Description of Work Drawing: Off Take

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 8

Off Take

Description of work Drawing

Earthfill type - B1 from


Borrow Area

+13.754

+13.084

POTONGAN Ts4 - Ts4


POTONGAN Ts4 - Ts4
SECTION
Description of work Drawing

Earthfill type - B1 from


Borrow Area

+13.754

+13.084

POTONGAN Ts4 - Ts4


SECTION
POTONGAN Ts4 - Ts4
SECTION

+13.854

+13.154 +13.154

+12.494

POTONGAN Ts4 - Ts4


SECTION
Page : 1

Calculation Quantity Keterangan

Hauling earthfill material from Borrow Area to Embankment with hauling distance
20 - 25 km

SEGMENT-1 14.58 m3

Potongan I - I L = 3.00 m

Area = 4.86 m2

Volume = area x L1
= 4.86 x 3.00
= 14.58 m3

SEGMENT-2 10.05 m3

Potongan I - I L = 20.50 m

Area = 0.49 m2

Volume = area x L1
= 0.49 x 20.50
= 10.05 m3

SEGMENT-3 10.05 m3
Potongan I - I L = 20.50 m

Area = 0.49 m2

Volume = area x L1
= 0.49 x 20.50
= 10.05 m3

SEGMENT-4 10.05 m3

Potongan I - I L = 20.50 m

Area = 0.49 m2

Volume = area x L1
= 0.49 x 20.50
= 10.05 m3

Sub Total 1 44.72 m3


Page : 2

Calculation Quantity Keterangan

SEGMENT-3 0.00 m3

Potongan Ts2-Ts2 L = m

Area = (0.5xb2xh1x2) + (bxh1)


= 1.84 + 0.43
= 2.27 m2
Volume = area x L
= 2.27 x 0.00
= 0.00 m3

SEGMENT-4 0.00 m3

Potongan Ts4-Ts4 L = m

Area J = 1.39 m2

Volume = area x L
= 1.39 x 0.00
= 0.00 m3

SEGMENT-6 0.00 m3

Potongan Ts4-Ts4 L = m
Area J = 1.09 m2

Volume = area x L
= 1.09 x 0.00
= 0.00 m3

Sub Total 2 0.00 m3


TOTAL 44.72 m3