Asphalt Concrete Road Small Daughter
Asphalt Concrete Road Small Daughter
Government Of Nepal
Ministry of Urban Development
Kathmandu Valley Development Authority
District Comissioners Office
Laxminibas,Lalitpur
DETAIL ESTIMATE
Project :- Road Improvement Works
Work :- Ashphalt Road and Road Improvement Works
Location :- Lalitpur F.Y:076/077
Earthwork in excavation
1 in Ordinary soil lift upto
1.5m using by machine
3 P.C.C. Works(1:2:4)
Tick Drain
0+000 to 0+030 1.00 30.00 0.30 0.075 0.68
0+030 to 0+060 1.00 30.00 0.30 0.075 0.68
0+060 to 0+090 1.00 30.00 0.30 0.075 0.68
0+090 to 0+120 1.00 30.00 0.30 0.075 0.68
0+120 to 0+150 1.00 30.00 0.30 0.075 0.68
0+150 to 0+180 1.00 30.00 0.30 0.075 0.68
0+180 to 0+210 1.00 30.00 0.30 0.075 0.68
Earthfilling and Back filling in layers in foundations, trenches,pits etc with common filler
5
material including compaction and watering all complete
80% of excavated
12.12
material
Total 12.12 Cu M
200 mm HDPE(10kg/m^2)
6
pipe
a) 200 mm
12.00 3.00 36.00
HDPE(10kg/m^2) pipe
Total 36.00 R. M
14 Dismental
Work:Disposal of
dismentalled and
excavated material up to
1 km all complete
a)
10.17
Dismental of manhole 6.00 1.13 1.500
b)
1.67
Dismental of Catchpit 12.00 1.21 0.23 0.500
Total 11.84 Cu. M
15 Disposal of excavated
material up to 5 km all
complete
80% of excavated
1.00 12.12
quantity
Total 12.12 Cum
Earthwork in excavation in
1 Ordinary soil lift upto 1.5m Cu M 15.15 693.92 10515.05
using by machine
200 mm HDPE(10kg/m^2)
6 pipe R. M 36.00 2464.31 88715.16
7 Sub Grade Preparation Sq. M 1758.43 61.16 107545.58
Sub Base Material (Crusher
8 run 63mm down) Cu M 351.69 3564.44 1253563.65
Base Course (45mm down
9 crushed) Cu M 263.76 4468.91 1178739.81
10 Bituminious Prime Coat Ltr. 1758.43 119.79 210642.33
11 Bituminious Tack Coat Ltr. 2110.12 108.85 229686.13
50mm thick Asphalt Concrete
12 Cu M 87.92 22614.38 1988290.21
13 C.I. metal grating(heavy duty) Nos 12.00 3292.50 39510.00
14 Manhole Cover(heavy duty) Nos 6.00 37199.05 223194.30