Professional Documents
Culture Documents
District Commisioner'S Office, Lalitpur Abstract Cost
District Commisioner'S Office, Lalitpur Abstract Cost
District Commisioner'S Office, Lalitpur Abstract Cost
8.00 Providing and laying of hand pack Cobble Stone (approx size
10cmx9cmx9cm) with granular material bedding on prepared
surface as per Drawing and Technical Specifications (SS 1006). m2 1.79 6,996.82 12,491.95
9.00
Providing and laying of Plain/Reinforced Cement Concrete in
Foundation complete as per Drawing and Technical m3 1.19 14,327.09 17,052.82
Specifications. PCC Grade M 20
................... ..................
Prepared By Checked By
S.N.
Description Unit Quantities Rate (NRs.) Ammount Remarks
10.00 Providing and laying Stone Masonry work in cement mortar 1:4
in structure complete as per Drawing and Technical
Specifications Random Rubble Masonry m3 4.54 12,877.77 58,413.56
................... ..................
Prepared By Checked By
S.N.
Description Unit Quantities Rate (NRs.) Ammount Remarks
12.00
Providing and fixing cover of C.I. Grating (Medium duty) with
frame at requird level including dismentalling, concreting nut No 9.00 3,292.51 29,632.57
bolting etc. all complete as per drawing and specification.(size;
as per site) (2710 )
13.00 Providing and Laying Reinforced Cement Concrete Flush jointed
Pipe for culverts Providing and Laying Reinforced cement
concrete NP3 Flush jointed pipe for culverts including fixing
with cement mortar 1:2 as per Drawing and Technical m 45.00 3,606.78 162,305.10
Specifications. 200 mm internal dia.
VAT@13%(d) 548,434.39
Contengency@4% 168,749.04
Total 4,935,909.48
................... ..................
Prepared By Checked By
KATHMANDU VALLEY DEVELOPMENT AUTHORITY
DISTRICT COMMISIONER'S OFFICE, Lalitpur
DETAIL ESTIMATE
NAME OF PROJECT: Lalitpur metropolitan city , road construction from Nepal Dairy to coloney
Locatin: Lalitpur
S.No. Description of Work Unit No. Length Breadth Height Quantity Remarks
1.0 Subgrade Preparation m2
0+00 to 0+260 1 200.00 5.00 1000.00
2.0 Base course m3
0+093.6 to 0+097.2 1 200.00 5.00 0.15 150.00
4.0 RCC (1:1.5:3 Mix) m3
0+000 to 0+085 1 200.00 5.00 0.15 150.00
5.0 Plywood for partition m2
1st Route 52 4 0.2 41.600
................... ..................
Prepared By Checked By
KATHMANDU VALLEY DEVELOPMENT AUTHORITY
DISTRICT COMMISIONER'S OFFICE, Lalitpur
DETAIL ESTIMATE SHEET
NAME OF PROJECT: Lalitpur metropolitan city , road construction from Nepal Dairy to coloney
Locatin: Lalitpur
Detail Measurement Sheet
Cuttin Wt.
g Total Total
S.N. Description Of Work Dia(mm) No per Page Total Remarks
Lengt Length(M) Meter Quantity(Kg)
h
1 reinforcement
a Long Bar 4074.074
0+000 to 0+033 10 33 ### 6600.000 0.617 4074.074
b Short Bar 4115.226
0+000 to 0+033 10 1333 5.00 6666.667 0.617 4115.226
Total Quantity(Kg) 8189.300
add 5% for wastage 409.465
Grand total 8598.765 kg
8.599 MT
................... ..................
Prepared By Checked By
KATHMANDU VALLEY DEVELOPMENT AUTHORITY
S.No. Description of Work Unit No. Length Breadth Height Quantity Remarks
Drainage Work
7 Earthwok m3 9 1.20 10.789875
12 Grating No 9 1 9