Submarine System Proposal

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

Submarine System Proposal

CHT Caribbean Submarine Cable System

The Power of Submarine Information Transmission


Route Overview

 Trunk
Mexico-Dominican Republic
 Branch
BU1-St Croix
BU3 BU2-Turks and Caicos
BU2
BU5 BU3-Haiti
BU1
BU4 BU4-Cuba
BU5-Jamaica

Page 2
Huawei Marine Confidential
System Characteristics
Items Description
System Type Repeatered Submarine Cable System
Design Life 25 Years

Number of Fibre Pairs 8 fibre pairs

Design Capacity 128x100Gbit/s per fibre pair based on Huawei OSN 9800 series platform

Modulation Format 100G SC-PDM-QPSK

Submarine Cable & Fiber Repeatered & G.654B fibre

Submarine Line Monitor Equipment HMN SLM 1630 R3

Repeater HMN RPT R2

Network Management System OptiX iManager U2000

Page 3
Huawei Marine Confidential
Plan of Work
2020 2021
Main Tasks
1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12

Contract signature Main contract comes into force(estimated)

Permits Survey PIP Installation PIP

DTS

2.5 months
Marine Survey OP

Precurement of material 6 months


Marine cable
manufacture
Manufacture 3 months

OAM manufacture
Material procurement 3 months Transit

System integration

2 months
Submarine plant
load and transit
2 month
Marine installation OP

System 1 month
commissioning and
acceptance

Notes:
1. CIF date is supposed to be Jan.1st, 2020. Then PAC date will be Nov.25th, 2021. Total project duration is around 23 months.
2. With limited information and so many countries involved, Permit application duration is assumed.
3. Project duration will also be subject to resources availability.
Page 4
Huawei Marine Confidential
Budgetary Price
DAP Price ( Million USD)
Item
BU1 St BU5
Trunk BU2 TCI BU3 Haiti BU4 Cuba Subtotal
Croix Jamaica
Project Management 0.77 0.13 0.15 0.01 0.01 0.03 1.09
Submarine Cable 18.29 2.77 3.94 0.08 0.07 0.47 25.62
Submersible Equipment 10.75 1.20 1.80 0 0 0 13.75
Dry plant 3.76 1.27 0.30 0 0 0.01 5.34
DTS & Survey 3.12 0.63 0.67 0.06 0 0.4 4.87
Marine Installation 7.06 0.93 1.00 0.07 0.07 0.6 9.73
Grand Total 43.76 6.93 7.86 0.22 0.15 1.51 60.43
Notes:
1. Land cable: 5km land cable between BMH and CLS are assumed.
2. Security: this budgetary pricing does not take into account any scope with regard to personnel and vessel security, as well as any ordinance and/or munitions
survey requirements.
3. Dry plant includes submarine line monitoring and power feeding equipment, excludes terminal transmission equipment.
4. This budgetary pricing exclude any applicable taxes and duties.
5. This budgetary pricing exclude any permits and related environment license.
6. This budgetary pricing exclude any applicable Fishery Compensation and Pipeline Crossing Compensation.
7. Price are valid for 6 months.
8. Pricing is based on vessel availability and current exchange and commodity rates.

Page 5 Huawei Marine Confidential


www.huaweimarine.com
Copyright© 2015 Huawei Marine Networks Co., Ltd. All Rights Reserved.
The information in this document may contain predictive statements including, without limitation, statements regarding the future financial and operating results, future product portfolio, new
technology, etc. There are a number of factors that could cause actual results and developments to differ materially from those expressed or implied in the predictive statements. Therefore, such
information is provided for reference purpose only and constitutes neither an offer nor an acceptance. Huawei Marine may change the information at any time without notice.