1. The document is a request for a builder and provides specifications for utility systems for a new Factory 10 in Vietnam, including foundations for cooling towers, pumps, and control panels.
2. It also specifies the size of a sumpit, wall openings and flashing for piping, a pipe rack crossing the main road, and ceiling openings and finishing.
3. The specifications include dimensions, weights, locations, and remarks for each item to provide the necessary details for the builder to complete the utility system construction.
1. The document is a request for a builder and provides specifications for utility systems for a new Factory 10 in Vietnam, including foundations for cooling towers, pumps, and control panels.
2. It also specifies the size of a sumpit, wall openings and flashing for piping, a pipe rack crossing the main road, and ceiling openings and finishing.
3. The specifications include dimensions, weights, locations, and remarks for each item to provide the necessary details for the builder to complete the utility system construction.
Original Description:
ok
Original Title
20191118 SMC1-Factory 10 Request for Builder List Rev 01
1. The document is a request for a builder and provides specifications for utility systems for a new Factory 10 in Vietnam, including foundations for cooling towers, pumps, and control panels.
2. It also specifies the size of a sumpit, wall openings and flashing for piping, a pipe rack crossing the main road, and ceiling openings and finishing.
3. The specifications include dimensions, weights, locations, and remarks for each item to provide the necessary details for the builder to complete the utility system construction.
1. The document is a request for a builder and provides specifications for utility systems for a new Factory 10 in Vietnam, including foundations for cooling towers, pumps, and control panels.
2. It also specifies the size of a sumpit, wall openings and flashing for piping, a pipe rack crossing the main road, and ceiling openings and finishing.
3. The specifications include dimensions, weights, locations, and remarks for each item to provide the necessary details for the builder to complete the utility system construction.
Project: SMC MANUFACTURING (VIETNAM) 1st FACTORY - FACTORY 10 FOR PRODUCTION WORK Date: 29-Oct-19
Subject: UTILITY SYSTEM - Request for Builder Rev. 01
No. Item W D H Weight Set Area Location Remarks mm mm mm kg m2 1. Foundation for Cooling tower and cooling pump Concrete base for Cooling 400 x 400 x 500 6 Tower -01 2,150 Concrete base for Cooling 400 x 400 x 600 1 Tower - 01 1 Cooling Yard RFB-01 Concrete base for Cooling 400 x 400 x 500 6 Tower - 02 2,150 Concrete base for Cooling 400 x 400 x 600 1 Tower - 02 Concrete base for Cooling 2 3,000 x 2,000 x 250 756 1 Cooling Yard RFB-01 Water Pump Concrete base for Cooling 3 800 x 500 x 250 250 1 Cooling Yard RFB-01 Control Panel Concrete base for 4 submersible pump Control 400 x 500 x 250 40 1 Cooling Yard RFB-01 Panel 2. Sumpit size 1 Sumpit PD-01 2,200 x 1,300 x 1,500 1 Cooling Yard RFB-01 3. Wall opening & flashing
Steel wall opening for RFB-02
1 700 x x 300 0.21 1 Factory 10 - External wall cooling piping ( Included Flashing) Steel wall opening for FF- 2 CDA-WS-Drain piping on 1,000 x x 300 0.30 1 Factory 10 - External wall RFB-02 pipe rack - factory 10 side Brick wall opening for FF- 3 CDA-WS-Drain piping on 1,000 x x 300 0.30 1 Factory 10 - Utility RFB-02 pipe rack - Utility side Brick wall opening WS - 4 CDA piping for acid tank - 250 x x 200 0.05 1 Factory 10 - Utility RFB-02 Utility side Brick wall opening WS 5 piping for sus sink- Utility 200 x x 200 0.04 1 Factory 10 - Utility RFB-02 side Brick wall opening Drain 6 piping on pipe rack - Utility 250 x x 200 0.05 1 Factory 10 - Utility RFB-02 side 4. Pipe rack Cooling Yard => Sub- RFB-03 1 Pipe rack cross main road 1 building 2 (Design by KVN)
5. Celing opening & finishing
1 for CDA and WS Ø60mm 6 Acid clean room ceiling RFB-04