RESOURCE COST OVERVIEW

COST STATUS COST DISTRIBUTION


Cost status for work resources. How costs are spread out amongst different resource types.

200000
180000 475180
160000
140000
120000
100000
80000
60000
40000
20000 2000000
0

Actual Cost Remaining Cost Baseline Cost Type: Work Type: Material

COST DETAILS
Cost details for all work resources.

Name Actual Work Actual Cost Standard Rate

foreman 50 hrs Rs. 8,000.00 Rs. 160.00/hr

surveyor 16 hrs Rs. 4,000.00 Rs. 250.00/hr

operator 10 hrs Rs. 1,500.00 Rs. 150.00/hr

Rcarp 344 hrs Rs. 51,600.00 Rs. 150.00/hr

genlabour 1,034 hrs Rs. 103,400.00 Rs. 100.00/hr

plumb 132 hrs Rs. 21,120.00 Rs. 160.00/hr

Roofing 918 hrs Rs. 183,600.00 Rs. 200.00/hr

HVAC eng 16 hrs Rs. 3,200.00 Rs. 200.00/hr

Elec 48 hrs Rs. 8,160.00 Rs. 170.00/hr

Drywall 144 hrs Rs. 28,800.00 Rs. 200.00/hr

siding 0 hrs Rs. 0.00 Rs. 200.00/hr

planning engr 50 hrs Rs. 25,000.00 Rs. 500.00/hr


site engr 0 hrs Rs. 0.00 Rs. 500.00/hr

Fcarp 184 hrs Rs. 36,800.00 Rs. 200.00/hr