working
procedures applicable for transmission line/ Sub Station works. In case gang is having
Gang leader not on permanent roll of the company then additional Supervisor from
company’s own roll having thorough knowledge about the works would be deployed so as
to percolate safety instructions up to the grass root level in healthy spirits. Contractor has
to ensure close supervision while executing critical locations of transmission lines / sub
stations and ensures that all safety instructions are in place and are being followed.
7. THAT the Contractor shall maintain in healthy and working condition all kind of
Equipments / Machineries / Lifting tools / Lifting tackles / Lifting gears / All kind of Ropes
including wire ropes / Polypropylene ropes etc. used for Lifting purpose during execution
of the project and get them periodically examined and load tested for safe working load in
accordance with relevant provisions and requirement of Building & other construction
workers Regulation of Employment and Conditions of Services Act and Central Rule 1998,
Factories Act 1948, Indian Electricity Act 2003 before start of the project. A register of
such examinations and tests shall be properly maintained by the contractor and will be
promptly produced as and when desired by the Engineer In-charge/Project Manager or by
the person authorised by him. The Contractor has to ensure to give special attention on
the formation / condition of eye splices of wire rope slings as per requirement of IS 2762
Specification for wire rope slings and sling legs.
THAT the Contractor has prepared a list of all Lifting machines, lifting Tools / Lifting
Tackles / Lifting Gears etc. / All types of ropes and Slings which are subject to safe
working load is enclosed at Annexure – 2 (SP) for review and approval of Engineer In-
charge/Project Manager.
Section IX. Contract Forms 9-151
8. THAT the Contractor has to procure sufficient quantity of Personal Protective Equipment
(PPE)conforming to Indian / International standards and provide these equipment to every
workman at site as per need and to the satisfaction of Engineer-in-charge/Project
Manager of EMPLOYER. The Contractor’s Site Supervisor/ Project Manager has to
ensure that all workmen must use Personal Protective Equipment at site. The Contractor
shall also ensure that Industrial Safety helmets are being used by all workmen at site
irrespective of their working (at height or on ground). The Contractor shall further ensure
use of safety shoes by all ground level workers and canvas shoes for all workers working
at height, Rubber Gum Boots for workers working in rainy season and concreting job, Use
of Twin Lanyard Full body Safety Harness with attachment of light weight such as
aluminium alloy etc. and having features of automatic locking arrangement of snap hook,
by all workers working at height for more than three meters and also for horizontal
movement on tower shall be ensured by contractor. The Contractor shall not use ordinary
half body safety harness at site. The Contractor has to ensure use of Retractable type fall
arrestors by workers for ascending / descending on suspension insulator string and other
similar works etc., Use of Mobile fall arrestor for ascending / descending from tower by all
workers. The contractor has to provide cotton / leather hand gloves as per requirement,
Electrical Resistance Hand gloves for operating electrical installations / switches, Face
shield for protecting eyes while doing welding works and Dust masks to workers as per
requirement. The Contractor will have to take action against the workers not using
Personal Protective Equipment at site and those workers shall be asked to rest for that
day and also their Salary be deducted for that day. EMPLOYER may issue warning letter
to Project Manager of contractor in violation of above norms.
THAT the Contractor shall prepare a detailed list of PPEs, activity wise, to commensurate
with manpower deployed, which is enclosed at Annexure – 3 (SP) for review and
approval of Engineer In-charge/Project Manager. It shall also be ensured that the sample
of these equipment shall be got approved from EMPLOYER supervisory staff before being
distributed to workers. The contractor shall submit relevant test certificates as per IS /
International Standard as applicable to PPEs used during execution of work. All the PPE’s
to be distributed to the workers shall be checked by EMPLOYER supervisory staff before
its usage.
The Contractor also agrees for addition / modification to the list of PPE, if any, as advised
by Engineer In-Charge/Project Manager.
9. THAT the Contractor shall procure, if required sufficient quantity of Earthing Equipment /
Earthing Devices complying with requirements of relevant IEC standards (Generally IECs
standards for Earthing Equipments / Earthing Devices are – 855, 1230, 1235 etc.) and to
the satisfaction of Engineer In-Charge/ Project Manager and contractor to ensures to
maintained them in healthy condition.
THAT the Contractor has prepared / worked out minimum number of healthy Earthing
Equipments with Earthing lead confirming to relevant IS / European standards per gang
wise during stringing activity/as per requirement, which is enclosed herewith at Annexure
– 4 (SP) for review and acceptance of Engineer In-Charge/ Project Manager prior to
execution of work.
Section IX. Contract Forms 9-152
10. THAT the Contractor shall provide communication facilities i.e. Walky – Talkie / Mobile
Phone, Display of Flags / whistles for easy communication among workers during Tower
erection / stringing activity, as per requirement.
11. THAT the Contractor undertakes to deploy qualified safety personnel responsible for
safety as per requirements of Employer/Statutory Authorities.
THAT the Contractor employing more than 250 workmen whether temporary, casual,
probationer, regular or permanent or on contract, shall employ at least one full time officer
exclusively as qualified safety officer having diploma in safety to supervise safety aspects
of the equipment and workmen who will coordinate with Engineer In-charge /Project
Manager/Safety Coordinator of the Employer. In case of work being carried out through
sub contractors the sub – contractor’s workmen / employees will also be considered as
the contractor’s employees / workmen for the above purpose. If the number of workers are
less than 250 then one qualified safety officer is to be deployed for each contract. He will
report directly to his head of organization and not the Project Manager of contractor He
shall also not be assigned any other work except assigning the work of safety. The
curriculum vitae of such person shall be got cleared from EMPLOYER Project Manager /
Construction staff.
The name and address of such safety officers of contractor will be promptly informed in
writing to Engineer In-charge with a copy to safety officer - In-charge before start of work
or immediately after any change of the incumbent is made during the currency of the
contract. The list is enclosed at Annexure – 5A (SP).
THAT the Contractor has also prepared a list including details of Explosive Operator (if
required), Safety officer / Safety supervisor / nominated person for safety for each erection
/ stringing gang, list of personnel trained in First Aid Techniques as well as copy of
organisation structure of the Contractor in regard to safety. The list is enclosed at
Annexure – 5B (SP).
12. The Project Manager shall have the right at his sole discretion to stop the work, if in his
opinion the work is being carried out in such a way that it may cause accidents and
endanger the safety of the persons and/or property, and/or equipment. In such cases, the
Contractor shall be informed in writing about the nature of hazards and possible
injury/accident and he shall comply to remove shortcomings promptly. The Contractor
after stopping the specific work can, if felt necessary, appeal against the order of stoppage
of work to the Project Manager within 3 days of such stoppage of work and decision of the
Project Manager in this respect shall be conclusive and binding on the Contractor.
13. THAT, if, any Employer’s Engineer/ supervisor at site observes that the Contractor is
failing to provide safe working environment at site as per agreed Safety Plan /
EMPLOYER Safety Rule/ Safety Instructions / Statutory safety requirement and creates
hazardous conditions at site and there is possibility of an accident to workmen or workmen
of the other contractor or public or the work is being carried out in an un safe manner or
he continues to work even after being instructed to stop the work by Engineer / Supervisor
at site / RHQ / Corp. Centre, the Contractor shall be bound to pay a penalty of Rs.
10,000/ - per incident per day till the instructions are complied and as certified by Engineer
/ Supervisor of Employer at site. The work will remain suspended and no activity will take
place without compliance and obtaining clearance / certification of the Site Engineer /
Supervisor of the Employer to start the work.
Section IX. Contract Forms 9-153
14. THAT, if the investigation committee of Employer observes any accident or the Engineer
In-charge/Project Manager of the Employer based on the report of the
Engineer/Supervisor of the Employer at site observes any failure on the Contractor’s part
to comply with safety requirement / safety rules/ safety standards/ safety instruction as
prescribed by the Employer or as prescribed under the applicable law for the safety of the
equipment, plant and personnel and the Contractor does not take adequate steps to
prevent hazardous conditions which may cause injury to its own Contractor’s employees
or employee of any other Contractors or Employer or any other person at site or adjacent
thereto, or public involvement because of the Contractor’s negligence of safety norms, the
Contractor shall be liable to pay a compensation of Rs. 10,00,000/- (Rupees Ten Lakh
only) per person affected causing death and Rs. 1,00,000/- (Rupees One Lakh only) per
person for serious injuries / 25% or more permanent disability to the Employer for further
disbursement to the deceased family/ Injured persons. The permanent disability has the
same meaning as indicated in Workmen’s Compensation Act 1923. The above
stipulations is in addition to all other compensation payable to sufferer as per workmen
compensation Act / Rules
THAT as per the Employer’s instructions, the Contractor agrees that this amount shall be
deducted from their running bill(s) immediately after the accident, That the Contractor
understands that this amount shall be over and above the compensation amount liable to
be paid as per the Workmen’s Compensation Act /other statutory requirement/ provisions
of the Bidding Documents.
15. THAT the Contractor shall submit Near-Miss-Accident report along with action plan for
avoidance such incidence /accidents to Engineer – In-charge/ Project Manager.
Contractor shall also submit Monthly Safety Activities report to Engineer – In-charge/
Project Manager and copy of the Monthly Safety Activities report also to be sent to Safety
In-charge at RHQ of the Employer for his review record and instructions.
16. THAT the Contractor is submitting a copy of Safety Policy/ Safety Documents of its
Company which is enclosed at Annexure – 6 (SP) and ensure that the safety Policy and
safety documents are implemented in healthy spirit.
17. THAT the Contractor shall make available of First Aid Box [Contents of which shall be as
per Building & other construction workers (Regulation of Employment and Conditions of
Services Act and Central Rule 1998 / EMPLOYER Guidelines)] to the satisfaction of
Engineer In-Charge/ Project Manager with each gang at site and not at camp and ensures
that trained persons in First Aid Techniques with each gang before execution of work.
18. THAT the Contractor shall submit an ‘Emergency Preparedness Plan’ for different
incidences i.e. Fall from height, Electrocution, Sun Stroke, Collapse of pit, Collapse of
Tower, Snake bite, Fire in camp / Store, Flood, Storm, Earthquake, Militancy etc. while
carrying out different activities under execution i.e. foundation works including civil works,
erection, stringing (as applicable), testing & commissioning, disposal of materials at site /
store etc. which is enclosed at Annexure – 7 (SP) for approval of the Engineer In-Charge/
Project Manager before start of work.
19. THAT the Contractor shall organise Safety Training Programs on Safety, Health and
Environment and for safe execution of different activities of works i.e. foundation works
including civil works, erection, stringing (as applicable), testing & commissioning, disposal
Section IX. Contract Forms 9-154
of materials at site / store etc. for their own employees including sub contractor workers on
regular basis.
The Contractor, therefore, submits copy of the module of training program, enclosed at
Annexure – 9 (SP), to Engineer In-charge/Project Manager for its acceptance and
approval and records maintained.
20. THAT the Contractor shall conduct safety audit, as per Safety Audit Check Lists enclosed
at Annexure – 8 (SP), by his Safety Officer(s) every month during construction of
Transmission Lines / Sub Stations / any other work and copy of the safety audit report will
be forwarded to the Employer’s Engineer In-charge / Site In-charge/Project Manager for
his comments and feedback. During safety audit, healthiness of all Personal Protective
Equipments (PPEs) shall be checked individually by safety officer of contractor and issue
a certificate of its healthiness or rejection of faulty PPEs and contractor has to ensure that
all faulty PPEs and all faulty lifting tools and tackles should be destroyed in the presence
of EMPLOYER construction staff. Contractor has to ensure that each gang be safety
audited at least once in two months. During safety audit by the contractor, Safety officer’s
feedback from EMPLOYER concerned shall be taken and recorded. The Employer’s site
officials shall also conduct safety audit at their own from time to time when construction
activities are under progress. Apart from above, the Employer may also conduct
surveillance safety audits. The Employer may take action against the person / persons as
deemed fit under various statutory acts/provisions under the Contract for any violation of
safety norms / safety standards.
21. THAT the Contractor shall develop and display Safety Posters of construction activity at
site and also at camp where workers are generally residing.
22. THAT the Contractor shall ensure to provide potable and safe drinking water for workers
at site / at camp.
23. THAT the Contractor shall do health check up of all workers from competent agencies and
reports will be submitted to Engineer In-Charge within fifteen (15) days of health check up
of workers as per statutory requirement.
24. THAT the Contractor shall submit information along with documentary evidences in regard
to compliance to various statutory requirements as applicable which are enclosed at
Annexure – 10A (SP).
The Contractor shall also submit details of Insurance Policies taken by the Contractor for
insurance coverage against accident for all employees are enclosed at Annexure – 10B
(SP).
25. THAT a check-list in respect of aforesaid enclosures along with the Contractor’s remarks,
wherever required, is attached as Annexure – Check List herewith.
towards Services Contract shall be made on submission of ‘Safety Plan’ along with all requisite
documents and approval of the same by the Engineer In-Charge/Project Manager.
IN WITNESS WHEREOF, the Contractor has hereunto set its hand through its authorised
representative under the common seal of the Company, the day, month and year first above
mentioned.
M/s..........………........................
WITNESS
1. Signature........................ Signature........................
Name............................... Name...............................
Note:
All the annexure referred to in this “Safety Plan“ are required to be enclosed by the contractor as
per the attached “Check List “
1. Safety Plan is to be executed by the authorised person and (i) in case of contracting
Company under common seal of the Company or (ii) having the power of attorney issued
under common seal of the company with authority to execute such contract documents
etc., (iii) In case of (ii), the original Power of Attorney if it is specifically for this Contract
or a Photostat copy of the Power of Attorney if it is General Power of Attorney and such
documents should be attached to this Safety Plan.
_______________________________________
[Name of Documentary evidence in support of
compliance]
(v) Public Insurance Liabilities Act 1991 and Rules. Yes/No
___________________________________
[Name of Documentary evidence in support of
compliance]
Section IX. Contract Forms 9-159
_______________________________________
[Name of Documentary evidence in support of
compliance]
(vii) Indian Petroleum Act 1934 and Rules. Yes/No
_______________________________________
[Name of Documentary evidence in support of
compliance]
(viii) License under the contract Labour (Regulation & Yes/No
Abolition) Act 1970 and Rules.
_______________________________________
[Name of Documentary evidence in support of
compliance]
(ix) Indian Electricity Rule 1956 and amendments if Yes/No
any, from time to time.
_______________________________________
[Name of Documentary evidence in support of
compliance]
(x) The Environment (Protection) Act 1986 and Yes/No
Rules.
_____________________________________
[Name of Documentary evidence in support of
compliance]
(xi) Child Labour (Prohibition & Regulation) Act 1986. Yes/No
_______________________________________
[Name of Documentary evidence in support of
compliance]
(xii) National Building Code of India 2005 (NBC 2005). Yes/No
_______________________________________
[Name of Documentary evidence in support of
compliance]
(xiii) Indian standards for construction of Low/ Medium/ Yes/No
High/ Extra High Voltage Transmission Line
_______________________________________
[Name of Documentary evidence in support of
compliance]
(iv) Any other statutory requirement(s) Yes/No
[please specify]
_______________________________________
[Name of Documentary evidence in support of
compliance]
13. Annexure – 10B (SP)
_______________________________________
[Name of Documentary evidence in support of
insurance taken]
(iii) Any Other Insurance Policies Yes/No
_______________________________________
[Name of Documentary evidence in support of
insurance taken]
____
EMPLOYER
ANNEXURE – 5
HEALTH, SAFETY & ENVIRONMENT
CONDITIONS IN CONTRACT DOCUMENT
ANNEXURE – 6
HEALTH & SAFETY CHECKLISTS
HEALTH AND SAFETY CHECKLIST
I) EXCAVATION :
1. Dumping of Excavated soil. (Minimum 1.5 Mts. or half the depth of
the pit which ever is more) Yes / No.
2. Whether angle of repose of soil as per design in the foundation is
maintained or not. Yes / No.
3. De watering arrangement is available ( If necessary) Yes / No.
4. Working area has been protected properly to avoid against fall of
passerby or animal in the excavated pit. Yes / No.
5 Shoring & Shuttering to protect the loose rock / soil against fall
exists. Yes / No.
6 Arrangement of illumination at construction site is available. (if
required ) Yes / No.
7 Check proper/adequate arrangement is made for extension of
electric supply. (Proper size of cable, Use of fuse, No loose Yes / No.
connection for De-watering Pumps/ Illumination / Electric
compressors etc. if applicable).
8 Check for damage / Uneven settlement of foundation. Yes / No.
9 Ensure Life saver arrangements have been made during
construction of well foundation in river bed. (Where necessary) Yes / No.
10 Check that the adequate arrangement is made for the storage of
blasting material at safe place. (if required) Yes / No.
11 Check that the blasting materials is handled with due care at site. ( If
required ) Yes / No.
12 Check that during blasting operation, Labour / Workmen / Passerby
are at safe places and arrangement is made to inform public by Yes / No.
caution markings (Red Flag) / Public Notices.
13 Check that the Blaster is holding the proper license issued by the
appropriate authority. as per the Indian Explosive Act. Yes / No.
14 Check that the length of the fuse wire used during blasting operation
is adequate. Yes / No.
15 Ensure Laying of temporary cable used for operation of Machines
SN Description of Activity Feed back Remarks
used during construction should not cause any danger for Yes / No.
electrocution of workmen.
16 Check that PPEs i.e. Safety helmets, Safety Shoes, is used by blaster
and their gang members during blasting. Yes / No.
17 Ensure that Shuttering and timbering has been made as detailed in
I:S: 3764. Yes / No.
18 Ensure that before undertaking excavation, the soil has been tested
and in case of availability of any explosive / dangerous gas, Yes / No.
necessary arrangement must be made to remove / dilute such gases.
19 The positions of underground installations such as sewers, water
pipes and electrical cables have been verified and in case of their Yes / No.
existence, they must be isolated.
20 Arrangement shall be made to prevent external vibrations due to rail
/ road traffic (If required). Yes / No.
21 Safety is ensured during the construction of Tr. Lines for buildings,
structures etc. which are coming in the vicinity of the excavated Yes / No.
area from collapse. ( If required )
22 Check that sufficient strong ladder of suitable length is available for
ingress / outgress of persons in the pit Yes / No.
23 Lone worker should not be allowed to work in the excavated area
beyond shoulder level. Yes / No.
24 Check for any possibility of seepage of water from nearby pond /
river should be estimated and taken care of. Yes / No.
25 After excavation the work has been completed speedily and back
filling done at the earliest. Yes / No.
B. TOWER ERECTION :
C. CONDUCTOR STRINGING:
REMARKS IF ANY:
Name :
Designation : Name : Name :
Representative of Designation: Designation:
Contractor Power Grid Rep. from Site. Power Grid Rep. from RHQ.
Safety Related Check List during Construction of Substation
II): SAFETY PRECAUTION DURING STORAGE, HANDLING AND USE OF BLASTING MATERIAL:
1 Check that the adequate arrangement is made for the storage of
blasting material at safe place. (Temporary Magazine is to be Yes / No.
installed observing all norms) as per Indian Explosive Act.
2. Check that the blasting materials is handled by licensed blaster with Yes / No.
due care at site. (If applicable)
3. Check smoking is prohibited in the vehicle carrying explosives. Yes / No.
4. Check that the Blaster is holding proper license issued by the Yes / No.
appropriate authority. As per Indian Explosive Act.
5. Check that the length of the fuse wire used during blasting operation Yes / No.
is adequate.
6. Check while transportation, no unauthorized person is allowed in Yes / No.
vehicle carrying explosives.
7. Check that the loading and unloading of explosives is being done Yes / No.
carefully.
8. Check explosives and detonators or blasting caps is not being Yes / No.
transported in the same vehicle.
9. Check while transportation the detonators and explosives are not Yes / No.
carried loose or mixed with other materials.
10 Check surplus explosives shall not be stacked near working area Yes / No.
during loading / unloading.
11. Check explosives shall not be held in hands when lightening the Yes / No.
fuse.
12. Check that blasting in the open has been carried out during the fixed Yes / No.
hours every day or on fixed days in the week so that the public at
large should know about this.
13. Check that arrangement has been made to display sufficient Yes / No.
warnings / sign board to enable the people to get out of the blasting
area to get off the danger zone
14. Check that the danger zone has been suitably cordoned off. Yes / No.
15. Check during blasting operations begin / after the firing of
explosives shall follow the loud siren. Yes / No.
16. Check that during blasting operation, Labour / Workmen / Passerby
are at safe places and arrangement is made to inform public by Yes / No.
caution markings ( Red Flag ) / Public Notices etc.
17. Check that PPEs i.e. Safety helmets, Safety Shoes, is used by blaster
and their gang members during blasting and also the persons Yes / No.
supervising the blasting operations.
SN Description of Activity Feed back Remarks
18. For covered blasting ensure placement of cover plates of proper
thickness and sufficient numbers of sand filled bags. Yes / No.
19. Ensure that permission for blasting has been obtained from the
appropriate authority. Yes / No.
8. Ensure that Winch, Pulleys etc. are properly earthed. Yes / No.
SN Description of Activity Feed back Remarks
9. For LT lines, check whether special persons are posted at each point
of isolation till return of permit (PTW) if positioning of person is Yes / No.
not possible then it is to be seen that all the point of isolation has
been kept in the locked position till the work is in progress.
10. Whether the network of LT lines has been thoroughly checked and
precautions taken against inadvertent charging. Yes / No.
11. Check that proper arrangement is made / available for grounding LT
lines coming across during conductor laying. (This can be done by Yes / No.
way of portable earthing and short circuiting devices which cab be
engaged to and disengaged from LT lines, keeping away from the
LT lines until all operations on the same are completed and all man
and materials are removed from the LT lines).
12. Check the provision and proper positioning for the guying and back
staying (Where necessary). Yes / No.
13. Check working of hydraulic crimping machine. Yes / No.
14. Check before and after crimping, dimensional changes in clamps
and are in accordance with the drawings and specifications. Yes / No.
REMARKS IF ANY:
Power Technologies, Inc. has been requested to review POWERGRID’s 132 KV, 220 KV, 400
KV and 800 KV lines with respect to conductor to ground, phase to phase and circuit to circuit
clearances and their appropriateness in light of present practice.
Based on a review of POWERGRID’s designs, we find that the phase to phase and circuit to
circuit clearances are consistent with practices used for line clearances throughout the world.
The values used by POWERGRID are generally in the middle range of that used throughout the
world and are expected to provide satisfactory performance.
The conductor to ground clearances are within typical limits and meet or exceed the
requirements of the National Electrical Safety Code, American National Standard Institute, C2,
as shown on Figure.
16
14 Rule 232C
Rule 232D
1.8 Pu SS
12 2.0
2.2
2.4 Actual
10
6
800 400 220
System Voltage (kV) - Clearances as a Function of System Voltage
Configuration - Horizontal
Conductor Bundle - Quad CSR Bursitis (35.1 mm id)
Max. conductor sag - 14.56 m
Phase to phase spacing - approx. 15 m.
Ground clearance - 12.4 m (as per IE rules):15 m (maintained to limit max. electric field
to 10 KV/m)
Right of way - 85 m
400 KV S/C LINE
Configuration - Horizontal
Conductor Bundle - Twin ACSR Moose (31.77 mm dia)
Maximum conductor sag - 12.87 m
Phase to phase spacing - 10 to 12 m
Ground clearance - 8.84 m (as per IE rules)
Right of way - 52 m
Configuration - Vertical
Conductor Bundle - Twin ACSR Moose (31.77 mm dia)
Maximum conductor sag - 12.87 m
Phase to phase spacing - 8 to 9 m
Ckt. to ckt. spacing - 12 to 14 m
Ground clearance - 8.84 m (as per IE rules)
Right of way - 52 m
Configuration - Vertical
Maximum conductor sag - approximately 9.8 m
Phase to phase spacing - 5 to 5.5 m
Ckt. to ckt. spacing - approximately 10
Ground clearance - 7.015 m (as per IE rules)
Right of way - 35 m
Configuration - Vertical
Conductor - ACSR Panther (21 mm dia)
Maximum conductor sag - approximately 6.6 m
Phase to phase spacing - approximately 4 m
Ckt. to ckt. spacing - approximately 7 m
Ground clearance - 6.1 m (as per IE rules)
Right of way - 27 m
ANNEXURE – 8
PROCEDURE OF PUBLIC CONSULTATION
POWERGRID’S PUBLIC CONSULTATION PROCESS
Public consultation forms an integral part of POWERGRID’s project cycle, and will be carried
out in Regional/local language for wider/better understanding. The process of consultation and
its documentation shall be as follows:
TRANSMISSION LINES
1. When planning a transmission line, public consultation is used as an integral tool for
screening, assessment and finalisation of route alignment. During initial screening and
walkover survey, POWERGRID's staffs meet the public in the route of proposed
transmission line. Observations and problems arising from these discussions are given
due consideration while finalising the route.
2. During the survey for tower spotting, POWERGRID’s site officials meet the public i.e.
people coming in the route of the line. This enables POWERGRID to gauge public
opinion. At the time of construction, every individual on whose land a tower is to be
erected is met with. People coming in the way of the ROW are consulted and their
views and suggestions are incorporated thus allowing for public participation.
3. During construction POWERGRID pays the compensation for any damages to each
land owner and obtains their final acknowledgement.
SUBSTATIONS
1. POWERGRID identifies location of the substation and notifies the area under LA Act.
3. Under Section 6 of LA Act, the DC issues a notice informing the public about the land
to be acquired and invites their claims. All effective people informed individually.
Compensation is paid to public according to local norms.
5. POWERGRID assess the social impacts of its land acquisition based on the socio-
economic survey and designs its compensation packages in consultation with the
people. POWERGRID organises meetings with the PAPs to evolve the RAP.
In order to further streamline the above process and to facilitate documentation of the same, and
to discuss the following:
complete project plan (i.e. its route and terminating point and substations, if any, in
between);
POWERGRID design standards in relation to approved international standards;
health impacts in relation to EMF;
measures taken to avoid public utilities such as school, hospitals, etc.;
other impacts associated with transmission lines and POWERGRID’s approach to
minimising and solving them; and
land acquisition details, proposed R&R measures and compensation packages in line
with POWERGRID’s policy
POWERGRID uses one or more of the following techniques at various stages. These include:
(1) Public meetings: POWERGRID will hold public meetings during its EAMP process at
appropriate locations along the length of the transmission line. Public meetings will
include one to one meetings with land owners during transmission tower spotting. Larger
group meetings will be organised at strategic distances along the length of the
transmission line. These will consist of all or at least most of the people to be directly
affected by the concerned project and their local Gram Panchayat leaders.
(2) Informal small group meetings: Informal small group meetings will be conducted during
walkover survey to find out local environmental and social issues along the proposed
transmission line route. These meetings will be conducted by ESMT staff at appropriate
intervals.
(3) Information brochures and Pamphlets: POWERGRID will make available information
and project specific details to the public through Information brochures and Pamphlets.
These brochures and pamphlets will contain information on: the overall project plan;
design and construction standards; prudent deviations from design standards from
transmission towers near schools, hospitals, human habitation; potential impacts and
generic mitigation measures; resettlement and rehabilitation; and, compensation.
(4) Operating field offices: Information regarding the proposed transmission line can be
accessed by the public from operating field offices. Information will be provided through
brochures and pamphlets and any further queries will be responded by POWERGRID’s
staff.
(5) Local planning visits and site visits: POWERGRID staff will visit field sites. During this
time informal contacts will be established with the local people. Reactions of the public to
the project will be informally gauged.
(6) Response to public Enquires: ESMC/ESMT will respond to public enquiries by post or
through notices in local news papers.
(7) Press release inviting comments: POWERGRID will publish details of proposed
transmission routes in two local newspapers. Public will be invited to comment in writing
or by meeting concerned POWERGRID officials within a specified period.
POWERGRID will then incorporate relevant objections and suggestions.
(9) Ombudsman or representative: For building a consensus on the project its impacts and
mitigation measures, the PAPs will be encouraged to elect or appoint a trusted
ombudsman or representative.
(10) Public Displays: POWERGRID will show their model projects to public/small
representative groups.
DOCUMENTATION
The proceedings of the above consultation shall be documented. Details recorded will include
date of the meeting, venue, number and possibly the names of the people attended, issues
discussed and the outcome of the meeting.
The manager at DHQ will apply combinations of the appropriate techniques at various activities
of a project depending upon the field conditions as shown below:
SS
- finalise SS site Public meetings,
- notify area under LAA Ombudsment or
- undertake detailed LA census representative, Public
Milestones Process Techniques
final negotiations and documentation of
- display
agreements
5. Execution of Execute environmental management works Information brochures and
Environmental - appropriate clearance for Transmission pamphlets, Operating field
management works line ROW, etc. offices, Response to
- compensatory afforestation public enquiries
6. Execution of Tls Information brochures and
Social - pay compensation as agreed and pamphlets, Operating field
management works documented in SAMP and execute other offices, Response to
measures public enquiries
कायशक्रम-1 कायशक्रम-2
दिनाांक : 05.07.2016 दिनाांक : 05.07.2016
ग्राम : तेलीगड
ुं रा ग्राम : कम्हली
तहसील : पाटन तहसील : पाटन
जजला : दगग (छत्तीसगढ) जजला : दगग (छत्तीसगढ)
छायाचित्र: जन परामर्श कायशक्रम
कायशक्रम-3 कायशक्रम-4
दिनाांक : 05.07.2016 दिनाांक : 06.07.2016
ग्राम : काुंदल ग्राम : कोंडापार
तहसील : गड
ुं रदे ही तहसील : धमतरी
जजला : बलोद (छत्तीसगढ) जजला : धमतरी (छत्तीसगढ)
छायाचित्र: जन परामर्श कायशक्रम
प्रस्तावित +800 के.िी. एि.िी.डी.सी. (Bipole) रायगढ़ - पग
ु लरु पारे षण लाईन
कायशक्रम-5 कायशक्रम-6
दिनाांक : 06.07.2016 दिनाांक : 09.07.2016
ग्राम : उमरपोटी ग्राम : औरी
तहसील : अभनपरू तहसील : डोंडीलोहारा
जजला : रायपर (छत्तीसगढ) जजला : बलोद (छत्तीसगढ)
छायाचित्र: जन परामर्श कायशक्रम
प्रस्तावित +800 के.िी. एि.िी.डी.सी. (Bipole) रायगढ़ - पग
ु लरु पारे षण लाईन
कायशक्रम-7 कायशक्रम-8
दिनाांक : 09.07.2016 दिनाांक : 09.07.2016
ग्राम : महरूम ग्राम : चारभाठा
तहसील : छररया तहसील : छररया
जजला : राजनाुंदगाव (छत्तीसगढ) जजला : राजनाुंदगाव (छत्तीसगढ)
छायाचित्र: जन परामर्श कायशक्रम
प्रस्तावित +800 के.िी. एि.िी.डी.सी. (Bipole) रायगढ़ - पग
ु लरु पारे षण लाईन
कायशक्रम-9 कायशक्रम-10
दिनाांक : 05.07.2016 दिनाांक : 10.07.2016
ग्राम : क डुट ला ग्राम : खड़खड़ी
तहसील : च की तहसील : च की
जजला : राजनाांदगाव (छत्तीसगढ) जजला : राजनाांदगाव (छत्तीसगढ)
छायाचित्र: जन परामर्श कायशक्रम
कायशक्रम-11 कायशक्रम-12
दिनाांक : 12.07.2016 दिनाांक : 13.07.2016
ग्राम : चचल्हाटी ग्राम : छतेरा
तहसील : च की तहसील : आरां ग
जजला : राजनाांदगाव (छत्तीसगढ) जजला : रायपरु (छत्तीसगढ)
छायाचित्र: जन परामर्श कायशक्रम
कायशक्रम-13 कायशक्रम-14
दिनाांक : 13.07.2016 दिनाांक : 13.07.2016
ग्राम : गल्
ु लु ग्राम : तेलासी
तहसील : आरां ग तहसील : पलारी
जजला : रायपरु (छत्तीसगढ) जजला : बल दाबाजार (छत्तीसगढ)
छायाचित्र: जन परामर्श कायशक्रम
कायशक्रम-15 कायशक्रम-14
दिनाांक : 13.07.2016 दिनाांक : 13.07.2016
ग्राम : गल्
ु लु ग्राम : तेलासी
तहसील : आरां ग तहसील : पलारी
जजला : रायपरु (छत्तीसगढ) जजला : बल दाबाजार (छत्तीसगढ)
छायाचित्र: जन परामर्श कायशक्रम
कायशक्रम-15 कायशक्रम-16
दिनाांक : 13.07.2016 दिनाांक : 15.07.2016
ग्राम : बटगन ग्राम : क हर द
तहसील : पलारी तहसील : बल दाबाजार
जजला : बल दाबाजार (छत्तीसगढ) जजला : बल दाबाजार (छत्तीसगढ)
छायाचित्र: जन परामर्श कायशक्रम
प्रस्तावित +800 के.िी. एि.िी.डी.सी. (Bipole) रायगढ़ - पग
ु लरु पारे षण लाईन
कायशक्रम-17 कायशक्रम-18
दिनाांक : 15.07.2016 दिनाांक : 18.07.2016
ग्राम : सिरियाडीह ग्राम : सिस्दा
तहसील : बल दाबाजाि तहसील : नवागढ़
जजला : बल दाबाजाि (छत्तीिगढ) जजला : जाांजगीि-चाांपा (छत्तीिगढ)
छायाचित्र: जन परामर्श कायशक्रम
प्रस्तावित +800 के.िी. एि.िी.डी.सी. (Bipole) रायगढ़ - पग
ु लरु पारे षण लाईन
कायशक्रम-19 कायशक्रम-20
दिनाांक : 18.07.2016 दिनाांक : 18.07.2016
ग्राम : िल्दाकला ग्राम : ड िा
तहसील : जैजैपिु तहसील : िालखि दा
जजला : जाांजगीि-चाांपा (छत्तीिगढ) जजला : जाांजगीि-चाांपा (छत्तीिगढ)
छायाचित्र: जन परामर्श कायशक्रम
प्रस्तावित +800 के.िी. एि.िी.डी.सी. (Bipole) रायगढ़ - पग
ु लरु पारे षण लाईन
कायशक्रम-21 कायशक्रम-22
दिनाांक : 19.07.2016 दिनाांक : 19.07.2016
ग्राम : त िना ग्राम : िप ि
तहसील : पि
ु ि तहसील : डभिा
जजला : िायगढ़ (छत्तीिगढ) जजला : जाांजगीि-चाांपा (छत्तीिगढ)
छायाचित्र: जन परामर्श कायशक्रम
प्रस्तावित +800 के.िी. एि.िी.डी.सी. (Bipole) रायगढ़ - पग
ु लरु पारे षण लाईन
कायशक्रम-1 कायशक्रम-2
दिनाांक: 19.01.2017 दिनाांक: 19.01.2017
ग्राम: अलिटोिा ग्राम: चििमटोिा
तहसील : कोरिी तहसील : कोरिी
जजला: गडचिरोिी (महाराष्ट्र) जजला: गडचिरोिी (महाराष्ट्र)
छायाचित्र: जन परामर्श कायशक्रम
कायशक्रम-3 कायशक्रम-4
दिनाांक: 18.01.2017 दिनाांक: 17.01.2017
ग्राम: दिघोरी ग्राम: फुडी हे टी
तहसील : पोम्भर्
ु ाा तहसील : गोंडपपपरी
कायशक्रम-5 कायशक्रम-6
दिनाांक: 18.01.2017 दिनाांक: 20.01.2017
ग्राम: जीभगाव ग्राम: पाटनवाड़ा
तहसील : साविी तहसील : आरमोरी
जजला: िंद्रपरु (महाराष्ट्र) जजला: गडचिरोिी (महाराष्ट्र)
छायाचित्र: जन परामर्श कायशक्रम
प्रस्तावित +800 के.िी. एि.िी.डी.सी. (Bipole) रायगढ़ - पग
ु लरु पारे षण लाईन
कायशक्रम-7
दिनाांक: 10.01.2017
ग्राम: वेडगाव
तहसील :गोंडपपपरी
जजला: िंद्रपरु (महाराष्ट्र)
Project: HVDC Transm
ansmission Line in SRTS-II
Construction of HVDC
DC transmission
transm line from Raigarh to Pugalur
Venue:
1. Kokkarayanpettai,
tai, Namak
Namakkal District, Tamil Nadu.
2. Muthalipalayam,, Tiruppu
Tiruppur District, Tamil Nadu
3. Arasampalayam,, Coimbat
Coimbatore District, Tamil Nadu
Date: 11.12.2015 to 16
16.12.2015
As per the Environment and Social Policy and Procedure (ESPP), public
consultation meeting was held on construction of HVDC transmission lines from
Raigarh to Pugalur at the following location/s
Sri.CA Mathew, DGM, HVDC Pugalur CAO welcomed the public on behalf of
POWERGRID to the public consultation meeting and briefed them about
POWERGRID and the project.
Sri. V. Saravanan, Chief Manager, introduced the project scheme to the public and
briefed them about the importance of the project and the benefits to the state of
Tamil Nadu in particular and nation in general.
Sri. Sanju Kishan, Sr.Environment Officer, RHQ, Bangalore briefed the Environment
and Social Policy and Procedures (ESPP) of POWERGRID. It was informed that the
public consultation was being held as per this policy to address the apprehensions
/ questions of the public.
The entire session was interactive with active participation of the public in local
language; Tamil. People clarified their queries about the project with POWERGRID
officials, details enclosed as Annexure 3.
POWERGRID Page 1
Pubic Consultation Report – HVDC Project
POWERGRID:
1. Sri. CA Mathew DGM / HVDC Pugalur CAO.
2. Sri. V Saravanan Chief Manager /Ariyalur
3. Sri. SanjuKishan Sr. Environment Officer/ RHQ Bangalore
4. Sri. Vishwanath S.A Sr. Engineer/ HVDC Pugalur CAO
POWERGRID Page 2
Pubic Consultation Report – HVDC Project
POWERGRID Page 3
Pubic Consultation Report – HVDC Project
POWERGRID Page 4
Pubic Consultation Report – HVDC Project
POWERGRID Page 5
Pubic Consultation Report – HVDC Project
POWERGRID Page 6
Pubic Consultation Report – HVDC Project
POWERGRID Page 7
Pubic Consultation Report – HVDC Project
POWERGRID Page 8
Pubic Consultation Report – HVDC Project
Annexure 3
Gist of clarifications raised by the villagers:
POWERGRID Page 9
Pubic Consultation Report – HVDC Project
Sri.CA Mathew, DGM, HVDC Pugalur CAO welcomed the panchayat president and
the public on behalf of POWERGRID to the public consultation meeting and briefed
them about POWERGRID and the project.
Sri. V. Saravanan, Chief Manager, introduced the project scheme to the public and
briefed them about the importance of the project and the benefits to the state of
Tamil Nadu in particular and nation in general.
The entire session was interactive with active participation of the public in local
language; Tamil. People clarified their queries about the project with POWERGRID
officials, details enclosed as Annexure 3.
The meeting concluded with vote of thanks and with a request to the public for
their support in completion of the project by Sri. Vishwanath, Sr.Engineer,
POWERGRID, HVDC Pugalur CAO.
POWERGRID Page 10
Pubic Consultation Report – HVDC Project
POWERGRID:
1. Sri. CA Mathew DGM / HVDC Pugalur CAO.
2. Sri. V Saravanan Chief Manager /Ariyalur
3. Sri. Sanju Kishan Sr. Environment Officer/ RHQ Bangalore
4. Sri. Vishwanath S.A Sr. Engineer/ HVDC Pugalur CAO
POWERGRID Page 11
Pubic Consultation Report – HVDC Project
POWERGRID Page 12
Pubic Consultation Report – HVDC Project
POWERGRID Page 13
Pubic Consultation Report – HVDC Project
POWERGRID Page 14
Pubic Consultation Report – HVDC Project
POWERGRID Page 15
Pubic Consultation Report – HVDC Project
POWERGRID Page 16
Pubic Consultation Report – HVDC Project
POWERGRID Page 17
Pubic Consultation Report – HVDC Project
Panchayat president indicating the side from where old lines are passing
POWERGRID Page 18
Pubic Consultation Report – HVDC Project
POWERGRID Page 19
Pubic Consultation Report – HVDC Project
Annexure 3
Gist of clarifications raised by the villagers:
3. Sri. Devaraj(Villager)
a. Question: What will be the benefit of this line to our village if this goes
through our village and from our lands? Will there be any effect on health of the
people and cattle?
Answer: Irrespective of the location there would be power transmission through
our lines across the states. Hence the benefit of this line would be to the entire state
of Tamilnadu and the neighbouring states for transfer of power from surplus state
to deficit states. Therefore this line would contribute towards improvement of
power scenario for the district and the villages. There is no recorded evidence on
health impact due to transmission lines, either in humans or animals.
POWERGRID Page 20
Pubic Consultation Report – HVDC Project
Sri. V. Saravanan, Chief Manager, introduced the project scheme to the public and
briefed them about the importance of the project and the benefits to the state of
Tamil Nadu in particular and nation in general.
The entire session was interactive with active participation of the public in local
language; Tamil. People clarified their queries about the project with
POWERGRID officials, details enclosed as Annexure 3.
The meeting concluded with vote of thanks by Sri. Rajeev, AE, POWERGRID,
Pallakad.
POWERGRID Page 21
Pubic Consultation Report – HVDC Project
POWERGRID:
1. Sri. Ravindran DGM / Palakkad
2. Sri. Saravanan Chief Manager / Ariyalur
3. Sri. Sanju Kishan Sr. Environment Officer/ RHQ Bangalore
4. Sri. Sugumar Sr.Engineer, Udumalpet
5. Sri. Rajeev AE/ Palakkad
POWERGRID Page 22
Pubic Consultation Report – HVDC Project
POWERGRID Page 23
Pubic Consultation Report – HVDC Project
POWERGRID Page 24
Pubic Consultation Report – HVDC Project
POWERGRID Page 25
Pubic Consultation Report – HVDC Project
POWERGRID Page 26
Pubic Consultation Report – HVDC Project
POWERGRID Page 27
Pubic Consultation Report – HVDC Project
Annexure 3
Gist of clarifications raised by the villagers:
POWERGRID Page 28
ANNEXURE – 10
ESTIMATED BUDGET
Budget Estimate
A. Compensation
1 Forest
3. Land Compensation for Tower Base & RoW corridor - Rs. 107992.0 lakhs
(Considering line corridor of 1686.068 km in ' agricultural land
in rural / semi-urban / urban setting' with compensation
@15 / 25 / 50 lakhs/acre respectively)
Vigilance
Company Secretary Chief vigilance officer
CORPORATE LEVEL
Director Director Director Director
(Finance) (Operation) (Projects) (Personnel) REGIONAL LEVEL
Executive Director
(Regional)
Executive Director (ESMD, CSR & LA)
AGM/DGM
(PESM)
GM DGM
(Env & Soc.) (Env. & Soc) Env . Officer
(Regional)
Soc. Officer
(Regional)
Ch. Mgr Sr. Engg. SITE LEVEL
Dy. Mgr.
(Soc.)
T
R
A
N
S
M
Y I
S
S
I
O
N
L
I
N
E
40m 40m
3m
67 m RoW
10m
10m
3m
Tree Felling for Foundation Area Tree Felling for Foundation Area
64J
64N E
64G
64K
64-J 64-N
64C
LEGEND
164 AP-
AP
160 Cart-track Development
AP
102
AP
AP
AP AP
AP
AP-
AP
-1
AP
-12
50
-
AP- -1 -1
-12
26
13
-1
-
-1
AP
ALTERNATIVE-2
AP- 27 07 AP- Railways broad gauge Temple / Mosque / Grave
13
AP- 157 30
2
AP-
31
140
6
105
0
167
-1
141 AP-
8
AP AP- AP-
AP- AP-15 112 AP-
34
119 100 54 AP-
AP -1 155 3 AP- AP- AP- MAHANADI RIV 49 Railways other gauge Hutments
-1 69 147 114 AP-
AP
33 KV
SH-9
71 AP- AP- 98 AP- 59 ER
64D 151 148 96 AP- AP- AP-
Canal Tree
-17
AP- 89 86 AP- 61 AP- 400
AP- 94 AP- AP- 62 AP-
NH-200
AP- 48 KV
3
175 85 A
176 91 P-8 AP- ROUTE-4 AP- 52 LAR T/L Stream / Nala / Drain Wells - lined, unlined
T/L
59 AP- A-C
4 64 46 AP- AP- HAM UR
AP-
AP-
83
AP-
65 TE -1 43 41 PA RAIP
177 ROU AP-
58
T/L
AR- Contours with height Borewells
AP-129
200
AP-
AP-
82 AP- A MN
AP- VT Power / Telephone line Reserved/Protected forest
AP
AP-12
45 RF / PF
AP
179 16 SH- AP-
AP- AP-165 3 AP- 14 62 AP- 0K
-1
AP
40
-15
AP
166 79 1 57 AP-
AP
59
E- Scrub Height triangulated 200
AP-106
47
-1
AP
AP- AP- 132 AP-
-14
8
AP-
8
AP- A CO AP- UT
-1
AP-1
142 AP- 63
AP-104
135 P-13 AP-
AP
KV S
43
132
HASDEV RIVER
181 MM 61
AP-1
78
AP
-13
RO
AP-
AP
AP-
3
/C B 40
AP- AP-16
AP
AP- RO ON P
4
3 AP-
9
Boundary State Height point
AP-
55
-12
AP
AP-10
200
AP
BZR
AP
182
AP-
60
-1
7
8 UTE OIN
AP-
170
-11
AP- -KSD AP-
-14
AP
25
115
T
3
-2
56
-10
-12
44
-11
10
AP
66 L T/
154
AP-
AP
AP-
108
AP- AP- L
3
AP-
-15
AP- AP- Boundary District Bench-mark
117
149 146 AP-
1
99 88 A
-12
53
9
AP- AP- 97 80
3
-11
172 AP- AP- AP- P-8 AP- AP- AP- 67 AP- RO
2
185 150 AP- 95 90 7 AP- 81 73 72 UT
4
AP- 101 82 56 E-
765
6
AP- 174 AP- AP-
AP-
77
AP-
69
2
AP- AP- KV Boundary Mandal Post office PO
187 93 92 AP- AP- 52 39 RA
74 68 AP- IGA
AP- 51 AP- RH Towns / Villages Police station PS
AP- 76 E-2 AP- -CH
189 ROUT 70 50 AP-
AP-
39 AP-
32 AM
AP- 40 RO PA 64O
AP- 178 AP- AP- AP- UT AP- T/L
191 75 54 49 E-1 36
AP- AP-
AP- AP- 46 AP- 41
AP- 180 71 44 ROU AP-
193 AP- AP- AP- T E-4 31
183 73 48 400 KV RAIGARH-RAIP
AP- UR T/L
AP- AP- AP- 72
200 AP- 197 184 AP-
198 42 AP- AP-
AP- AP- 33 30 400 AP-
AP- AP- AP- 37 35 KV AP-
201 74 AP- AP- 43 4 3
AP- 47 45 T/L AP- GANTRY
186 AP- 12
AP- 27 AP- AP-
188 40 14 5
AP- 0 AP-
203 KV 1
AP-2
AP AP- AP-
AP-18
AP-
AP- -209 190 75 26 T/
L
AP-
6 AP-
210 AP-
AP
AP
AP- 2
1
AP- 29 24
-2
211
-19
AP-
AP
04
AP
AP
AP- AP-
5
28
-19
-19
ROU 23 7
-2
TE-1
-19
0
AP-
6
AP
AP- AP- 8
2
76 AP-
AP
AP- 9
02
AP- AP-
10
08
AP- AP- 22
RAIL
214 199 ROUTE
AP- -3 AP-
215 A AP- 25
AP AP- P-27 AP- 400 KV D/C ROU-RPR T/L
W
AP- A 26 13
217 P-216 -2 28
A
AP- SETTLEMENTS/VILLAGE/ TOWN AREA
AP-2
05 400
Y
15
ALTERNATIVE-1
AP
AAPP--29 KV
L
AP- -2 AP- D/C
INE
218 30
0 77 D/C T/L RO
0
AP 7 AP-
AP- AP- -219 78 AP- 400 KV AP-
17 400
U-R
PR
(U/C
2 31 T/L
2
AP- 23
AP 20 AP- KV MAJOR ROADS
40
224 AP- -221 79 LAR
0
222 A-
)
CH
KV
AP- AP- A MP
22
45 AP- 32 A
LA
T/L
0K
40
R
V
AP- AP AP
A-
AP-
D/
225 80 AP- -47
AP
AP -3
C
4
CH
AP- 8 3
-3
SH
AP- -35
4
49 AP- 36
AM
AP
L-
AP- 42 AP- AP
M
46 AP- AP- 39 -3 -3
P
HS
43 41 8 7
AT
T/
AP-
/L
AP-
L
81 50
AP-
51
1
E-
UT
RO
AP-
52
CO
MM
RO ON P AP-
53
U O
AP- TE-1 INT
82
AP-
54 Sr. ROUTE LENGTH
AP- No. DESCRIPTION
57
AP-
55
AP-
56
AP- 1 Proposed 800 Kv HVDC Route -1
AP- 59
60
AP-
129
AP-
124 220KV D
/C SHL-M
ALTERNATIVE-3 AP-
AP-
65
64
AP- AP-
63 62
AP-
AP-
61
58
2 Proposed 800 Kv HVDC Route -2
HS T/L AP-AP-66
67
AP- SUB AP- AP-
1 26 89 88 AP-
AP-1
22 STA
TIO
AP-
87 68 3 Proposed 800 Kv HVDC Route -3
AP- N
AP- A 1 23 AP- AP-
128 P-127 AP-1
18 114 AP- AP-
81
69
110 AP- AP-
CO 107 1 00 AP-
AP- MM AP- AP- AP- 80
AP- O 98
400
130 129 ROUT N PO 1 21 AP- 116
AP- AP-
70
KV L E-3 INT AP- AP- 117 AP- 90 AP-
ARA 1 119 115 AP- AP- AP- 72
20 113 AP- 82 AP- 7 AP-
- CH
AMP AP-
1 AP 105 AP- AP- AP- AP
92 -91 AP- AP- AP- AP- AP- 74 3 71 4 Proposed 800 Kv HVDC Route -4
A T/
L
11 AP- -106 AP- AP- AP- 94 93 86 AP- 84 83 AP- 76 75
108 1 02 AP- 97 95 85 77
99 AP-
AP- 78
96
AP- AP-
104 103
64H
e-
ut
e-
R1
ut
Ro
Ro
e-
T.
t
ou
T.
AL
AL
T .R
AL
R2.AP-1
R3.AP-1
AP1
common point near saoli
R3.AP-2 AP2
R2.AP-2
R3.AP-3
R3
I NE
e-
ut
EL
Ro
BE
T.
AL
AP3
R3.AP-4
E
LIN
D/C
ALT. Route-R1
V
0K
Tadoba wildlife sanctuary
22
E
LIN R3
ALT. Route-R2
D/C .AP
-5 22
V 0
0K KV
22 D/
R3.AP-6 C
LI
NE
TR
. NO
-1
UL
99
&2
M
R3.AP-7
00
-
LI
AU
AP4
R2.AP-4
55-P12
IR
AP5
H
HC
55-P16
AR
R2.AP-5
G
-7
SH
M
R2.AP-6
AP6 NO-66,67
MUL ROAD KM R2.AP-7
R3.AP-8 CHIRAULI TO AP7
MSH -7 GARH
R3.AP-9
UL R3.AP-13 R3.AP-12
M
LI- R3.AP-11 AP8
RAU R3.AP-10
HI
HC
E AR
LIN G
D/C -7
V SH
0K M
22
R3.AP-14
R2.AP-8
AP9
ER LINE
R3 R3.AP-15
te-
ou R2.AP-9
TOW
T. R
AL
220KV D/C
R3.AP-16
R3.AP-18
R3.AP-17
AP10
R2.AP-10
R3.AP-19
E
IN
EL
BE
R2.AP-11
AP11
AP12
AP16 R2.AP-12
AP14 R2.AP-14
R3.AP-20 AP13
AP15
220
MS KV
H-3 D/C R2.AP-13
R1
6 0 M TO
U WE
e-
L- RL
CH
ut
AM INE
Ro
AU R2.AP-15
SH R3.AP-21
I R3.AP-22
T.
AL
R3.AP-23
R3.AP-24
MS
AP19 AP18 H
AP17 -3
60
MR2.AP-16
UL
&120
R2.AP-17 TO
CH
O-119
AM
AU
SH
TR. N
R3.AP-25 I RO
AD
KM
LINE
NO
AP20 -9
,10
D/C
220 KV
R2.AP-18
AP21
R3.AP-26
R3.AP-27
R2.AP-19
INE
EL
BE
R3.AP-28 AP22
R2.AP-20
-R2
te
Rou
.
ALT
R3.AP-29
AP23
R2.AP-21
AP24
R3.AP-30
AP25
R3.AP-31
R2.AP-22
R3.AP-32
AP26
E
LIN
D/C
KV
220
AP27
R2.AP-23
R3.AP-33
56-M9
R2.AP-24
56-M13
AP28
1
te-R
R 3
e-
u
ut
. Ro
Ro
ALT
T.
AL
AP29 R2.AP-25
R3.AP-34 AP30
INE
EL
AP31
BE
AP32
R2.AP-26
R3.AP-35
INE
ary
EL
R2.AP-27 d
un
BE
o
n eb
zo
ve
ati LS
R3.AP-36 AP33 R2.AP-28
s
en W
o-s ala
Ec apr
ch
R2.AP-29
R3.AP-37
E
IN
EL
AP34
BE
MS
H
-9
MU
LT
O
R3.AP-38 AS
HT
MSH- YR
9 CHAN OA
R3.AP DRAP D
-39 UR - AS KM
HTY NO
AP35 -20
1,2
02
R2.AP-30
ry
R3.AP-40
unda
R2.AP-31
M
SH
AP36 -9
chap e zone bo
C
H
AN
D
LS
R3.AP-41 R
AP
U
rala W
AP37 R
-A
SH
TY
tiv
ensa
AP38 R2.AP-32
R3.AP-42
R2.A 220
Eco-s
P-3 KV
3 D/C
TO
W ER
LIN
E
-R2
e
out
AP39R3.AP-43
.R
ALT
NE
LI
C
D/
R2.AP-34
V
0K
22
AP40
R3.AP-44
R2.AP-35
R2.AP-36
AP41
R3.AP-45
INE
56-M10
EL
56-M14
BE
ALT. Route-R3
R3.AP-47
R3.AP-46
ute-R1
ALT. Ro
R2.AP-37
NE
LI
C
Eco-s la WLS
chapra
D/
V
0K
22
R3.AP-48
ensati
AP44
AP46
R2.AP-40
R3.AP-49
AP47
AP48
07
6&
-0 R3.AP-50
NO
ER
W
TO
NE
LI
C
D/
V
0K
22
R2.AP-41 AP49
R3.AP-51
INE
AP50
EL
BE
WA
RD
HA
RIV
ER
R3.AP-52
AP51
R2.AP-42
56-M11
56-M15