Professional Documents
Culture Documents
Chapter 3 PDF
Chapter 3 PDF
Control
Chapter 3 – Master Production
Scheduling (MPS)
The Master Schedule is:
The formal link between production
planning and actual production
The basis for calculation of resources
needed
The driving force behind the material
requirements plan
The primary priority plan for
manufacturing
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
The Master Schedule:
Works with end items.
Its breaks down the production plan into
the requirements for individual end items.
In each family, by date and quantity.
The total of the items in the MPS should
not be different from the total shown
on the production plan.
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
Objectives and Steps for the
MPS
Objectives –
Maintain good customer service
Make effective use of resources
Maintain effective levels of inventory
Accomplished by:
Develop a preliminary MPS
Check MPS against capacity and resources
Reconcile any differences
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
Information Needed to Develop
an MPS
Production Plan data
Forecasts for individual items
Actual customer orders
Inventory levels
Capacity constraints
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
Relationship to Production Plan
MPS
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
MPS Example
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
MPS Example - Develop a
preliminary MPS
1.
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
MPS Example
2.
3.
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
Rough-cut Capacity Planning -
Check MPS against capacity
and resources
Establishes whether critical resources
are available
Bottleneck operations
Critical labor resources
Critical material
Often uses a resource bill for a single
product
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
Example Resource Bill
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
Example Resource Bill
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
Example Resource Bill
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
Resolution of Differences
Compare the total time required to the
available capacity of the work centre.
If available capacity is greater than the
required capacity, the MPS is workable.
If not, method of increasing capacity have
to be investigated by adjust the available
capacity with overtime, extra workers,
routing through other work centres or
subcontracting.
If not, need to revise the MPS.
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
Resolution of Differences
Finally master production schedule must be judged
by three criteria:
Resource use
performance be acceptable?
Cost
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
Final Assembly Schedule
Assembly according to customer
schedule
Generally used in an Assemble-to-Order
environment
Many options
Too many possible final configurations to
forecast or master schedule
MPS usually done at the option level
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
Example MPS Environments
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
MPS, FAS and Other Planning
Activities
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
MPS Planning Horizon
Minimum time horizon over which the
master schedule must extend to ensure
complete planning
Calculated as the longest end-to-end
lead time of the product structure
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
EXAMPLE - Cumulative Planning
Horizon
For this product – Minimum Planning Horizon 12
weeks
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
Delivery Promises
MPS is a plan for what production can
and will do
Sales delivery promises can be made
from
“Consumption” of forecasts – Projected
available balance
Available to Promise calculations
MPS values for a given time period left after
actual customer orders are subtracted.
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
Available to Promise Example
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
Projected Available Balance
Within demand time fence (forecast not
taken into account)
PAB = Prior period PAB + MPS – customer
orders
Outside of demand time fence
PAB = Prior period PAB + MPS – greater of
customer order or forecast
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
Example of MPS with ATP and
PAB (Demand time fence at end of week 3)
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
Time Fences
Points in the planning horizon to define the
flexibility allowed in the MPS
Frozen Zone (closest to current date)
Capacity and materials committed to customer orders,
forecast generally ignored
Senior management approval for changes
Slushy Zone
Less commitment of materials and capacity
Tradeoffs negotiated between marketing and
manufacturing
Liquid Zone – All changes allowed within limits of
the Production Plan
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.
Time Fences
Introduction to Materials Management, 7th Edition © 2012, 2008, 2004, 2001, 1998, 1996 Pearson Education, Upper Saddle River, NJ 07458.
Arnold, Chapman, Clive All Rights Reserved.