Professional Documents
Culture Documents
Translated Copy of BAB - 4 - Indo
Translated Copy of BAB - 4 - Indo
WORK IMPLEMENTATION
START
Preparatory Work
Piling Work
PDA Test
Loading Test
FINISH
2. Piling Work
Piling Process is done by using two stakes, the number of dots which
must piling amounted to 1037 points. Using Square Pile measuring 40 cm
x 40 cm and depth of 30 m. in the process of piling there are several
conditions that must be held before stake.
Pile will piling must meet the age criteria specified. If the process of
piling using the HSPD stake age should be more than 8 days from the
date of excretion in the factory. Whereas when using Hammer Pile Driver,
the age of the stake to be more than 10 days from the date of production
at the plant. Caused piling depth is 30 m. then the continuation or
extension of the pile toward the upper bottom pile.
Preparatory Work
Checks
Yes
Formwork Brick
No
Checks Formwork
Yes
Cast Concrete
1. Preparatory of Work
As has been done before Piling, a point that has been marked with
Total Station then be used as pilecap manufacturing areas. Then the first
checked first pile heights, and the position of the pile by using theodolite
and waterpass auto level.
Figure 4.11. Marking point Pilecap
Start
Preparatory Work
Reinforcement Column
Yes No
Checks
Installation of Formwork
No
Checks Formwork
Yes
Cast Concrete
2. Column Reinforcement
In Tegal Transmart construction project, there are five types of
columns with different dimensions and different uses. Here is a table of
dimensions and reinforcement columns in Tegal Transmart development
projects, namely:
Table 4.2. Type of Column
formwork After the installation process, then the foundry. Before the
casting is done, it's good practice to check to see the position of
reinforcement, decking position, and the cleanliness of the premises. In
practice, casting a column using the help of Tower Crane and Bucket due
to be at a high elevation. With a catchment of 0.8 m 3 each bucket, casting
for one column can be done with one-time charge bucket or more.
Coinciding with the casting, stirring ready mix with the quality of K-
300 in concrete formwork using a vibrator to avoid the occurrence of
segregation or decrease in aggregate. And the checking of vertical
columns to check the position of the column that has not changed position.
Figure 4:27. Casting Process Column
3.5.3. Beam
The beam was a structural component that serves both support the
weight uniformly distributed load and concentrated load resting on
columns. Beams and plates is a unity in construction for floor slabs and
beams in doing casting monolithically. Process and work description of the
implementation of the general beam can be seen in the flowchart:
Start
Preparatory Work
Installation Scaffolding
Reinforcement Beam
No
Checks
Yes
Installation of Formwork
No
Checks Formwork
Yes
Cast
1. Preparatory of Work
The preparatory work on the column firstly study was contract
document (design, and specification). After preparation is complete, it will
be measured using the TST (Total Station Theodolite) and Waterpass.
The goal is to Determine the elevation of the beam.
2. Installation Scaffolding
Installation of scaffoldings a process that must be done before
doing the work made the Beam. Scaffolding aims to support the weight of
the upper reinforcement beam during the assembly process or when the
casting process.
3. Reinforcement Beam
reinforcement beams used on this project Several types of beams
with different dimensions and use of reinforcement are different Also,
According to the needs and design load calculations. The following Data
for reinforcement beams:
Table 4.3. Type of Beam
1. Preparatory Work
Preparatory work begins by determining the type of plate to be used.
Tegal Transmart in construction projects, there are two types of floor plate
is used, the type of conventional concrete slab and concrete floor plate
using a metal deck. Different types of plate, of course, different ways of
implementation.
➢ Conventional Concrete Floor plate
development Transmart At Tegal, which uses a conventional floor
plate used some Ground Floor. Due to the conventional floor plate
is more suitable if the bottom of the floor plate is in the form of land.
➢ Floor plate with Metal Deck Using a
floor plate is used pad floor 1 to floor 3. Due to the use of metal
decks, concrete requirements that are used less and load received
smaller beams and columns without reducing the strength of the
floor plate.
2. InstallationScaffolding
Installation scaffoldingis only valid on the floor plate using a metal
deck. Due to the use of scaffolding performed in conjunction with the
installation of reinforcement beams, so that the floor plate and beams into
a single entity or a monolith. In conventional concrete floor plate, only
required the installation of spacers in the form of concrete decking or hack
iron and iron foundry relat as a barrier thickness.
Figure 4:39. Installation Slab Formwork
3. SlabReinforcement of
Reinforcementthe floor plate is used in conventional floor plate only.
While on the floor using a metal deck plate, fitted only with the size of the
M7-150 wiremesh.
4. InstallationFormwork
InstallingFormwork in conventional floor plate did not use because
existing formwork barrier and is planned as one with the tie beam and
pilecap. Just before casting, a conventional floor plate floor work needs to
be given in the form of cement mortar with low quality and have ketebalah
2 cm.
While using metal decks, wiremesh just been lined with concrete
decking, and does not require bekesting. Due wiremesh and metal deck is
mounted by means of welding to the beam or column.
Therefore, they invented a tool that controls every work that takes
place in a construction job that S curve or curve Scheduling. With the tools
on this one, then every job and stages of construction work can be
monitored.