Snag Ohdc Project

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

SNAG LIST

1) Main Outlet pipe from bore well should be 3 inches

2) Water tank distribution pipes should be supported by concrete supports

3) Control valves and union valves to be fixed in pump outlets pipe

4) Manhole in fire pump room to be closed properly and suction header to be relocated as advised by
client at site

5) Floater switch to be provided in all water tanks

6) Missing vent pipe from holding tank to be provided

7) Lay one more 4 inches interconnection pipe between two holding tanks

8) All finishing fixtures invoice required to submit

9) Two individual outlet lines to be installed for both sewage pumps

10) Water proofing to be applied in both holding tanks

11) Holding maintenance access to be rectified

12) Fire breaching inlet cabinet to be properly fixed and supported

13) End cap to be fixed in spare main water inlet pipe

14) All panels should undergo load balancing according to the load consumption

15) Air condition unit to be fixed in pump room

16) Proper concrete foundation to be required for pumps in pump room

17) All pumps should require union valve installation

18) Proper access to be required to do maintenance in pump room

19) Flexible pipe connection to be required in above fire pump to manage the vibration

20) Leakage in cold water booster and transfer pump to be rectified

21) Disconnect isolator to be provided for fire pump control panel installed in pump room