PDA Test 7 Days Aug 31 Sep 6
PDA Test 7 Days Aug 31 Sep 6
redecessors April May June July August September October November December January February
Mode W-2W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9W10W11W12W13W14W15W16W17W18W19W20W21W22W23W24W25W26W27W28W29W30W31W32W33W34W35W36W37W38W39W40W41W42W43W44W45W46W47W48
1 PROJECT WWTPO SURYACIPTA 291 days Mar 20 Feb 20
2 PEKERJAAN PERSIAPAN 70 days Mar 20 Jun 8
3 Direksikeet, peralatan kantor & gudang 25 days Apr 1 Apr 29
proyek
4 Surveying 15 days Apr 12 Apr 29 3SS+10 days
5 Pembuatan jalan akses & pemadatan 38 days Apr 12 May 26 3SS+10 days
6 Mob & demob 25 days Apr 1 Apr 29 3SS
7 Testing material 10 days May 29 Jun 8 3SS+50 days
8 Shop dwg as built dwg 7 days Apr 15 Apr 22 4SS+2 days
9 Listrik & air kerja 15 days Apr 12 Apr 29 3SS+10 days
10 Keamanan proyek & koordinasi 10 days Mar 20 Mar 31 3SS-10 days
lingkungan
11 Contraktor's all risk insurance termasuk 10 days Mar 20 Mar 31 3SS-10 days
TPL,Fire,Thelf
12 Kelengkapan PPE 10 days Apr 1 Apr 11 3SS
13 Dewatering 30 days Apr 1 May 5 3SS
14 PILE FOUNDATION 54 days Jul 12 Sep 13
15 Mob Demob Alat Pancang 7 days Jul 29 Aug 5
16 Bangunan FCR 27 days Aug 6 Sep 6
17 Supply Material Pancang FCR 21 days Aug 12 Sep 4 5FS+67 days
18 Jasa Pre Bore Ring (Wet Boring) FCR 14 days Aug 6 Aug 22
Project: sch wwtpo Split Inactive Task Duration-only Finish-only Critical Manual Progress
Date: Aug 19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split
Page 1
ID Task Task Name Duration Start Finish Predecessors April May June July August September October November December January February
Mode W-2W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9W10W11W12W13W14W15W16W17W18W19W20W21W22W23W24W25W26W27W28W29W30W31W32W33W34W35W36W37W38W39W40W41W42W43W44W45W46W47W48
45 Plat Lantai 28 days Sep 9 Oct 10
46 Pekerjaan Pembesian 25 days Sep 9 Oct 7 44FS-15 days
47 Pekerjaan Bekisting 10 days Sep 26 Oct 7 46FF
48 Pekerjaan Beton Readymix K-350 3 days Oct 8 Oct 10 47
49 Pekerjaan Dinding 47 days Oct 8 Dec 1
50 Dinding Step 1 19 days Oct 8 Oct 29
51 Fabrikasi & Install Pembesian 14 days Oct 8 Oct 23 48FS-3 days
52 Install Bekisting 4 days Oct 20 Oct 23 51FF
53 Install Scaffolding 4 days Oct 20 Oct 23 51FF
54 Install Waterstop PVC lebar 25cm 4 days Oct 20 Oct 23 51FF
Project: sch wwtpo Split Inactive Task Duration-only Finish-only Critical Manual Progress
Date: Aug 19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split
Page 2
ID Task Task Name Duration Start Finish Predecessors April May June July August September October November December January February
Mode W-2W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9W10W11W12W13W14W15W16W17W18W19W20W21W22W23W24W25W26W27W28W29W30W31W32W33W34W35W36W37W38W39W40W41W42W43W44W45W46W47W48
92 Install scaffolding 2 days Dec 12 Dec 13 90FF+1 day
93 Cor beton readymix K-350 1 day Dec 15 Dec 15 92
94 Uninstall Bekisting 1 day Dec 16 Dec 16 93
95 Pekerjaan Open Channel 10 days Dec 15 Dec 25
96 Fabrikasi & install pembesian 4 days Dec 15 Dec 18 94FS-2 days
97 Fabrikasi & Install bekisting 4 days Dec 19 Dec 23 96
98 Install scaffolding 2 days Dec 22 Dec 23 97FF
99 Cor beton readymix K-350 1 day Dec 24 Dec 24 98
100 Uninstall Bekisting 1 day Dec 25 Dec 25 99
101 Surface Protection ex ………………….. Tebal 14 days Dec 15 Dec 30 88
300 mikron
102 BANGUNAN SECONDARY CLARIFIER 78 days Sep 27 Dec 26
103 Pekerjaan Pasir & lantai kerja 4 days Sep 29 Oct 2
106 Plat Lantai 16 days Sep 27 Oct 15
107 Pekerjaan Pembesian 15 days Sep 27 Oct 14 105FS-5 days
108 Pekerjaan Bekisting 5 days Oct 9 Oct 14 107FF
109 Pekerjaan Beton Readymix K-350 1 day Oct 15 Oct 15 108
110 Pekerjaan Dinding 49 days Oct 15 Dec 10
111 Dinding Step 1 21 days Oct 15 Nov 7
112 Fabrikasi & Install Pembesian 7 days Oct 15 Oct 22 109FS-1 day
113 Install Bekisting 10 days Oct 21 Oct 31 112FS-2 days
114 Install Scaffolding 10 days Oct 21 Oct 31 113FF
115 Install Waterstop PVC lebar 25cm 10 days Oct 21 Oct 31 113FF
Project: sch wwtpo Split Inactive Task Duration-only Finish-only Critical Manual Progress
Date: Aug 19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split
Page 3
ID Task Task Name Duration Start Finish Predecessors April May June July August September October November December January February
Mode W-2W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9W10W11W12W13W14W15W16W17W18W19W20W21W22W23W24W25W26W27W28W29W30W31W32W33W34W35W36W37W38W39W40W41W42W43W44W45W46W47W48
140 Uninstall Bekisting 1 day Dec 22 Dec 22 139
141 Surface Protection ex ………………….. Tebal 14 days Dec 11 Dec 26 134
300 mikron
142 PEKERJAAN LAIN LAIN 48 days Dec 27 Feb 20
143 Bangunan FCR 45 days Dec 31 Feb 20
144 Grating Fiber Reinforced Polyethylene 45 days Dec 31 Feb 20 41
(FRP)
145 Shading Membrane PVC High Tension 45 days Dec 31 Feb 20 41
komplit
146 Pasir pengisi lantai flocculant 3 days Dec 31 Jan 2 41
147 Railing SS 304 dia. 1.5 14 days Dec 31 Jan 15 41
148 Lampu Penerangan di FCR 1A 14 days Dec 31 Jan 15 41
149 Pengecatan dinding expose 14 days Dec 31 Jan 15 41
150 Pengecatan kolom beton shading 7 days Dec 31 Jan 7 41
151 Pengecatan pipa 4” shading 7 days Dec 31 Jan 7 41
152 Pekerjaan Jacketing Hot Pipe 14 days Dec 31 Jan 15 41
153 Pekerjaan Jacketing (rockwool 14 days Dec 31 Jan 15 41
50mm,alumunium 0.6mm,tapping
screw dan kawat)
154 Bangunan Clarifier 7 days Dec 27 Jan 3
155 Plat SS 304 tebal 4 mm, termasuk 7 days Dec 27 Jan 3 102
angkur
156 Steel Leader finish galvanized h-4 meter 7 days Dec 27 Jan 3 102
Project: sch wwtpo Split Inactive Task Duration-only Finish-only Critical Manual Progress
Date: Aug 19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split