Quotation Cesar
Quotation Cesar
LESS:
Labor only
Prepared by:
Danny Delgado
SubCon
PROJECT : ONE UPTOWN RESIDENCES
LOCATION : ONE UPTOWN, TAGUIG CITY
SCOPE OF WORK : ADDITIONAL WORKS #1 -QUOTATION
DATE : JUNE 30, 2018
DESCRIPTION UNIT QTY COST TOTAL COST
Concrete Topping at Frontage of Retail Area lm 32.00 80.00 2,560.00
CHB laying at ledge of toilet sqm 15.68 150.00 2,352.00
Plastering sqm 17.05 150.00 2,557.50
Edging Corner lm 47.60 120.00 5,712.00
Chamfer for double corner of Tiles lm 15.70 120.00 1,884.00
Installation of Wall Tiles sqm 32.34 250.00 8,085.00
Installation of Wall Tiles at PWD sqm 8.79 250.00 2,197.50
Cutting of Floor Accent: Tiles lm 438.45 60.00 26,307.00
Installation of 8mmx8mm Aluminum Groove at Wall lm 59.00 65.00 3,835.00
TOTAL AMOUNT 55,490.00
Labor only
Sir:
Sending you our quotation for the following works.
Thank you very much.
Prepared by:
Cesar Espora
Sub Con
PROJECT : 4 STOREY BUILDING
LOCATION : EDISON ST., CORNER MORSE, MAKATI CITY
SCOPE OF WORK :ADDITIONAL WORKS - RESIDENTIAL OPEN COURT
DATE : AS OF FEBRUARY 7, 2018
ACCOM
DESCRIPTION UNIT QTY COST TOTAL COST
PREVIOUS
SLAB AND BEAM - 3/F and 4/F % AMOUNT
Hauling of Materials lot 1.00 15,000.00 15,000.00 0.00% -
Chipping work for Beam Rebars lot 1.00 3,000.00 3,000.00 0.00% -
Drill works for Slab Rebars lot 1.00 2,000.00 2,000.00 0.00% -
Cleaning works lot 1.00 6,000.00 6,000.00 0.00% -
Formworks -Slab and Beam sqm 7.00 1,000.00 7,000.00 0.00% -
Rebars - Slab and Beam sqm 7.00 500.00 3,500.00 0.00% -
Concreting - Slab and Beam sqm 6.00 1,200.00 7,200.00 0.00% -
Scaffolding sqm 6.00 500.00 3,000.00 0.00% -
CHB 3RD FLOOR & 4TH FLOOR
CHB Laying sqm 12.00 300.00 3,600.00 0.00% -
Plastering sqm 24.00 300.00 7,200.00 0.00% -
TILES
Topping for Tile sqm 7.00 150.00 1,050.00 0.00% -
Tile Works sqm 7.00 350.00 2,450.00 0.00% -
PAINTING WORKS
Skim Coat works sqm 36.00 150.00 5,400.00 0.00% -
Painting sqm 36.00 150.00 5,400.00 0.00% -
LESS:
Labor only
Prepared by:
Danny Delgado
ACCOMPLISHMENT
PRESENT TO DATE
% AMOUNT % AMOUNT
50.00% 7,500.00 50.00% 7,500.00
100.00% 3,000.00 100.00% 3,000.00
100.00% 2,000.00 100.00% 2,000.00
50.00% 3,000.00 50.00% 3,000.00
100.00% 7,000.00 100.00% 7,000.00
100.00% 3,500.00 100.00% 3,500.00
100.00% 7,200.00 100.00% 7,200.00
50.00% 1,500.00 50.00% 1,500.00
0.00% - 0.00% -
0.00% - 0.00% -
0.00% - 0.00% -
0.00% - 0.00% -
0.00% - 0.00% -
0.00% - 0.00% -
0.00% - 0.00% -
0.00% - 0.00% -
40.44% 34,700.00 40.44% 34,700.00
PROJECT : 4 STOREY BUILDING
LOCATION : EDISON ST., CORNER MORSE, MAKATI CITY
SCOPE OF WORK :ADDITIONAL WORKS - WATERPROOFING
DATE : AS OF DECEMBER 5, 2017
total 38,200.00
Prepared by:
Danny Delgado
PROJECT : 4 STOREY BUILDING
LOCATION : EDISON ST., CORNER MORSE, MAKATI CITY
SCOPE OF WORK :ADDITIONAL WORKS NO.3 - CIVIL WORKS
DATE : AS OF DECEMBER 5, 2017
4th FLOOR TOPPING - SLAB OVER HUNG UNDER FIREWALL
DESCRIPTION UNIT QTY COST TOTAL COST
Hauling lot 1 5,000.00 5,000.00
Cleaning lot 1 4,000.00 4,000.00
total 20,925.00
total 6,080.00
total 11,600.00
Prepared by:
Danny Delgado
6-Jan-18
SUMMARY
CIVIL WORKS @ PARKING AREA, RAMP AND RETAINING WALL - Billing 1 216,040.95
ADDITIONAL WORKS NO. 2 - BILLING NO. 2 56,400.00
TOTAL 272,440.95
Prepared by:
Danny Delgado