ID Task Task Name Duration Start Finish Predecessors April May June July August September October November

redecessors April May June July August September October November December January February
Mode W-2W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9W10W11W12W13W14W15W16W17W18W19W20W21W22W23W24W25W26W27W28W29W30W31W32W33W34W35W36W37W38W39W40W41W42W43W44W45W46W47W48
1 PROJECT WWTPO SURYACIPTA 291 days Mar 20 Feb 20
2 PEKERJAAN PERSIAPAN 70 days Mar 20 Jun 8
3 Direksikeet, peralatan kantor & gudang 25 days Apr 1 Apr 29
proyek
4 Surveying 15 days Apr 12 Apr 29 3SS+10 days
5 Pembuatan jalan akses & pemadatan 38 days Apr 12 May 26 3SS+10 days
6 Mob & demob 25 days Apr 1 Apr 29 3SS
7 Testing material 10 days May 29 Jun 8 3SS+50 days
8 Shop dwg as built dwg 7 days Apr 15 Apr 22 4SS+2 days
9 Listrik & air kerja 15 days Apr 12 Apr 29 3SS+10 days
10 Keamanan proyek & koordinasi 10 days Mar 20 Mar 31 3SS-10 days
lingkungan
11 Contraktor's all risk insurance termasuk 10 days Mar 20 Mar 31 3SS-10 days
TPL,Fire,Thelf
12 Kelengkapan PPE 10 days Apr 1 Apr 11 3SS
13 Dewatering 30 days Apr 1 May 5 3SS
14 PILE FOUNDATION 54 days Jul 12 Sep 13
15 Mob Demob Alat Pancang 7 days Jul 29 Aug 5
16 Bangunan FCR 27 days Aug 6 Sep 6
17 Supply Material Pancang FCR 21 days Aug 12 Sep 4 5FS+67 days
18 Jasa Pre Bore Ring (Wet Boring) FCR 14 days Aug 6 Aug 22

19 Jasa Hidroulic FCR 14 days Aug 6 Aug 22


20 Pengelasan Sambungan 14 days Aug 6 Aug 22
21 Loading Test Static 7 days Aug 23 Aug 30
22 PDA Test 7 days Aug 31 Sep 6
23 Bangunan Clarifier 54 days Jul 12 Sep 13
24 Supply Material Pancang Clarifier 21 days Jul 12 Aug 5
25 Jasa Pre Bore Ring (Wet Boring) Clarifier 21 days Aug 6 Aug 30

26 Jasa Hidroulic Clarifier 21 days Aug 6 Aug 30


27 Pengelasan Sambungan 21 days Aug 6 Aug 30
28 Loading Test Static 7 days Aug 31 Sep 6
29 PDA Test 7 days Sep 7 Sep 13
30 PEKERJAAN TANAH 98 days Sep 8 Dec 30
31 Bangunan FCR 98 days Sep 8 Dec 30
32 Pekerjaan Galian & Buang Galian 14 days Sep 8 Sep 23 22
33 Urugan kembali ex galian & Pemadatan 7 days Dec 23 Dec 30 101FF

34 Timbunan lereng & Pemadatan 4 days Dec 26 Dec 30 33FF


35 Potong tiang pancang 8 days Sep 12 Sep 20 32FF-2 days
36 Bangunan Clarifier 92 days Sep 15 Dec 30
37 Pekerjaan Galian & Buang Galian 14 days Sep 15 Sep 30 29
38 Urugan kembali ex galian & Pemadatan 7 days Dec 19 Dec 26 141FF

39 Timbunan lereng & Pemadatan 4 days Dec 26 Dec 30 33FF


40 Potong tiang pancang 8 days Sep 19 Sep 27 37FF-2 days
41 BANGUNAN FOOD CHAIN REACTOR 97 days Sep 9 Dec 30
42 Pekerjaan Pasir & lantai kerja 4 days Sep 22 Sep 25
43 Pekerjaan Urugan Pasir t = 10 cm 4 days Sep 22 Sep 25 32FS-2 days
44 Pekerjaan lantai kerja t = 5 cm 2 days Sep 24 Sep 25 43FS-2 days

Task Project Summary Manual Task Start-only Deadline Progress

Project: sch wwtpo Split Inactive Task Duration-only Finish-only Critical Manual Progress
Date: Aug 19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split

Summary Inactive Summary Manual Summary External Milestone Late

Page 1
ID Task Task Name Duration Start Finish Predecessors April May June July August September October November December January February
Mode W-2W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9W10W11W12W13W14W15W16W17W18W19W20W21W22W23W24W25W26W27W28W29W30W31W32W33W34W35W36W37W38W39W40W41W42W43W44W45W46W47W48
45 Plat Lantai 28 days Sep 9 Oct 10
46 Pekerjaan Pembesian 25 days Sep 9 Oct 7 44FS-15 days
47 Pekerjaan Bekisting 10 days Sep 26 Oct 7 46FF
48 Pekerjaan Beton Readymix K-350 3 days Oct 8 Oct 10 47
49 Pekerjaan Dinding 47 days Oct 8 Dec 1
50 Dinding Step 1 19 days Oct 8 Oct 29
51 Fabrikasi & Install Pembesian 14 days Oct 8 Oct 23 48FS-3 days
52 Install Bekisting 4 days Oct 20 Oct 23 51FF
53 Install Scaffolding 4 days Oct 20 Oct 23 51FF
54 Install Waterstop PVC lebar 25cm 4 days Oct 20 Oct 23 51FF

55 Cor Beton Readymix K-350 1 day Oct 24 Oct 24 54


56 Uninstall Bekisting 1 day Oct 25 Oct 25 55
57 Test Rendam 3 days Oct 27 Oct 29 56
58 Dinding Step 2 19 days Oct 24 Nov 14
59 Fabrikasi & Install Pembesian 14 days Oct 24 Nov 8 57FS-5 days
60 Install Bekisting 4 days Nov 5 Nov 8 59FF
61 Install Scaffolding 4 days Nov 5 Nov 8 59FF
62 Install Waterstop PVC lebar 25cm 4 days Nov 5 Nov 8 59FF

63 Cor Beton Readymix K-350 1 day Nov 10 Nov 10 62


64 Unistall Bekisting 1 day Nov 11 Nov 11 63
65 Test Rendam 3 days Nov 12 Nov 14 64
66 Dinding & Lantai Gutter 19 days Nov 10 Dec 1
67 Fabrikasi & Install Pembesian 14 days Nov 10 Nov 25 65FS-5 days
68 Install Bekisting 4 days Nov 21 Nov 25 67FF
69 Install Scaffolding 4 days Nov 21 Nov 25 67FF
70 Install Waterstop PVC lebar 25cm 4 days Nov 21 Nov 25 67FF

71 Cor Beton Readymix K-350 1 day Nov 26 Nov 26 70


72 Uninstall Bekisting 1 day Nov 27 Nov 27 71
73 Test Rendam 3 days Nov 28 Dec 1 72
74 Pekerjaan Balok (400x350) 14 days Nov 26 Dec 11
75 Fabrikasi Pembesian 7 days Nov 26 Dec 3 73FS-5 days
76 Install Scaffolding 7 days Nov 26 Dec 3 75FF
77 Install Bekisting 7 days Nov 26 Dec 3 75FF
78 Install Pembesian 7 days Nov 26 Dec 3 75FF
79 Cor Beton Readymix K-350 3 days Dec 4 Dec 6 78
80 Install Siku L 50.50.5 SS 304 4 days Dec 8 Dec 11 79
81 Uninstall Bekisting 2 days Dec 10 Dec 11 80FF
82 Pekerjaan Kolom (400x400) → jadi 11 days Dec 2 Dec 13
(350x350)
83 Fabrikasi Pembesian 5 days Dec 2 Dec 6 81FS-9 days
84 Install Pembesian 5 days Dec 6 Dec 11 83FS-1 day
85 Install Bekisting 5 days Dec 6 Dec 11 84FF
86 Install Scaffolding 5 days Dec 6 Dec 11 84FF
87 Cor Beton Readymix K-350 2 days Dec 12 Dec 13 86
88 Uninstall Bekisting 1 day Dec 13 Dec 13 87FS-1 day
89 Pekerjaan Jembatan Mixer 5 days Dec 11 Dec 16
90 Fabrikasi & install pembesian 2 days Dec 11 Dec 12 88FS-3 days
91 Fabrikasi & Install Bekisting 2 days Dec 11 Dec 12 90FF

Task Project Summary Manual Task Start-only Deadline Progress

Project: sch wwtpo Split Inactive Task Duration-only Finish-only Critical Manual Progress
Date: Aug 19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split

Summary Inactive Summary Manual Summary External Milestone Late

Page 2
ID Task Task Name Duration Start Finish Predecessors April May June July August September October November December January February
Mode W-2W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9W10W11W12W13W14W15W16W17W18W19W20W21W22W23W24W25W26W27W28W29W30W31W32W33W34W35W36W37W38W39W40W41W42W43W44W45W46W47W48
92 Install scaffolding 2 days Dec 12 Dec 13 90FF+1 day
93 Cor beton readymix K-350 1 day Dec 15 Dec 15 92
94 Uninstall Bekisting 1 day Dec 16 Dec 16 93
95 Pekerjaan Open Channel 10 days Dec 15 Dec 25
96 Fabrikasi & install pembesian 4 days Dec 15 Dec 18 94FS-2 days
97 Fabrikasi & Install bekisting 4 days Dec 19 Dec 23 96
98 Install scaffolding 2 days Dec 22 Dec 23 97FF
99 Cor beton readymix K-350 1 day Dec 24 Dec 24 98
100 Uninstall Bekisting 1 day Dec 25 Dec 25 99
101 Surface Protection ex ………………….. Tebal 14 days Dec 15 Dec 30 88
300 mikron
102 BANGUNAN SECONDARY CLARIFIER 78 days Sep 27 Dec 26
103 Pekerjaan Pasir & lantai kerja 4 days Sep 29 Oct 2
106 Plat Lantai 16 days Sep 27 Oct 15
107 Pekerjaan Pembesian 15 days Sep 27 Oct 14 105FS-5 days
108 Pekerjaan Bekisting 5 days Oct 9 Oct 14 107FF
109 Pekerjaan Beton Readymix K-350 1 day Oct 15 Oct 15 108
110 Pekerjaan Dinding 49 days Oct 15 Dec 10
111 Dinding Step 1 21 days Oct 15 Nov 7
112 Fabrikasi & Install Pembesian 7 days Oct 15 Oct 22 109FS-1 day
113 Install Bekisting 10 days Oct 21 Oct 31 112FS-2 days
114 Install Scaffolding 10 days Oct 21 Oct 31 113FF
115 Install Waterstop PVC lebar 25cm 10 days Oct 21 Oct 31 113FF

116 Cor Beton Readymix K-350 1 day Nov 1 Nov 1 115


117 Uninstall Bekisting 2 days Nov 3 Nov 4 116
118 Test Rendam 3 days Nov 5 Nov 7 117
119 Dinding Step 2 20 days Nov 1 Nov 24
120 Fabrikasi & Install Pembesian 7 days Nov 1 Nov 8 118FS-6 days
121 Install Bekisting 10 days Nov 6 Nov 17 120FS-3 days
122 Install Scaffolding 10 days Nov 6 Nov 17 121FF
123 Install Waterstop PVC lebar 25cm 10 days Nov 6 Nov 17 121FF

124 Cor Beton Readymix K-350 1 day Nov 18 Nov 18 123


125 Uninstall Bekisting 2 days Nov 19 Nov 20 124
126 Test Rendam 3 days Nov 21 Nov 24 125
127 Dinding & Lantai Gutter 20 days Nov 18 Dec 10
128 Fabrikasi & Install Pembesian 7 days Nov 18 Nov 25 126FS-6 days
129 Install Bekisting 10 days Nov 22 Dec 3 128FS-3 days
130 Install Scaffolding 10 days Nov 22 Dec 3 129FF
131 Install Waterstop PVC lebar 25cm 10 days Nov 22 Dec 3 129FF

132 Cor Beton Readymix K-350 1 day Dec 4 Dec 4 131


133 Uninstall Bekisting 2 days Dec 5 Dec 6 132
134 Test Rendam 3 days Dec 8 Dec 10 133
135 Pekerjaan Open Channel (lantai & 10 days Dec 11 Dec 22
dinding)
136 Fabrikasi & install pembesian 3 days Dec 11 Dec 13 134
137 Fabrikasi & Install bekisting 5 days Dec 15 Dec 19 136
138 Install scaffolding 5 days Dec 15 Dec 19 137FF
139 Cor beton readymix K-350 1 day Dec 20 Dec 20 138

Task Project Summary Manual Task Start-only Deadline Progress

Project: sch wwtpo Split Inactive Task Duration-only Finish-only Critical Manual Progress
Date: Aug 19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split

Summary Inactive Summary Manual Summary External Milestone Late

Page 3
ID Task Task Name Duration Start Finish Predecessors April May June July August September October November December January February
Mode W-2W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9W10W11W12W13W14W15W16W17W18W19W20W21W22W23W24W25W26W27W28W29W30W31W32W33W34W35W36W37W38W39W40W41W42W43W44W45W46W47W48
140 Uninstall Bekisting 1 day Dec 22 Dec 22 139
141 Surface Protection ex ………………….. Tebal 14 days Dec 11 Dec 26 134
300 mikron
142 PEKERJAAN LAIN LAIN 48 days Dec 27 Feb 20
143 Bangunan FCR 45 days Dec 31 Feb 20
144 Grating Fiber Reinforced Polyethylene 45 days Dec 31 Feb 20 41
(FRP)
145 Shading Membrane PVC High Tension 45 days Dec 31 Feb 20 41
komplit
146 Pasir pengisi lantai flocculant 3 days Dec 31 Jan 2 41
147 Railing SS 304 dia. 1.5 14 days Dec 31 Jan 15 41
148 Lampu Penerangan di FCR 1A 14 days Dec 31 Jan 15 41
149 Pengecatan dinding expose 14 days Dec 31 Jan 15 41
150 Pengecatan kolom beton shading 7 days Dec 31 Jan 7 41
151 Pengecatan pipa 4” shading 7 days Dec 31 Jan 7 41
152 Pekerjaan Jacketing Hot Pipe 14 days Dec 31 Jan 15 41
153 Pekerjaan Jacketing (rockwool 14 days Dec 31 Jan 15 41
50mm,alumunium 0.6mm,tapping
screw dan kawat)
154 Bangunan Clarifier 7 days Dec 27 Jan 3
155 Plat SS 304 tebal 4 mm, termasuk 7 days Dec 27 Jan 3 102
angkur
156 Steel Leader finish galvanized h-4 meter 7 days Dec 27 Jan 3 102

157 Kisi-kisi alumunium dimensi 4,5 x 1 7 days Dec 27 Jan 3 102


meter ex YKK
158 Jalan dan Saluran 30 days Dec 31 Feb 3
159 Perkerasan Jalan Aspal 30 days Dec 31 Feb 3 41
160 Saluran Drainase 40 x 40 cm 30 days Dec 31 Feb 3 41
161 Kansten (40x25x15x13) 28 days Dec 31 Jan 31 41
162 Lampu Penerangan PJU 28 days Dec 31 Jan 31 41
163 Grass / Penanaman rumput di lereng 28 days Dec 31 Jan 31 41
timbunan
164 Paving Block K300 tebal 6 cm setara 21 days Dec 31 Jan 23 41
Conblock

Task Project Summary Manual Task Start-only Deadline Progress

Project: sch wwtpo Split Inactive Task Duration-only Finish-only Critical Manual Progress
Date: Aug 19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split

Summary Inactive Summary Manual Summary External Milestone Late