TIME-SHEET

Name : MIKHAIL GORBACHOV SAMAL Month: Jan'19


Position : SITE INSPECTOR
Company : AECOM

Present at Present at
Date Day Weekly Rest Leave (L) Tasks Performed
Site Office home office

1-Jan-19 Tue
2-Jan-19 Wed
3-Jan-19 Thu
4-Jan-19 Fri
5-Jan-19 Sat X WEEKLY REST
6-Jan-19 Sun X WEEKLY REST
7-Jan-19 Mon √ MTHL OFFICE
8-Jan-19 Tue √ MTHL Project Site office Package-2
9-Jan-19 Wed √ MTHL Project Site office Package-2
10-Jan-19 Thu √ MTHL Project Site office Package-2
11-Jan-19 Fri √ MTHL Project Site office Package-2
12-Jan-19 Sat √ MTHL Project Site office Package-2
13-Jan-19 Sun X WEEKLY REST
14-Jan-19 Mon √ MTHL Project Site office Package-2
15-Jan-19 Tue √ MTHL Project Site office Package-2
16-Jan-19 Wed √ MTHL Project Site office Package-2
17-Jan-19 Thu √ MTHL Project Site office Package-2
18-Jan-19 Fri √ MTHL Project Site office Package-2
19-Jan-19 Sat X WEEKLY REST
20-Jan-19 Sun X WEEKLY REST
21-Jan-19 Mon √ MTHL Project Site office Package-2
22-Jan-19 Tue √ MTHL Project Site office Package-2
23-Jan-19 Wed √ MTHL Project Site office Package-2
24-Jan-19 Thu √ MTHL Project Site office Package-2
25-Jan-19 Fri √ MTHL Project Site office Package-2
26-Jan-19 Sat √ Public Holiday Republic Day
27-Jan-19 Sun X WEEKLY REST
28-Jan-19 Mon √ MTHL Project Site office Package-2
29-Jan-19 Tue √ MTHL Project Site office Package-2
30-Jan-19 Wed √ MTHL Project Site office Package-2
31-Jan-19 Thu √ MTHL Project Site office Package-2

Signature : Approved by:

Total Site office Days : 21

Total Home Office Days : 0