This document provides a detailed estimate for the proposed construction of a building belonging to Shankar Vasudeo. It includes 3 sentences summarizing the key information:
The estimate contains 6 items for the construction including excavation, cement concrete, reinforced cement concrete, reinforcement, centering and shuttering, and brick work. The total estimated cost for the construction is Rs. 17,99,906.28 based on rates from the PWD SOR 2014.
This document provides a detailed estimate for the proposed construction of a building belonging to Shankar Vasudeo. It includes 3 sentences summarizing the key information:
The estimate contains 6 items for the construction including excavation, cement concrete, reinforced cement concrete, reinforcement, centering and shuttering, and brick work. The total estimated cost for the construction is Rs. 17,99,906.28 based on rates from the PWD SOR 2014.
This document provides a detailed estimate for the proposed construction of a building belonging to Shankar Vasudeo. It includes 3 sentences summarizing the key information:
The estimate contains 6 items for the construction including excavation, cement concrete, reinforced cement concrete, reinforcement, centering and shuttering, and brick work. The total estimated cost for the construction is Rs. 17,99,906.28 based on rates from the PWD SOR 2014.
BUILDING TILAK WARD DEORI. municipal authorised engineer (reg no.) 07/6904 DETAIL ESTIMATE Detail estimate for the proposed construction of building belongs to Shankar vasudeo s/o chetram vasudeo at ambedkar ward deori. rate as per p.w.d. s.o.r. 2014 S.no. Pariculars of item nos l b h Qty Rate Unit Amount 1 2 3 4 5 6 7 8 9 10 1 excavation Eartth work in excavation by mechinical means (hydraulic excavator )/ manual means in over areas foundation trenchese or drains (not exceedings 1.5 m in width or 10 cm sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m 2.6.1 All kinds of soil S.O.R. Item No. 2.6.1. Page -22 column and septic tank
in columns 23 0.90 0.90 1.00 18.63
septic tank 1 3.25 3.00 1.00 9.75 28.38 129.00 cum 3661.02 2 cement concrete Providing and laying in position cement concrete of specified grade excluding the cost of centering shuttering - All work up to plinth level 4.1.2 With 40 mm nominal size graded stone aggregate 4.1.2.2 M 10 S.O.R. Item No. 4.1.2.2 page -45
in columns 23 1.50 1.50 0.10 5.18
front open 1 5.66 3.00 0.10 1.70 kitchen 1 2.48 3.75 0.10 0.93 porchj and stair 1 3.00 3.75 0.10 1.13 drawing 1 5.68 4.45 0.10 2.53 open 1 2.36 1.17 0.10 0.28 tiolet 1 2.36 1.37 0.10 0.32 bed 1 3.15 2.68 0.10 0.84 court yard 1 3.16 3.00 0.10 0.95 bed room 1 2.37 4.09 0.10 0.97 guest 1 2.16 3.16 0.10 0.68 tiolet 1 1.10 2.37 0.10 0.26 rear open 1 5.66 1.30 0.10 0.74 total 16.50 3890.00 cum 64168.00 3 Reinforced cement concrete Reinforced cement concrete work in beams, suspanded floors, roofs having slope of any degree landing balconies lintels, bands plain window sills stairs case and sprial stair cases up to floor two level excluding cost of cenetering , shuttering, finishing and reinforcement concrete grade M-20 Nominal mix(with 20 mm nominal size graded stone aggrete) S.O.R. Item no -5.3.1. Page -65
column footing 23 1.30 1.30 0.20 7.77
column up to plinth 23 0.30 0.20 1.20 1.66 columnup to roof 23 0.20 0.20 3.35 3.08 plinth beam 2 21.32 0.20 0.30 2.56 7 5.66 0.20 0.30 2.38 1 5.32 0.20 0.30 0.32 2 2.36 0.20 0.30 0.28 1 3.16 0.20 0.30 0.19 1 3.15 0.20 0.30 0.19 roof beam 2 21.32 0.20 0.30 2.56 7 5.66 0.20 0.30 2.38 1 5.32 0.20 0.30 0.32 2 2.36 0.20 0.30 0.28 1 3.16 0.20 0.30 0.19 1 3.15 0.20 0.30 0.19 roof slab in building 1 10.74 8.00 0.10 8.59 net total 32.94 total add 5% for stair laft 1.65 g total 34.58 5202.00 cum 179906.28 4 Reinforcement Reinforcment for R.C.C. work including 1.0X78.5X28.04/100 = 2201.00 straightering ,cutting bending , placing in position and binding wire up to floor level including all wastage etc. complete. Cold twisted bars(C T D) 1% of R.C.C. WORK S.O.R.Item NO. 5.16.3 Page 68 2201.00 62.90 KG 138442.90 5 Centering and shuttering Centering and shuttering including strutting propping etc. and removal of from for suspanded floors, roofs landing balconies and and access platefrom shelves (cast in situ) lintels, beams , beam girders , bressuments and centilevers, columns , pillars posts and struts wall in superstructure S.O.R.Item no. 5.9.3. Page 66
column footing 20 1.30 0.20 5.20
20 0.90 0.20 3.60
columnup to roof 20 0.20 3.35 13.40
20 0.30 3.35 20.10 plinth beam base 6 8.00 0.20 9.60 2 15.24 0.20 6.10 3 3.99 0.20 2.39 roof beam base 6 8.00 0.20 9.60 side 2 15.24 0.20 6.10 base 3 3.99 0.20 2.39 roof slab 1 10.74 8.00 85.92 total 164.40 add 5% for stair case and laft 8.22 g.total 172.62 264.00 45571.68 6 Brick work Brick work with well burnt open bhatta, bricks, crushing strength not less than 25 kg/sqcm and water absorption not more than 20% in foundation and plinth 6.3.1 cement mortor 1:6 (1 cement:6 sand) Item no. 6.3 Page - 85
door d1 4 1.00 2.10 8.40 door d2 2 0.85 2.10 3.57 window w1 3 0.90 1.20 3.24 net deduction 15.21 net total 414.44 123.00 sqm 50976.49 6 flooring Marble stone flooring with 18 mm thick marble stone(sample of marble shell by Enginner-in -charge) over 20 mm (average) thick base of cement mortor 1:4 (1 cement: 4 sand ) laid and jointed with grey cement slurry including rubbing and polishing complete with :(area of slab over 0.5 sqm)
total 42.34 399.00 sqm 16892.02 9 Wood work Provding wood work in frames of doors windows , celerestory window and other frames wrought framed , wrought framed and fixed in position 9.1.2 Sal wood S.O.R. Item no.9.1.2. Page-131 door d1 4 4.96 0.075 0.125 0.19 door d2 2 3.8 0.075 0.125 0.07 window w1 3 4.2 0.075 0.125 0.12 0.38 71308.00 cum 26767.24 Providing and fixiing panelled and glazed shutters for doors , windows and clerestory windows including ISI marked black enamelled M.S. butt hings with necessary screws excluding panelling which will be paid for separatly 9.5.1.1 35 mm thick shutters S.O.R. Item No. 9.5.1.1 Page -131
door d1 4 0.85 1.93 6.56
door d2 2 0.7 1.93 2.70 window w1 6 0.33 1.05 2.08 w2 2 0.22 1.05 0.46 total 11.81 2776.00 sqm 32770.68 TOTAL 930974.32 add 10% for sanitary and water supply 93097.43 G.Total 1,024,071.75 Say 9,57,000.00 In words Rs nine lacs fifty seven thousands