Professional Documents
Culture Documents
System, Installation and Startup System CSTD CT02-023.805.02 CT02-023.814.66 PDF
System, Installation and Startup System CSTD CT02-023.805.02 CT02-023.814.66 PDF
Document Version
Siemens reserves the right to change its products and services at any time.
In addition, manuals are subject to change without notice. The hardcopy documents cor‐
respond to the version at the time of system delivery and/or printout. Versions to hard‐
copy documentation are not automatically distributed.
Please contact your local Siemens office to order a current version or refer to our website
http://www.healthcare.siemens.com.
Disclaimer
Siemens provides this documentation “as is” without the assumption of any liability under
any theory of law.
The content described herein requires superior understanding of our equipment and may
only be performed by qualified personnel who are specially trained for such installation
and/or service.
Copyright
“© Siemens, 2005” refers to the copyright of a Siemens entity such as:
Siemens Healthcare GmbH - Germany
Siemens Aktiengesellschaft - Germany
Siemens Shenzhen Magnetic Resonance Ltd. - China
Siemens Shanghai Medical Equipment Ltd. - China
Siemens Medical Solutions USA Inc. - USA
Siemens Healthcare Diagnostics Inc. - USA and/or
Siemens Healthcare Diagnostics Products GmbH - Germany
1 General Information 9
1.1 Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
1.2 Preliminary Steps for System Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
1.2.1 Preliminary Steps for Customers . . . . . . . . . . . . . . . . . . . . . . . . . . 10
1.2.2 General Preliminary Steps . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
1.2.3 Transport Device . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
1.2.4 Service Key . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
1.3 Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
1.4 Contact Address for Document Updates . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
1.5 Abbreviations, Acronyms, and Definitions . . . . . . . . . . . . . . . . . . . . . . . . . . 14
1.6 System Components Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
1.7 Safety Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
1.7.1 Working with Heavy Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . 18
1.7.2 Electrostatic Discharge (ESD) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
1.7.3 Protection Against Electrical Shocks or Hazards . . . . . . . . . . . . . . 18
1.7.4 Information Regarding Radiation Protection. . . . . . . . . . . . . . . . . 19
1.8 List of Required Installation Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
1.9 Special Installation Equipment for the Acceptance Test . . . . . . . . . . . . . . . 22
3.3 Gantry . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
3.3.1 General Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
3.3.2 Positioning the Gantry. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
3.3.3 Bolting the Gantry to the Floor . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
3.3.4 Removing the Transport Device . . . . . . . . . . . . . . . . . . . . . . . . . . 49
3.3.5 Removing the transport safety devices: . . . . . . . . . . . . . . . . . . . . 49
3.4 Patient Table . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
3.4.1 RTP Installation Sensation Open . . . . . . . . . . . . . . . . . . . . . . . . . . 52
3.4.2 Existing flooring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
3.4.3 Bolting the Table to the Floor . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
3.4.4 Remove the transport safety brackets of the PHS . . . . . . . . . . . . . 61
3.4.5 Patient Table Positioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
3.4.6 Removing the Transport Rollers . . . . . . . . . . . . . . . . . . . . . . . . . . 71
3.4.7 Variant A: Installing the Fuse Panel and Service Switch Panel. . . . 73
3.4.8 Installing the Foot Switch (in the base of the patient table). . . . . 74
3.5 PDC Cabinet (Power Distribution Cabinet) . . . . . . . . . . . . . . . . . . . . . . . . . . 76
3.5.1 General Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76
3.5.2 Positioning the PDC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76
3.5.3 Removing the Cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 77
3.5.4 Removing the Transport Bracket . . . . . . . . . . . . . . . . . . . . . . . . . . 77
3.5.5 Installing the UPS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 78
3.6 Installing the WCS (Water Cooling System). . . . . . . . . . . . . . . . . . . . . . . . . . 79
3.6.1 General Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
3.6.2 Positioning the WCS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80
3.6.3 Water Cooler Types . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80
3.6.4 Connecting the Water Hoses to the Gantry / WCS. . . . . . . . . . . . . 82
3.7 Pipe Kit (optional) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85
3.8 Attaching the Hose Connection Pieces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87
3.8.1 Connecting to the hospital's cold water supply (water-water 87
type only) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.8.2 Connecting the cool air system (water-air type only) . . . . . . . . . . 88
3.8.3 Connecting the external air fan (water-air split type only) . . . . . . 90
3.9 Containers (optional) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91
3.10 Monitor, Keyboard, Mouse, Control Box . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92
3.10.1 General Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92
3.11 ICS Computer. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 93
3.11.1 Base Foot of Tower 8. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 93
3.12 IRS2 / IRS3 Computer. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94
3.12.1 IRS Mounting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94
3.13 IRSmx. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 96
3.13.1 IRS mounting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 96
3.14 IES tower . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 97
3.15 Switch Box . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 98
3.16 UPS (provided locally, optional) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99
3.17 Ethernet Switch . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100
3.18 Multiple Socket Strip . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101
9 Documentation 247
1.1 Introduction
This document describes all steps necessary to install and start the following CT systems:
SOMATOM SENSATION 10, SENSATION 16, SOMATOM SENSATION CARDIAC, SOMA‐
TOM SENSATION 40, SOMATOM SENSATION 64, SOMATOM SENSATION CARDIAC 64,
SOMATOM SENSATION OPEN.
Every system is subject to extensive testing and adjustment processes at the factory in ac‐
cordance with specifications and is delivered in the customer-specific configuration. All
required adjustments are described in this document.
The figures in this document are used for illustration and orientation purposes. For this
reason, there may be some differences with the actual SW and HW. Always refer to the
text.
The most recent version of the documents listed above is distributed via the Siemens In‐
tranet only. These documents are not part of the system documentation.
The documents may be requested under the CS home page:
http://cs.med.siemens.de
The local planning manager is responsible for all room and system preparations. The fol‐
lowing prerequisites must be met:
n Room construction is complete and the installation site has been cleaned.
n Voltage supply and chilled water supply are available.
n Internal line impedance has been checked in accordance with the planning guide .
n Radiation protection provided (walls, doors, lead-lined windows).
n System transport route approved and checked (dimensions, access,load).
Every new Sensation CT-System is delivered with a service key (white customer binder /
valid for 1 year). A new service key has to be generated by the local Service group prior
to start-up (chapter ( System Start-Up / Page 161)). If you run into difficulties generat‐
ing the service key, contact the
CT-Hotline +49-9191-18-8080
n The following system data is required for the service key to be generated:
- System serial number
- Dongle number
The dongle is a black component mounted at the parallel port of the ICS and IES.
The dongle number is imprinted on the dongle.
1.3 Documents
The binder "Technical documentation (blue binder)" contains a complete overview of the
delivered documents and their print numbers.
The following documents are delivered with the system:
n Technical documentation (blue binder)
Contains: Installation instructions, Acceptance test instructions, Test instructions,
Safety information
n System Owner Manual
Contains: Customer and system-specific information.
n Operator Manual
Contains: Operating Instructions, Patient planning and CT logbook
n Operator Manual Wizard/syngo CTWP
Contains: Operating Instructions
n Release Notes
Designation Description
PDC Power Distribution Cabinet
PET Positrons Emissions Tomograph
PG Planning Guide
PHS Patient Handling System
PMMA Polymethylmethacrylat (Plexiglas, Acrylglas, Piacryl)
Primary cooling cir‐ Cooling circuit between the outdoor unit/on-site cooling system
cuit and the indoor unit (WCS).
RTC Rotation Tilt Controller
RTP Radiation Therapy Planning
Secondary cooling Cooling circuit between the gantry and the indoor cooling unit
circuit (WCS).
SRS Siemens Remote Service
SW Software
UPS Uninterruptable Power Supply
WCS Water Cooling System
Keep the components wrapped in the pink plastic film until they are required.
Always use ESD wristbands when touching electrical components or devices.
WARNING
Dangerous voltages (up to 560V_DC) are present when system is switched on.
Dangerous voltages (about 560V) may be present even when the system is
switched off due to capacity power.
Consequences: Risk of electric shock!
Observe poweroff instructions and discharge wait times (allow at least five
minutes discharge time after thelast scan for all involved HV and UDC parts).
Secure the system against unintended switch-on (e.g. block braker against
switching on and/or mark breaker against switch on) Ensure via measure‐
ments that all voltages are switched off. Connect the stationary and rotating
parts of the gantry to a protective conductor prior to working in the gantry.
All necessary radiation protection measures must be performed prior to releasing radia‐
tion.
All personnel working on the installation must wear a dosimeter to monitor their radia‐
tion exposure.
A detailed list of service tools is located in Intranet product documentation > spare parts
catalogue > Test Tools catalogue
n The following instructions refer to standard sea/air freight with all components in
wooden crates.
n Protective clothing must be be worn for your personal safety (safety shoes, gloves,
etc.).
2.3 Gantry
n Place the gantry container on the floor.
n Remove the nails from the wooden crate.
n Remove the top and sides of the crate.
n Remove the mounting screws (4 screws at each corner) from the two yellow mount‐
ing brackets holding the gantry on the pallet( Fig. 2 Page 25).
n Remove the two mounting brackets.
Fig. 2: Gantry transport pallet, mounting device/screws
Special screws (M12 x 70, part no. 48 23 261) must be used to attach the gantry trans‐
port device.
Adhere to the warning labels on the transport device. ( 3/Fig. 3 Page 26).
n Position the transport device on both sides of the gantry( Fig. 3 Page 26) .
- Avoid damaging the gantry when attaching the transport device.
n Turn the centering screw ( 2/Fig. 3 Page 26)through the transport device and into
the recess in the gantry stand .
n Use the centering screw to adjust the distance between the gantry and transport de‐
vice. The distance should be equal on both sides.
n Attach the mounting screws( 1/Fig. 3 Page 26) through the centering screws and
tighten at a torque of 77 Nm ±10%. Adhere to the instructions on the transport de‐
vice.
n Lower the four transport wheels by turning the spindles in clockwise direction. Insert
a metal rod through the upper spindle holes in order to make the spindle easier to
turn.
n Turn the spindle until the distance between the gantry and pallet is approx. 5-10 mm.
n Move the gantry to the right and remove the pallet.
n Lower the gantry by turning the spindles in counterclockwise direction until the dis‐
tance between the gantry and floor is approx. 15 mm.
Maintain the minimum distance from the floor to prevent the gantry from hitting the
ground.
n Gantry installation is continued in chapter ( Installing the Components / Page 42) "
register.
1
3
2
n Remove the fastening straps and then remove the package (from the table).
n Remove the connecting frame from the pallet:
- Remove the connecting frame cover by removing the 4 screws.
- Remove the two screws securing the connecting frame to the pallet.
n Remove the four mounting screws at the table base.
n Remove the wooden board attached to the patient table( Fig. 4 Page 27)
- This board has two important functions:
1. As a ramp to safely move the patient table off the pallet.
2. As a drilling template for bolting the patient table to the floor. Æ
n Remove the wooden block nailed to the wooden panel( Fig. 4 Page 27).
n Place the wooden board at the front edge of the pallet (head end of the patient table)
and attach the board with two screws at the positions shown in .
( 2/Fig. 5 Page 28)
n Place the wooden block under the wooden board to prevent the board from bending
( 1/Fig. 5 Page 28) . Lift the patient table by turning the two screws at the right and
left transport rollers, and the 1 screw at the rear transport roller, until the table can be
moved ( Fig. 7 Page 28) ( Fig. 6 Page 28).
n Carefully move the patient table down the ramp to the floor.
n Remove the wooden board (ramp) from the pallet and place it on the table. The board
will be used later as the drilling template for mounting the patient table.
n Patient table installation continues in the chapter ( Installing the Compo‐
nents / Page 42)
5 1
3
1
2 4
Fig. 10: WCS cabinet with pallet Fig. 11: WCS cabinet attachment points to pallet
5 1
3
1
5
2 4
Fig. 12: Console (120 or 140 cm) Fig. 13: Container for ICS and IES computer
Fig. 15: Transport brackets and unpacking tools Fig. 16: Transport brackets and unpacking tool
n Remove the wooden slats and cover from the transport bracket ( 1/Fig. 14 Page 32)
n Remove both wooden beams (lower left/right) ( 2/Fig. 15 Page 32)
n Remove the wedges (left/ right ) ( Fig. 15 Page 32)
Be careful when removing the wedges; the pallet tilts forward.
n Use both wedges as a ramp to roll the IRS off the pallet ( Fig. 16 Page 32)
n The IRS is mounted on the wall using 2 L-brackets and washers. It is bolted to the floor
at 4 places inside the IRS. Refer to ( Installing the Components / Page 42) for a de‐
tailed description
To prevent it from falling over, the IRS has to be mounted on the wall or bolted to the
floor with the materials provided. In earthquake zones, both floor and wall mounting are
required.
Fig. 17: IRS transport wheels Fig. 18: IRS transport equipment
n Use both wedges as a ramp to roll the IRS off the pallet ( Fig. 16 Page 32)
n The IRS is mounted on the wall using 2 L-brackets and washers. It is bolted to the floor
at 4 places inside the IRS. Refer to ( Installing the Components / Page 42) for a de‐
tailed description
To prevent it from falling over, the IRS has to be mounted on the wall or bolted to the
floor with the materials provided. In earthquake zones, both floor and wall mounting are
required.
1. Remove all nails and fasteners with the pry bar if necessary.
2. Remove the top and sides of the wooden crate if necessary.
2.10.3 Transporting
Move the IRS on its rollers near its final installation location.
Do not move the IRS over uneven sections of the floor. Vibrations can damage the IRS.
Large obstructions can break the wheel mountings.
Fig. 22: ICS monitor and accessories Fig. 23: ICS computer
The patient table must be bolted to the floor.
Some countries (earthquake-prone areas) require special floor mounting for the gantry.
Refer to ( Special Component Mounting / Page 102).
The tabletop of the “RTP patient table” is a flat tabletop. This flat tabletop is higher than a
standard curved tabletop. For this reason, it is not possible to open or close the gantry
Fig. 27: Tilt converter Fig. 28: MCU (gantry left stand)
It is not permitted to crane the CT gantry by its transport frame.
For further craning information, please refer to the Planning Guide.
Adhere to all personal safety information prior to beginning work (e.g., safety shoes,
gloves, etc.).
Maintain the recommended safety distances from the wall for all moveable components
(gantry, patient table, etc.).
Please note that access is required to enable service activities for certain components
(e.g., left/right gantry stand) Adhere to the requirements described in the Planning
Guide.
n Wear protective gear when working with heavy equipment (Safety shoes, gloves,
etc.).
n To prevent components from tipping over, the distance between components and the
floor should not exceed 15 mm (approx. 1/2 inch).
n Transporting components: Components may only be transported to the examination
rooms along the approved transport route.
3.3 Gantry
For RTP (Radiation Therapy Planning) the Sensation Open gantry installation has to be
highly accurate. Pay attention to the hints “ RTP installation (Sensation Open only)”
respectively “Normal installation” this chapter.
The gantry has to stand on 4 adjustable feet.
The adjustable feet, respectively the distance plates at RTP (Sensation Open) must have
direct contact with the concrete floor (do not place the adjustable feet / distance plates
on a soft floor covering).
Remove the existing flooring in the area of the installation support surface area.
For normal installations, replace the removed flooring with a shim of appropriate thick‐
ness (not necessary for RTP installation).
Do not push or pull the plastic cover on the gantry; this could result in misalignment of
or damage to the cover.
The gantry should not be transported over uneven flooring. Hard bumps against the
gantry may damage its more sensitive parts (such as the ball bearings).
When transporting the gantry over doorways and in corridors, always check the height
to prevent collisions.
Fig. 30: Position of the adjustment screws Fig. 31: Gantry with installed transport device
n Prior to lowering the gantry, ensure that the 4 adjustment screws are not visible from
the gantry base( 1/Fig. 30 Page 46).
Fig. 32: Levelling the gantry (left) Fig. 33: Levelling the gantry (top)
n After leveling is complete, check whether the gap under the gantry is not less than 1.5
mm (at the lowest point).
n Unscrew the adjustment screws until they contact the floor. Slightly retract the adjust‐
ment screws.
n Lower the gantry until all weight is off the transport wheels.
n Check the leveling again.
- The gantry should not wobble.
- The gantry has be standing on its own.
- The gap under the gantry should be not less than 1.5 mm (but as small as possible).
Fig. 34: Leveling the gantry Fig. 35: Leveling gantry top
n After leveling is completed, check whether the gap between the underside of the gan‐
try and the floor is not less than 21 mm and not more than 24 mm.
n Place a distance plate with the relief on top under each adjustment screw
( Fig. 36 Page 48).
Fig. 36: Gantry stand, distance plate Fig. 37: Gantry stand, center pin
n Put a center pin through each adjustment screw to center the distance plate under the
adjustment screw ( 1/Fig. 37 Page 48).
n Loosen the adjustment screws (clockwise) until they contact the distance plate. Slight‐
ly retract the adjustment screws.
n Lower the gantry until all weight is off the transport wheels.
n Check the leveling again.
The gap between floor and underside of the gantry must be between 21 mm and 24
mm.
Otherwise, the “RTP Base Cover” cannot be installed. Refer to( RTP base cover installa‐
tion of the Gantry/Patient table / Page 227).
- The gantry should not wobble.
- The gantry has to be standing on its own.
- The gantry frame should not contact the distance plates.
(1) screws
(2) centering screws
- Loosen and remove the signal and grounding cable (middle right).
- Lift and remove the gantry back panel (2 persons are required).
After the transport safety devices are removed, all parts must be collected and stored
with the customer's system equipment.
The gantry is equipped with the following transport safety devices ( Fig. 39 Page 50)
and ( Fig. 40 Page 50):
Fig. 39: Overview of transport brackets Fig. 40: Parts of tilt transport safety device
n Back of gantry:
- 4 rubber spacers installed between the rotating and stationary unit, at 1, 5, 7, and
11 o’clock positions. The rubber spacers are installed as shock absorbers.
- 1 metal plate with 4 Allen screws. The metal plate is mounted behind the slip ring
unit at the 3 o’clock position.
n Front of gantry:
- 4 Allen screws on the rotating unit. The screws are to the left and right of the X-ray
tube assembly and to the left and right of the DMS.
- Remove the four rubber spacers at the back of the gantry ( Fig. 41 Page 50).
- Remove the four Allen screws from the metal plate at the back of the gantry
( Fig. 42 Page 50).
- Remove the four Allen screws from the front of the gantry (rotating section).
- Store the transport brackets with the other service tools in a secure location in case
they are needed at a later date.
- Unlock the rotary protection (1 o'clock position on the rotating part) and carefully
rotate the gantry by hand. Make sure all the transport brackets have been removed.
- Close the front panel of the gantry and tighten the two screws (lower left and
right).
- Before attaching the back panel of the gantry, connect the signal and grounding ca‐
ble. Attach the gantry back panel.
- Tighten the two attachment screws on the back panel.
n Right gantry stand:
- In the right gantry stand, a tilt safety device is installed on the rocker arm. This tilt
transport safety device is available for newer systems only.
- Remove the screw and the L-shaped shim plates ( Pos. 1 and 2/Fig. 43 Page 51).
Fig. 43: Tilt transport safety device
(1) Screw
(2) L-shaped shim plate
For RTP (Radiation Therapy Planning) the installation of the Sensation Open patient
table has to be highly accurate. Pay attention to the hints “ RTP installation (Sensa‐
tion Open only)” respectively “Normal and Bariatric installation” in this chapter.
Remove the existing flooring in the area of the installation support surface area
For normal installations replace the removed flooring with a shim of appropriate thick‐
ness (not necessary for RTP installation).
Bolting the table to the floor is mandatory. Use all 6 drill holes.
The materials provided are intended for attaching the table to the floor using anchors
and screws. For any other type of attachment, the project manager must decide how to
proceed. In this case, the project manager must obtain the required materials.
During the RTP table installation of the Sensation Open, a gantry Z-laser will be used to
adjust the drilling template orthogonally to the scan plane.
For an RTP patient table with a flat tabletop, you have to tilt the gantry in the negative
n Connect the power supply at the laser and the local power ( 1/Fig. 45 Page 53).
n Attach a plumb line at approximately 200 cm height to the wall opposite the gantry.
n Rotate the gantry until the gantry Z-laser (12 o‘clock position) ( 1/Fig. 46 Page 54)
and the plumb line ( 2/Fig. 46 Page 54) are congruent. Mark the laser (at three
points) at the wall.
n Rotate the gantry until the gantry Z-laser (6 o‘clock position) ( 1/Fig. 46 Page 54) and
the plumb line ( 2/Fig. 46 Page 54) are congruent.
n Check the tolerance between the Z-laser (at 6 o‘clock) and the 12 o‘clock marking. De‐
pendent on the distance, the following tolerance is acceptable:
If the Z-laser is not in tolerance, align the drilling template as for a “normal and
bariatric installation” ( Normal and / Page 64). Please note that table alignment
with the Z-laser is preferred.
If the gantry Z-laser adjustment is in tolerance, continue with ( Drilling and adjusting
the drilling template (RTP installation only) / Page 55).
Fig. 47: Position drilling template Fig. 48: Adjust drilling template
n Place the drill sleeve ( 1/Fig. 49 Page 55) into the holes of the transport ramp
( 2/Fig. 49 Page 55).
Fig. 49: Drilling template Fig. 50: Pre drill the anchorage points
n Predrill the patient table anchorage points with a 8 mm drill through these drill sleeve
( Fig. 50 Page 55). The position of the transport ramp cannot be moved during the
drilling.
n Remove the drilling template.
If you have an RTP kit, you have to install the connecting frame later. Refer to ( RTP
table prepositioning / Page 69).
n The connecting frame is positioned between the patient table and gantry.
n The connecting frame must be centered to the gantry. Use a tape measure to measure
the connecting frame position referenced to the outer edges of the gantry. Pay atten‐
tion to the cable exiting from the connecting frame.
Deviations from the center may not exceed 1 mm.
Fig. 51: Connecting Frame Gantry
n When positioning is complete, attach the connecting frame to the gantry with the
screws (M10x30) ( 1/Fig. 51 Page 56) and washers provided.
n Push the connecting frame to the floor with the screws (clockwise)
( 2/Fig. 51 Page 56).
If you have a Sensation Open System with RTP Kit, do not tighten the screws
( 2/Fig. 51 Page 56) yet. The screws must be tightened after the final table adjust‐
ments. Refer to ( Completing steps / Page 202).
3.4.3.4 Installation instruction for anchors (Normal, Bariatric and RTP installation)
n The drilling procedure is described on pages ( Fig. 52 Page 58)
( Fig. 53 Page 60) step D-I (anchor installation, type IL S 14/80).
Use "Liebig anchors" to attach the patient table to the floor. The following tools are re‐
quired for proper installation:
n Pencil
n Drill
n Vacuum cleaner (to clean the drill holes)
n Hammer
n Allen socket size 6 for torque wrench
n Allen socket size 8 for torque wrench
n Torque wrench (9 - 25 Nm)
The following materials are included in the delivery volume and are used for Variation 1
or 2:
- 1 drill bit BB 14/260, (1)(diameter 14 mm, length 260 mm)
- 6 Liebig anchors, (2) and (3)
- 6 hexagon screws 8x30 (4)
- 6 Allen screws 8x110 (5)
- 1 Loctite No. 221 (6)
- For RTP installation only: Special wrench for the patient table adjustment feet
The figures show how to correctly install the anchors. The drawings describe the process
steps. Please note the drawings are not to scale.
Variation 1
Variation 2
Fig. 53: Installation instructions for anchors in a concrete flloor (with a floor covering)
After the transport safety devices are removed, all parts must be collected and stored
with the customer's system equipment.
n Remove the transport bracket at the back of the tabletop ( Fig. 54 Page 61).
- Remove the plastic cover at the back of the tabletop ( Fig. 54 Page 61).
- Remove the 4 Allen screws at the transport bracket ( Fig. 54 Page 61).
n Remove the transport bracket under the tabletop ( Fig. 55 Page 61).
- Move the tabletop toward the gantry until you can see the transport bracket.
- Remove the 3 hexagonal screws and then the transport bracket ( Fig. 55 Page 61)
n Remove the vertical transport bracket near the base of the gantry
( Fig. 56 Page 62), ( Fig. 57 Page 62), ( Fig. 59 Page 63),
( Fig. 60 Page 63), ( Fig. 58 Page 62).
The load is taken off the table spindle during transport. Follow the directions printed on
the vertical transport base ( Fig. 59 Page 63).
For basic units Sensation Cardiac serialnumber 52000 until 52003 and Sensation16 seri‐
alnumber 50000 until 50039 the motorcontroller has to be removed, to become the mo‐
If necessary:
n Disassemble the motor controller by removing the screws marked "A" in
( Fig. 56 Page 62).
n Carefully move the motor controller to the left ( Fig. 57 Page 62).
n The motor axle becomes visible.
Fig. 56: Mounted motor controller Fig. 57: Disassembled motor controller
Manual / mechanical lifting of the patient table with a ratchet is slow, but it is the only
way to move the table up or down without power. When moving the table, do not ex‐
ceed the mechanical end stops.
n Using a ratchet and a 13 mm hexagonal socket at the motor axle, back turn the motor
manually by 2 counterclockwise rotations until the table moves upward.
- Remove the 3 screws (2 below, 1 above) from the red metal plate
( 1/Fig. 59 Page 63)
- Use the ratchet to raise the table a few rotations until the transport bracket is freely
moveable.
- Remove the transport bracket (large red metal plate ( 1/Fig. 59 Page 63)
- Remove the transport bracket (small red metal plate under the tabletop;
( 1/Fig. 60 Page 63). The tabletop has to be pushed forward. Manually raise the
table.
Fig. 59: Vertical transport bracket #3 Fig. 60: Upper transport bracket #3
n Using the ratchet, extender, and a 13 mm hexagonal socket, raise the patient table to
a height of 1000 mm to provide better access to the inside of the table. The 1000 mm
are measured from the upper edge of the patient table to the floor. Installing the Ta‐
ble Covers
n Install the white metal covers provided under the tabletop ( 2/Fig. 61 Page 64).
- Push the cover from the foot-end of the patient table until it abuts the front cover.
- Attach the covers with the Allen screws provided (screws with flat plastic heads).
n Install the white covers provided at the foot-end of the patient table.
- Adjust and attach the cover with 2 Allen screws (flat plastic head;
( 1/Fig. 61 Page 64)).
n Install the covers previously removed ( 2/Fig. 54 Page 61) from the ends of the table
( 3/Fig. 61 Page 64)).
For RTP (Radiation Therapy Planning) the installation of the Sensation Open patient
table has to be highly accurate. Pay attention to the hints “ RTP installation” respec‐
tively “Normal installation” and “Bariatric installation” in this chapter.
n Center the patient table at the spacer. Measure the distance from the front edges of
the patient table to both sides of the spacer.
- Deviations from the center may not exceed 1 mm.
n Lower the table to the floor.
- To lower the table, turn the hexagonal screws on the transport rollers in counter‐
clockwise direction until the table is resting on the floor and the transport rollers
can move freely.
n Check the table position with respect to the gantry using a tape measure.
- Measure distances a/a’, b/b’ and c/c’ as shown in ( Fig. 62 Page 65).
- Compare the measured values with the tolerance permitted for distances a/b/c as
shown in( Fig. 62 Page 65) , upper right.
- Correct the distances if necessary until they are within tolerance.
n Level a normal table:
- Place a water level on the patient table ( 1/Fig. 62 Page 65)
- Align the patient table with the small metal plates (provided) to 0.0˚ (± 0.5˚).
- If the table is not level, the small metal plates (provided) must be placed under the
table. They should be placed near the floor mounting bolts.
n Level a Bariatric table (Part no. 7729697):
- Place a digital water level on the patient table ( Fig. 63 Page 66)
- Align the patient table with the small metal plates (provided) to 0.0˚ (± 0.2˚).
- The small metal plates must be placed under the table. They should be placed near
the floor mounting bolts.
n Attach the connecting frame to the patient table using the 2 screws and washers pro‐
vided. Refer to ( Installing the connecting frame - part 2/2 (table) / Page 71).
n Check the distances again ( Fig. 62 Page 65) and correct, if necessary.
n Bolt down the table using the 6 screws and washers provided (as shown in Figure J on
( Fig. 52 Page 58)( Fig. 53 Page 60)
- Secure the mounting bolts with Loctite 221.
- The two screws at the center of the table are attached using special washers. To
prevent collisions, the flat side of the washer has be parallel to the travel rails of the
patient table. Refer to ( Fig. 81 Page 72).
n Tighten the 6 mounting bolts at a torque of 20 Nm (± 10%).
n Level the adjustment screws to the lowest position ( 1/Fig. 64 Page 66).
n Take a water level (min. 1.2 m) with a digital spirit level on the top and place it diag‐
onally and vertically over the adjustment screws and align the screws
( 2/Fig. 64 Page 66) to 0.0˚ ±0.1˚.
Ensure that the adjustment screw does not protrude by more than 5 mm (5 ro‐
tations) ( 3/Fig. 74 Page 70). If necessary, put shims under the adjustment
feet ( 2/Fig. 74 Page 70) so that the adjustment feet are adjustable in up‐
ward direction for approx. 4 rotations.
n Move the adjustment feet to the side ( 1/Fig. 65 Page 67).
n Move and position the patient table over the six anchors.
n Lift the patient table with a crowbar ( 2/Fig. 66 Page 67)and move the adjustment
feet over the anchors ( 1/Fig. 66 Page 67).
n Remove the transport rollers of the patient table. Refer to ( Removing the Transport
Rollers / Page 71).
Fig. 65: RTP table - final position Fig. 66: RTP lift table
n Slightly bolt down the table (do not tighten the screws yet) using the 6 screws and
washers provided as shown in Figure J on ( Fig. 52 Page 58) ( Fig. 53 Page 60).
Loctite is not needed.
During RTP installation (Sensation Open only), the distance between the gantry/patient
table bottom line and flooring is too large. Compensate for the gap with a spacer plate .
plates are required, the plates have to be connected using two clamping sleeves; see
( 1/Fig. 67 Page 68), ( 1/Fig. 68 Page 68), ( 1/Fig. 69 Page 68).
n Position the spacer plate and the connecting frame between the gantry and patient
table as shown in ( Fig. 70 Page 68).
Fig. 69: Spacer plate detail figure Fig. 70: Spacer plate with connecting frame
For an RTP patient table with a flat tabletop, you have to tilt the gantry in the negative
n Install the connecting frame. See ( Installing the connecting frame - part 1/2 (at gan‐
try) / Page 56) and ( Installing the connecting frame - part 2/2 (table) / Page 71).
Pay attention to the cable exiting from the connecting frame.
n Open the gantry front cover .
n During the RTP table installation, the Sensation Open gantry Z-laser will be used to
align the patient table orthogonally to the scan plane. Position the gantry Z-laser in
the 12 o'clock position.
n Connect the power supply at the laser and the local power ( 1/Fig. 45 Page 53).
n Attach a plumb line at approximately 200 cm height to the wall opposite the gantry.
n Rotate the gantry until the gantry Z-laser ( 1/Fig. 46 Page 54)and the plumb line
( 2/Fig. 46 Page 54)are congruent. The position of the Z- laser cannot be changed for
the following mounting steps.
n Lift the patient table up to 920 mm from the top edge to the patient table base (not
to the floor).
n Position the patient table so that the center line of the patient table
( 2/Fig. 71 Page 69) and the gantry Z-laser ( 1/Fig. 71 Page 69) are congruent.
To move the table in the X-direction, use the adjustment screws on the adjustment
feet ( 1/Fig. 72 Page 69).
Put a shim plate between table and screw to protect the surface.
Fig. 71: RTP table adjustment Fig. 72: RTP table adjustment X-direction
n Do not move the tabletop out of the top support. Place the RTP phantom
( 1/Fig. 73 Page 70) on the table with the adjustment feet ( 5/Fig. 73 Page 70)
Fig. 73: RTP table adjustment in X and Z directions Fig. 74: RTP table adjustment feed
n Put the digital water level on the RTP phantom as shown in ( 2/Fig. 73 Page 70)
( 3/Fig. 73 Page 70), but with the tabletop retracted.
n Perform angle measurements at the tabletop front, tabletop center and tabletop end.
n Align the patient table with the adjustment feet in the X-direction to 0.0 ±0.1 and
align it in the Z-direction to 0.0˚ ± 0.2˚ ( 1/Fig. 74 Page 70).
This table pre-aligment for the table incline in X- and Z-direction can be also executed
with the instructions in chapter ( Patient Table Aligment for / Page 201).
You then have to check the angle tolerances in X- and Z-direction in a later chapter.
- For aligment in X-direction, adjust the same feet height for all three feet at one
side.
- For aligment in Z-direction, adjust the same feet height for the two middle feet.
Unscrew the corresponding table screws beforehand. Ensure that the adjustment
screw does not protrude by more than 5 mm (5 rotations) ( 3/Fig. 74 Page 70). If
necessary, put shims under the adjustment feet ( 2/Fig. 74 Page 70) so that the ad‐
justment feet are adjustable in upward direction for approx. 4 rotations.
The two screws at the center (see ( Fig. 81 Page 72)) of the table are at‐
tached using special washers. To prevent collisions, the flat side of the wash‐
er has be parallel to the travel rails of the patient table.
n Check if the center line of the patient table is congruent with the gantry Z-laser
( Fig. 71 Page 69).
n Bolt down the table slightly using the 6 screws and washers provided (without Loc‐
tite).
n Verify the center line of the patient table is congruent with the gantry Z-laser
( Fig. 71 Page 69).
n Verify whether the X and Z-table positions are within tolerance ( Fig. 73 Page 70).
If you have an RTP kit, you have to install the connecting frame later. Refer to ( RTP
table prepositioning / Page 69).
n The connecting frame is positioned between the patient table and the gantry.
Fig. 75: Connecting Frame patient table
n Attach the connecting frame to the patient table with screws (M10x30)
( 1/Fig. 75 Page 71) and washers provided.
n Push the connecting frame to the floor with the screws (clockwise)
( 2/Fig. 75 Page 71).
If you have a Sensation Open System with RTP Kit, do not tighten the screws
( 2/Fig. 51 Page 56) yet. The screws must be tightened after the final table adjust‐
ments. Refer to ( Completing steps / Page 202).
n Variant B (newer systems): The attachment point of the transport rollers is at another
position. The fuse panel and the service switch panel are already mounted
( Fig. 78 Page 72) ( Fig. 79 Page 72).
Fig. 76: Transport roller (front/left) Fig. 77: Transport roller (front/right)
(1) bolts
(2) screws at the top of the transport roller
Fig. 78: Variant B: Transport roller (front/left) Fig. 79: Variant B: Transport roller (front/right)
Fig. 80: Transport roller (rear/center) Fig. 81: Screw attachment (center)
n The transport rollers are removed once the patient table has been bolted to the floor.
3.4.7 Variant A: Installing the Fuse Panel and Service Switch Panel.
During transport, the fuse panel and service switch panel are attached behind the left and
right transport rollers with cable ties.
n Fuse panel (left side of the patient table) ( Fig. 82 Page 74)
- Cut the cable ties and position the fuse panel in the recess provided.
- Attach the support plate to the base of the patient table (using the screws previous‐
ly removed from the transport roller support bracket).
- Tighten both screws to secure the fuse panel.
- Be careful when working inside the patient table to prevent cables from being dam‐
aged.
- Ensure that the cables are not damaged by moveable parts of the patient table. Se‐
cure loose cables with cable ties.
n Service switch panel (right side of the patient table) ( Fig. 83 Page 74)
- Cut the cable ties and position the service switch panel in the recess provided.
- Attach the support plate to the base of the patient table (using the screws previous‐
ly removed from the transport roller support bracket).
- Tighten both screws to secure the service switch panel.
- Be careful when working inside the patient table to prevent cables from being dam‐
aged.
- Ensure that the cables are not damaged by moveable parts of the patient table. Se‐
cure loose cables with cable ties.
Fig. 82: fuse panel (left) Fig. 83: servide switch panel (right)
3.4.8 Installing the Foot Switch (in the base of the patient table)
Fig. 84: Foot switch kit (overview)
Fig. 85: Foot switch (rear right) Fig. 86: Foot switch (back left)
(A) M4 x 10 xcrew with contact disk (A) M4 x 10 xcrew with contact disk
(B) M4 x 20 screw with contact disk (B) M4 x 20 screw with contact disk
(C) Offset bushing (C) Offset bushing
Fig. 87: Foot switch (front left) Fig. 88: foot switch (rear left)
(A) M4 x 10 xcrew with contact disk (A) M4 x 10 xcrew with contact disk
(B) M4 x 20 screw with contact disk (B) M4 x 20 screw with contact disk
(C) Offset bushing (C) Offset bushing
n Insert the foot switch in the recesses in the base of the patient table, and attach it us‐
ing the screws, contact disks, and offset bushings provided. Refer to
( Fig. 84 Page 74) ( Fig. 85 Page 75) ( Fig. 86 Page 75) ( Fig. 87 Page 75)
( Fig. 88 Page 75) for foot switch alignment and attachment. ( Fig. 84 Page 74)
presents an overview of the parts required for installation.
n Connect the foot switch to the connectors provided in each recess and the check the
mechanical function. Affix the connection cable to the base of the patient table.
In countries with special regulations (earthquake-prone areas), refer to ( PDC and WCS
Housing / Page 106).
CAUTION
Installation of the UPS in the PDC during transport.
Consequence:Tipping hazard !
Countermeasure:The UPS shall not be installed in the PDC during transport.
Remove the UPS whenever transporting or changing the position of the PDC.
n Cables should be routed in an organized, structured manner at the bottom of the PDC
(no rolled-up cables).
In countries with special regulations (earthquake-prone areas), refer to ( PDC and WCS
Housing / Page 106).
The wall connections for air intake/outlet in the building must be ordered separately
or organized locally (refer to the "planning guide" for details).
- Accessories: The following accessories are included in the WCS delivery volume:
Manometer and connection hose to monitor the water pressure.
Two connectors for the filling and draining hose connections for the WCS.
It is prohibited to switch on the water pump in the WCS prior to filling the water circula‐
Connection of the gantry water supply is the same for the water-water, water-air and
water/air split WCS.
The water hoses have imprinted directional arrows. When routing the hoses, ensure that
the arrows on the water hoses show the water flow.
Fig. 96: water hose connection gantry Fig. 97: water hose connection gantry
n Connect the water hose with the red mark to the "water outlet" in the right gantry
stand (connection in back; ( Fig. 96 Page 83) ( Fig. 97 Page 83)
n Connect the water hose with the blue mark to the "water inlet" in the right gantry
stand (connection in the front; ( Fig. 96 Page 83) ( Fig. 97 Page 83))
n Tighten the connections.
Type A : Use size 36 and 40 hexagonal wrenches to tighten the connections
( Fig. 96 Page 83).
Type B : Use size 40 hexagonal wrench to tighten the connections ( Fig. 97 Page 83).
Fig. 98: Water hose connection WCS (right)
n Shorten the water hoses to the length required (using a sharp knife or hand saw) and
attach the connecting pieces. Refer to the installation instructions for the connecting
pieces on ( Attaching the Hose Connection Pieces / Page 87).
n Attach the hose with the red mark from the gantry to the "gantry water inlet" at the
WCS (left connection) ( Fig. 98 Page 83)
n Attach the hose with the blue mark from the gantry to the "gantry water outlet" at
the WCS (right connection) ( Fig. 98 Page 83)
n Use size 36 and 40 hexagonal wrenches to tighten the connections.
n Route the hoses from the gantry to the on-site pipes. Shorten the water hoses to the
length required (using a sharp knife or hand saw) and attach the connecting pieces.
Refer to the installation instructions for the connecting pieces on ( Attaching the
Hose Connection Pieces / Page 87).
Please note that the excess length must be long enough to connect the other
side of the on-site pipes with the WCS.
n Attach and tighten the pipe kit adapter ( Fig. 100 Page 85) to the on-site pipes.
You cannot connect the adapter directly to the on-site pipes. The on-site part
of the adapter must be sealed!
n Attach the hose to the on-site pipes.
Fig. 100: Adapter - hose to pipe
n At the other side of the on-site pipes, route the hoses from the on-site pipes to the
WCS. Shorten the water hoses to the length required (using a sharp knife or hand
saw) and attach the connecting pieces. Refer to the installation instructions for the
connecting pieces on ( Attaching the Hose Connection Pieces / Page 87).
n Attach and tighten the pipe kit adapter ( Fig. 100 Page 85) to the on-site pipes.
You cannot connect the adapter directly to the on-site pipes. The on-site part
of the adapter must be sealed!
n Attach the hose to the on-site pipes.
- Mark the previously connected hose with the same color as the connected hose of
the on-site pipe’s other side.
n Remove the caps from the end of the water hoses and route the hoses to the connec‐
tions in the WCS ( Fig. 98 Page 83).
n Attach the hose with the red mark from the gantry to the "gantry water inlet" at the
WCS (left connection) ( Fig. 98 Page 83).
n Attach the hose with the blue mark from the gantry to the "gantry water outlet" at
the WCS (right connection) ( Fig. 98 Page 83).
n Use size 36 and 40 hexagonal wrenches to tighten the connections.
Fig. 103: Installed connecting piece Fig. 104: Completed connecting piece
3.8.1 Connecting to the hospital's cold water supply (water-water type only)
n Route the preinstalled flexible water hoses from the WCS to the prepared on-site wa‐
ter connection (shorten the hoses if necessary).
n Connect the on-site water supply to the hose ends using the connecting pieces provi‐
ded.
If may be necessary for this step to be performed by a plumber (e.g. if the hoses are too
short).
n The water hose / water pipe from the hospital cold water supply must be connected to
the "central water supply intake" at the WCS.
n The water hose / water pipe from the hospital cold water supply (main water supply
from the WCS >> return line) must be connected to the "central water supply outlet "
at the WCS.
Insulate the metal hose adapters. The insulation material is included in the box of the
metal hose adapters.
n Connect the manometer to the WCS:
- The manometer and connecting hose to monitor water pressure is in a container at
the base of the WCS.
- Attach the connecting hose to the manometer. The straight side is connected to the
manometer, the curved side is connected to the WCS.
- Attach the manometer to the "gantry water outlet" at the WCS.
- To improve monitoring, the manometer can be attached inside the WCS with a ca‐
ble tie (e.g., at the pipe from the " gantry water outlet ").
The length of the air hose is 4 m. The minimum distance between the wall vents for the
"air intake" and "air outlet" is 1 m.
A minimum distance under tolerance may result in air turbulence (direct flow of the
warm air into the air intake ).
1. 2 air hoses
2. 2 air hose adapters for the air intake and outlet at the WCS.
3. Installation material for the air hoses (long cable ties)
The wall adapter for the air intake / outlet has to be ordered separately or organized lo‐
cally, (refer to the “Planning Guide”).
3.8.3 Connecting the external air fan (water-air split type only)
The mechanical and electrical installation from the external air fan (outdoor unit), the op‐
tional flow heater and WCS (indoor unit) have to be finished during preparation (prein‐
stallation).The hoses to the air fan are filled as well. Refer to the document “Preinstalla‐
tion - Installation of the external air split cooling system” (CT00-000.811.02.xx.xx).
The back of each container must maintain at least a 10 cm distance from the wall (rea‐
son: to keep the computer cool).
Fig. 105: Console (120 or 140 cm) Fig. 106: Container for ICS and IES computer
Fig. 107: ICS monitor and accessories Fig. 108: IES monitor/keyboard/mouse
To ensure a secure position, the base foot must be screwed on prior to start-up.
n Lift the device slightly in back.
n Push the base foot under the device in the direction of the arrow
( (1)/Fig. 109 Page 93).
Make sure that the screw holes for the screws are aligned.
n Screw on the base foot with the knurled screws ( (2)/Fig. 109 Page 93).
over.
In earthquake-prone areas, use both floor and wall mounting according to the special
regulations for these countries, refer to ( IRS / Page 107)
n The IRS should be positioned in accordance with the project plan or at the direction of
the project manager. The IRS may also be positioned in an adjacent room.
n Do not remove the spacer from the IRS.
n To prevent it from tipping over, the IRS must be mounted to the wall refer to ( IRS
Mounting / Page 94)
n Bolt the IRS to the floor as shown in ( Fig. 113 Page 95)
Fig. 113: IRS mounting to prevent tipping
3.13 IRSmx
The IRS is air-cooled by internal ventilators. Unimpaired circulation from the intake and
outlet has to be ensured. For correct cooling, a minimum distance of 100 mm at the
back and 150 mm at the front between the IRS and other objects is required!
Never put the IRS into a closed cabinet; otherwise, it will overheat!
For the exact installation location, refer to the project plan or ask the on-site project
manager. The IRS can also be installed in a room adjacent to the examination room.
n For the installation, fold down the spacers at the back of the IRS. This is necessary to
maintain the minimum distance to the wall.
Fig. 114: IRSmx2 tower - spacers and rollers
1 2
(1) Spacers with rollers "up"; transporting position
(2) Spacers with rollers "down"; installation position
Up to Tower 7:
If The IES is connected to the multiple socket strip, ensure that the distance between the
IES and ICS does not exceed 5 m due to the cables provided in the delivery volume.
n Position / attach the switch box at a suitable position close to the ICS (e.g., within the
container, on the wall behind the ICS container, or on the ICS).
(A) Part A
(B) Part B
(1) Power supply W9 (from PDC)
(2) 4 mounting holes
(3) attach with contact disk washers, self-looking nuts
(4) Ground connection W12 (from IES)
(5) Ground connection W14 (from PDC)
The metal cover may be assembled once part A is attached at the respective installation
location.
Fig. 119: Assembling the metal cover
The ICS and ICS monitor are always connected to the multiple socket strip. If the IES is
purchased, IES monitor, Ethernet switch, and external MOD (if purchased) are connected
to the multiple socket switch as well. Take into account the computer and monitor cable
lengths when positioning the multiple socket strip.
4.1 General
The special component mounting described in this chapter is mandatory only in coun‐
tries with specific requirements (e.g., earthquake-prone countries or areas).
Adhere to all country-specific requirements and regulations.
The patient table has to always be bolted to the floor.
n For all other countries, the procedure in this chapter is not required and may be ignor‐
ed.
n The required installation materials (screws, anchors, washers) have to be obtained lo‐
cally (exception couch).
n The gantry has to be bolted to the floor using 4 screws through the adjustment
screws.
n Mark the positions for the drill holes using the gantry adjustment screws
( Fig. 120 Page 103).
n Raise the gantry with the transport device ( Fig. 121 Page 103) and move it away to
obtain access to drill the holes.
n Drill the four holes for the anchors and remove the dust with a vacuum cleaner.
- Drilling depth: Ensure that the anchor sits securely in the concrete and is not just
anchored in the subflooring.
n Insert the anchors in the four holes in the floor.
n Return the gantry to the installation location and align the holes in the adjustment
screws to the holes in the floor.
n Prior to lowering the gantry, ensure that the 4 adjustment screws do not extend out
beyond the base of the gantry ( 1/Fig. 120 Page 103).
n Lower the gantry using the 4 transport device spindles ( Fig. 121 Page 103) until
there is a uniform gap of 1.5 mm under the gantry (at its lowest point; use a 1.5 mm
thick metal rod to gauge the distance).
n Level the gantry using the transport device and a water level on the metal housing
(not the covers) to the left, right, and top (horizontal, vertical).
Fig. 122: Levelling the gantry (left) Fig. 123: Levelling the gantry (top)
n After leveling is complete, check whether the gap under the gantry is less than 1.5
mm (at the lowest point).
n Unscrew the adjustment screws until they contact the floor. Slightly retract the adjust‐
ment screws.
n Lower the gantry until all weight is off the transport wheels.
n Check the leveling again.
n
n
The gantry has to be standing on its feet.
The gap under the gantry should be no less than 1.5 mm (but as small as possible).
n The holes in the adjustment screws must align exactly with the holes in the floor
n Insert screws with washers through adjustment screws and into the anchors.
n Tighten all 4 screws with a torque wrench to anchor the gantry. The maximum torque
depends on the type of screw used.
n Continue with( Removing the Transport Device / Page 49)
Continue with, ( Installing the Components / Page 42), and follow the installation pro‐
cedure beginning on ( Patient Table / Page 52)
4.5 IRS
To prevent it from tipping over, the IRS has to be bolted to the wall and/or floor.
4.5.2 IRSmx
Siemens does not provide special equipment for mounting in earthquake-prone areas. If it
is required, the PM must provide a solution.
5.1 Introduction
n This chapter describes the CT system cabling and presents all electrical connections
and power and signal cables to be established during installation.
n Route the cables as described in the following pages. Each cable is identified by a W-
number, and each plug is imprinted with the X-number of the corresponding connec‐
tor.
n The set of cables comes in either standard length (16 m) or extended length (25 m),
depending on the purchase order.
n Cable W3 is specific to customer requirements.
Fiber optic cables are very senitive and can be damaged easily. They must be handled
carefully and routed at the end of the cabling procedure. Fiber optic cables should not
be bundled with other cables.
The mimimum bending radius for a fiber optic cable is 50 mm ( approx. 2 inches ).
Correct cable routing is a basic prerequisite for a reliable system.
Follow these instructions carefully.
Do not roll up excessive cable length. The remaining cable has to be extended in cable
ducts as as long as possible. If no cable duct is available, the remaining cable length has
to be rolled up as wide as possible so as to meander.
In any case, do not tie wrap this cable.
(1) PDC
(2) Gantry
(3) cable inlet
(4) cable number
(5) length of cable in the unit from the socket to the cable outlet under (or on) the floor
W5 Protective con‐ 25 m / 50 m
ductor
W8 Power cable 16 m / 25 m With plug for non-heating device
W9 Power cable 16 m / 25 m
W10 Power cable 3m
W11 Protective con‐ 16 m / 25 m
ductor
W12 Protective con‐ 3m
ductor
W13 Power cable 3m With plug for non-heating device
W14 Protective con‐ 16 m / 25 m
ductor
W15 Power cable 16m / 25 m With plug for non-heating device
W95 Protective con‐
ductor
W802 Power cord USA: 3 m FRG: 2 m
W810 Power cord USA: 3 m FRG: 2 m
W811 Power cord USA: 3 m FRG: 2 m
W812 Power cord USA: 3 m FRG: 2 m
W813 Power cord USA: 3 m FRG: 2 m
1. Use only one of the two cables W4 and W4_10. The other cable may be disposed of.
For details regarding the container fan and cabling for additional and second monitors
(Tower 7 and above), refer to "Installation of Hardware and Software Options",
CT00-000.814.23.xx.xx.
1. With Tower 8 are USB keyboards are available with Tower 8. The PS/2 cable W63 is not needed The cable
range of the cables provided is up to 4m.
2. The USB mouse is available with Tower 8; the PS/2 cable W64 is not needed. The cable range of the provi‐
ded cables is up to 4m.
Cabling details for additional and second monitors (Tower 7 and above), refer to "Installa‐
tion of Hardware and Software Options" CT00-000.814.23.xx.xx.
WARNING
Connection of non-Siemens devices to the PDC, e.g. camera, patient monitoring
device etc. can cause system malfunctions. This can cause injury and/or damage
to the equipment.
Consequence: Risk of accident and injury or damage.
Only connect Siemens devices and components described and approved in
the service doumentation.
(1) X1 (W4)
(2) X2 (W5)
(3) X3 (W53)
*1) Work in progress: Connector X1 from cable W4 (or W4_10) can be mounted at the
cut-out in the WCS connection area( Fig. 132 Page 122). The WCS internal counterpart
to X1 can be connected to W4 (or W4_10).
(1) X1 (W4)
(2) X2 (W5)
(3) X3 (W53)
*1) Work in progress: Connector X1 from cable W4 (or W4_10) can be mounted at the
cut-out in the WCS connection area( Fig. 132 Page 122) . The internal WCS counterpart
to X1 can be connected to W4 (or W4_10).
Fig. 132: Installing X1 at the WCS conncetion area
*1) Work in progress: Connector X1 from cable W4 (or W4_10) can be mounted at the
cut-out in the WCS connection area ( Fig. 132 Page 122). The internal WCS counterpart
to X1 can be connected to W4 (or W4_10).
L1,L2,L3, N,PE (main pow‐ --- (obtain locally) Main power supply (on-site)
er supply) X111 => *3)
*2a) Cables W2 and W3 must be routed in parallel and at a distance from other voltage
and signal cables. Cable W3 is delivered at a customer-specific length (as ordered) be‐
cause it is very stiff and cannot be rolled. The cable length delivered may be adapted to
the actual length required. In addition, crimping pliers are required to attach the cable
ends to the terminals. The crimping pliers are not delivered with the system. We recom‐
mend using the following tools:
(1) E703 X1 from connecting frame (1) X701 from Gantry left
(2) ECG X704 (2) PE 700
(3) Gantry X702
(4) X703
*6) These cables (W52/W67/W68 coming from the gantry)have to be connected in the
patient table. The connectors and plate have to be secured with cable ties
( Fig. 138 Page 130).
Required connections can change quickly. The current connection layout is attached to
the right or left side of the computer( Fig. 147 Page 133)
19” flat screen n.a. (DVI cable) ICS monitor - DVI interface
ICS: Monitor connection
(graphic card)
ICS: twisted pair Ethernet ca‐ W62 IRS switch connector: 8MDI
ble
ICS: D31.X1 W73 Switch box: X4
ICS: D31.X2 W71 Switch box: X6
ICS: X11/12/13/14 W74 Switch box: X5
Part no.: 7711703, 7130300 W77 Switch box: X8
ICS: COM 2
Part no.: 7711844, 8879418,
8879616, 8879566,
10143562, 10497984 ICS:
COM 1
ICS: keyboard (PS/2) W63 ICS keyboard
ICS: keyboard (USB) hard wired ICS keyboard
(1) D24
(2) D32.X1
(3) LAN to ICS
(4) Power
(5) PE
Do not use cable ties to secure the cables! Use the hook-and-loop tape provided.
1 2
After connecting the IRS power cable, attach the electric shock protection
Fig. 158: Monitor (Flat screen) Fig. 159: Monitor connections at rear
Fig. 160: 19” flat screen/preparation Fig. 161: 19” flat screen/remove cover
Fig. 162: 19” flat screen/remove display stand Fig. 163: 19” flat screen/cable connections
Fig. 164: 19” flat screen/display stand attached Fig. 165: 19” flat screen/cover attached
If the monitor (ICS, IES, or dual) is delivered with an additional PE cable,
then connect the PE cable of the monitor to the IMS power distribution PE sockets (PIT).
The monitor voltage supply is provided via the multiple socket strip, UPS (only option for
IES) or on-site connector.
Fig. 172: IES Tower 8D (10143561) Fig. 173: IES Tower 8E (10392906)
Required connections can change quickly. The current connection layout is attached to
the right or left side of the computer ( Fig. 174 Page 151).
19” flat screen n.a. (DVI cable) IES monitor: DVI interface
IES: Monitor connection
Switch box X9 W76 IES COM 1 (Option)
Local UPS W80 IES COM 1 (Option)
Voltage supply from on-site socket W802 IES Power supply
When connecting the IES via the PDC (USP option), note that both the IES and ICS are
supplied with power from the multiple socket strip. For this reason, the distance be‐
tween them is limited to approx. 5 m.
or
(1) 1X IES
(2) 2X ICS
(3) 3X to 7X other network partners
(4) LAN
The multiple socket strip or the on-site connector provide the monitor voltage supply.
The Multiple Socket Strip is not watertight and must be mounted therefore at a suitable
place. It is recommended to attach the multiple socket strip at the wall (on-site) or the
rear wall of the table.
Fig. 177: Mounting the multiple socket strip Fig. 178: Multiple socket strip
1
2
3
(1) Nut
(2) Contact washer
(3) Multiple socket strip
(1) W12
(2) W9
(3) W14
An additional firmware for PET and Maquet Systems has to be installed. The installation
is described ( Installation of firmware / Page 181).
Disconnect the monitor signal cable to the computer. Otherwise, the graphics board will
be destroyed.
Do not turn on the water pump before you fill the gantry water system.
=>the water pump will be destroyed when you switch on the WCS without water.
Do not mix anti-freeze into the chilled gantry water.
If the water flow into the gantry is too strong (noise can be heard),
close the valve by 15 to 30 degrees ( Fig. 184 Page 158) position C.
The primary cooling circuit (indoor unit to outdoor unit) of the water/air split cooling sys‐
tem had to be connected and filled prior to the CT system installation.
Refer to document “Preinstallation - Installation of the external air split cooling system”
(CT00-000.811.02.xx.xx).
n The manometer for water pressure monitoring (delivered with the WCS) must be con‐
nected to the WCS " gantry water outlet ".
n Two 1/2" garden hoses of the necessary length and hose connectors must be availa‐
ble. The hose connectors are included with the WCS delivery volume (the package is
within the WCS).
The nominal static water pressure for the Gantry-WCS water system: 2 bar (± 0.2 bar;
Fig. 185: Water-water-type: filling and draining Fig. 186: Water-air-type: filling and draining
(1) Gantry water drainage connector and valve (1) Gantry water drainage connector and valve
(2) Gantry water filling connector and valve (2) Gantry water filling connector and valve
n Install the brass connector to one end of the garden hose and tighten accordingly. The
brass connector is included in the WCS delivery volume (to connect the filling / drain‐
ing hoses to the WCS).
n Remove the brass cap from the gantry water filling valve at the WCS "gantry water in‐
let". The cap will be used later to open/close the valve.
n Connect the hose to the gantry water filling valve ( Fig. 185 Page 159),
( Fig. 186 Page 159), ( Fig. 187 Page 159) and tighten it.
n Attach the water connection adapter to the other end of the garden hose (obtain lo‐
cally based on the water tap of the on-site water supply).
n Connect the water connection adapter to a nearby water tap (on-site water supply)
and tighten accordingly.
n Install the 2nd brass connector on the second garden hose and tighten it accordingly.
n Remove the brass cap from the gantry water drainage valve at the WCS (next to the
water pump; ( Fig. 185 Page 159), ( Fig. 186 Page 159), ( Fig. 187 Page 159). The
cap will be used later to open/close the valve.
n Connect the second garden hose to the "gantry water drainage valve" and tighten.
n The other end of the garden hose must be routed and secured to a drain.
n Open the gantry water drainage valve with one of the brass caps (to open, turn in
counter-clockwise direction).
n Close the red lever for the "Gantry Water Inlet".
- The red lever is in the horizontal position ( Fig. 184 Page 158).
n The manometer must be connected to the "Gantry Water Outlet".
n Open the water tap.
n Slowly open the gantry water filling valve with the brass cap (to open, turn in counter-
clockwise direction).
- Water flows through the gantry water system bypass.
n Check the seals of all hose connections at the gantry and WCS.
n Flush the system for several minutes.
n After 5-10 minutes, use the 5 mm Allen wrench to open the magnet valve
( Fig. 182 Page 158) to the end stop (turn in clockwise direction). If
( Fig. 183 Page 158) is installed, turn it to position 10. Water now flows from the
WCS to the gantry. The system must be flushed like this for 30 minutes.
- Some air will escape from the internal air vent installed in the WCS (audible hiss).
n Close the gantry water drainage valve, then close the gantry water filling valve.
n Set the lever to vertical position (open; ( Fig. 184 Page 158).
n Open the gantry water filling valve.
- The water pressure should increase. Check the manometer.
- Close the gantry water filling valve when the pressure reaches 2.2 bar -2.5.
n Close the water tap.
n Check the hose connection seals again.
n Keep the hoses connected in case refilling is necessary during start-up.
n To refill, open the water tap, then open the fill valve, until reaching 2.2 bar on the
manometer.
n Refill is mandatory at 1.8 bar.
n Remove the filling and drainage hoses if pressure remains constant during the start-up
process.
- Disconnect the filling water hose from the on-site water supply, then disconnect it
from the WCS. Pour the remaining water in the hose down the drain.
- Disconnect the draining water hose from the WCS and pour the remaining water in
the hose down the drain.
n Reinstall the brass caps on the filling and drainage valves to prevent leakage.
Every new CT system is delivered with a service license key valid for one year.
A new service license key must be obtained from your local Siemens representative (e.g.,
service technician) prior to system start.
If this is not posible, contact the CT Hotline at +49-9191-18- 8080.
Remember that some components contain hazardous voltage levels even though the
system is switched off.
WARNING
Dangerous voltages (up to 560V_DC) are present when system is switched on.
Dangerous voltages (about 560V) may be present even when the system is
switched off due to capacity power.
Consequences: Risk of electric shock!
Observe poweroff instructions and discharge wait times (allow at least five
minutes discharge time after the last scan for all involved HV and UDC parts).
Secure the system against unintended switch-on (e.g. block braker against
switching on and/or mark breaker against switch on) Ensure via measure‐
ments that all voltages are switched off. Connect the stationary and rotating
parts of the gantry to a protective conductor prior to working in the gantry.
Once the system is switched on, every person working on it must wear an x-ray film
badge for dose monitoring.
If a bottle of DESALGIN is delivered with the phantom, add the DESALGIN to the water
phantom.
If no bottle of DESALGIN is included with delivery, then the water phantom will already
have been sterilized by the manufacturer. Follow the instructions included with the
phantom.
Never use de‐ionized water. De-ionized water introduces the risk of microbe contamina‐
tion.
n Insert the nylon screws and tighten them to seal the phantom.
n Backcover:
- The backcover of the gantry is closed and locked (safety switch).
n Frontcover:
- The frontcover of the gantry must remain closed to prevent vibrations caused by
the open door, and to obtain good image quality (stable temperature / humidity in
the gantry).
n Check to ensure that the fuses in the PDC correspond to the table above.
( Tab. 5 Page 166)
- Set the fuses to position "1".
n Check to ensure that main fuses F 200 and F 100 are inserted.
n Service switches S1 and S2 in the PDC cabinet have to be deactivated (yellow LED is
off).
n Check the fuses in the left gantry stand using the table above.
n Set all fuses to position "1".
For safety reasons, all fuses in the WCS cabinet are switched off when delivered (pro‐
tects the water pump against working without water >> the water system must be fil‐
led).
For safety reasons, all fuses and switches from contactors in the WCS cabinet are switch‐
ed off when delivered (protects the water pump against working without water >> the
water system must be filled).
n Activate all fuses and the main switch in the WCS cabinet. Refer to
( Fig. 133 Page 123)
- Set all switches to position "1".
7.4.2.5 Checking the fuses in the flow heater (option of water/air split type)
For safety reasons, all fuses and switches from contactors in the flow heater cabinet are
switched off when delivered (protects the water pump against working without water
>> the water system must be filled).
n Activate all fuses and the main switch in the cabinet of the flow heater.
- Set all switches to position "1".
n Patient table:
- The green switch at the service switch panel (at the right side of the table support
frame) must be switched off (= in Position "0").
n Gantry:
- The two service switches (RTC and Brake) at MCU board D301 (left gantry stand)
must be switched off (= switch in "down" position).
- Service switch S 301 must be in position "1".
Systems for 380/420/440/460 or 480 V line voltage are equipped with an additional T1
auto-transformer (toward the right in the PDC near the stationary generator).
Systems for countries with 400 V line voltage do not have this additional T1 auto-trans‐
former installed.
n All systems are delivered with a country-specific line voltage setting (50 or 60 Hz).
n The connectors for voltage and frequency adjustment use a cage clamp to establish
connection. Pushing a screwdriver into the hole releases the connection and enables
the wire to be inserted or removed. If you remove the screwdriver, you interrupt con‐
tact.
Ensure there is no voltage present in the PDC cabinet prior to adjusting the frequency
(on-site power supply is switched off and main fuses have been removed).
(1) Jumpers
(2) Connection terminal X251
For systems with 380/420/440/460/480 V line voltage only.
Systems with 400 V line voltage do not include the additional T1 auto-transformer.
n Check the line voltage set at the connection terminal of the T1 auto-transformer using
the table below. If the line voltage is not 400V, connect the T1 auto-transformer
L1/L2/L3 as described in the table below. Install the enclosed bonding jumper be‐
tween connectors 1U6 - 2U1, 1V6 - 2V1, and 1W6 - 2W.
n Set the appropriate country-specific line voltage.
(1) Jumper
(2) Connector X262
n Check the jumper position at connection X262; if necessary, correct to the country-
specific line frequency as described below.
n Position the jumpers according to the country-specific settings.
- Remove the three jumpers with pliers.
- Insert the jumpers into the correct positions (based on the table above).
n The jumper settings for 50 or 60 Hz frequency will be checked again during the start-
up procedure in ( Quick Checks / Page 164)
Since direct measurements for this system are no longer required, in compliance with
DIN EN 62353:2008, a justification has to exist for the sake of completeness .
WARNING
In case of measurements with switched on system dangerious voltage levels are
present.
Consequences: Risk of electric shock!
Do not touch electronic connections. Use only appropiate measurement tools.
Do not confuse fuse F100 (80A) with fuse F200 (40A) (refer the labels)
( Fig. 196 Page 175)
n If the rotational field is inverted, phases L1 and L2 of the main power supply cable
have to be exchanged.
WARNING
Dangerous voltages (up to 480V_AC) are present when the on-site power supply is
switched on.
Consequences: Risk of electric shock!
For safe work conditions, the on-site power supply must be switched off. Se‐
cure the on-site power supply against unintended switch-on (e.g. block braker
against switching on and/or mark breaker against switch on). Ensure via
measurements that all voltages are switched off.
WARNING
Dangerous voltages (up to 480V_AC) are present when the on-site power sup‐
ply is switched on.
Consequences: Risk of electric shock!
For safe work conditions, the on-site power supply must be switched off.
Secure the on-site power supply against unintended switch-on (e.g. block
braker against switching on and/or mark breaker against switch on). Ensure
via measurements that all voltages are switched off.
open.
=> Safety switch
If an on-site UPS (optional) is responsible for the IES power supply, connect the UPS in
accordance with the cabling plan prior to this step. Then switch on the UPS and manual‐
ly switch on the IES.
n Press the "SYSTEM ON" switch (3 seconds) at the control box( Fig. 197 Page 177)
- The green LED at the control box goes on.
- All system components are now switched on
Fig. 197: Control box
n The software platforms (syngo and Somaris/5) are displayed automatically at the ICS
monitor.
- Monitor the software start-up at the monitor.
- No error messages should display while the computer is booting.
n The system goes into standby mode.
n Wait until the Checkup is displayed.
n Select: Cancel
- The Checkup window closes.
UPS Settings (Optional in the PDC) in Windows
n If the UPS is installed in the PDC, it has to be configured in Windows Refer to the docu‐
ment "Installation of Hardware and Software Options" CT00-000.814.23.xx.xx for the
installation instructions and configuration procedure.
ger than the change in time setting. For example, changing the time to "CET minus 6
hours" (CET = Central European Time) requires that the X-ray tube has not been used for
more than 6 hours.
n Some system-specific configuration data (serial numbers, options) is preset at the fac‐
tory.
n During the configuration process, all customer and location-specific configuration da‐
ta must be entered and set.
n Go to the configuration menu in the service platform:
- Select: Configuration
n VA70 and lower: Follow the instructions in the document "Configuration Software",
document number CT02-023.816.02.xx. for the system configuration.
VB10 and higher: Follow the instructions in the document "Configuration Software",
document number CT00-000.843.02.xx. for the system configuration.
VB30 and higher: Follow the instructions in the document "Configuration Software",
document number CT00-000.843.07.xx. for the system configuration.
These documents are part of the CB-Doc.
n When configuration is complete, the system must be restarted to activate the new set‐
tings.
7.9.3.1 SW VB40
n Local Service - Configuration - Application
n Activate checkbox Enable Average CT mode
n Click Save - Finish - Home (system restarts automatically.)
If one of the screws at the front of the gantry is loose, or if the Frontcover is opened, the
following message displays when Rot-Mode is started:
"The gantry covers are open. Are you sure nobody is inside?".
The system asks explicitly about the start of rotation.
Test weights may be necessary for balancing the gantry. Test weights and balancing
weights are included in the delivery volume.
When you add or remove a weight use LOCTITE 243 to secure the screws. There must
always be a steel plate (washer or pressure plate) between lead packet and screw.
For an RTP patient table with a flat tabletop, you have to tilt the gantry in the negative
n Prerequisites:
- Front cover closed, plexiglas strip attached.
- Gantry should rotate 15 minutes
- The 3 fans have to be switched off. (To switch off the fans, use the 3 fuses F304/
F305/F308 in the left gantry stand)
n Select Local Service
- With SW <= VA70: OPTION --> Local Service.
- With SW >= VB10: OPTION --> Service --> Local Service
n Click "Tune-up".
n Select "Adjustments" > "Balance Gantry".
n Do not select "include calibration".
n Select: Go.
n When the balance is correct, the test concludes with "OK" status. If there is an imbal‐
ance, the "Compensation Instructions" indicate the weight to add or remove. Follow
the instructions in the software.
It is recommended if the system is idle for an extended period of time, or in case of inter‐
mittent tube arcing.
n After initially switching on the pump, pressure in the water system may drop due to
escaping air.
n Switch off the water pump at the WCS to check the water pressure.
- Switch off fuse F3 (main power) at the WCS (electronics unit).
n Connect the manometer to the "Gantry Water Outlet".
n Check the water pressure at the manometer
- Nominal water pressure: 2 bar (± 0.2 bar)
n Refill if the water pressure is less than 1.8 bar.
n Follow the instructions under ( Filling the Water System / Page 158) for the refill pro‐
cedure.
erly for all scan types (Topo, Sequence, and Spiral). A scan mode is loaded containing a
higher number of readings than necessary for the respective scan time. After a radiation
exposure period of 110% (scan time plus 10%), the generator has to switch off radiation.
n Note: The test must be performed for each mode (Topo, Sequence and Spiral).
- Tolerance for each Test: >100% ... 110%.
- Set Timout-Supervision to 110%
n The test is performed in Service mode.
n Select: TestTools => Controller => Xray Timeout
n Select: Topo
n Select: Topogram length: 153
n Select: GO
- Follow the instructions in the software.
- The test results are displayed on-screen in %.
n Select: Sequence
n Select: Scantime: 0.5 s
n Select GO
- Follow the instructions in the software.
- The test results are displayed on-screen in %.
n Select: Spiral
n Select: Rot-Time: 0.5 s
n Select: Spiral length: max.
n Select: GO
- Follow the instructions in the software.
- The test results are displayed on-screen in %.
Fig. 201: Leveling in the X-direction Fig. 202: Leveling in the Z-direction
n Correct the RTP phantom position until it is perfectly aligned (0˚ ± 0.02˚).
n Verify once more the correct position via the static sagittal light markers (nearly
match) and the rotating lightmarkers.
n Modify the value “rot brake distance (AP)” ( 1/Fig. 205 Page 195) for example from
719 to 722.
n Select Control System ( Fig. 205 Page 195)
n Select Write ( Fig. 205 Page 195)
n Select Perm Filesystem ( Fig. 205 Page 195)
n Select Write ( Fig. 205 Page 195)
n Close the service window.
n Load a spiral mode for gantry rotation (gantry rotation is needed for tube reposition‐
ing). Cancel the scan.
n Repeat the topogram of the phantom and verify the tube AP position again.
7.22.3 Verification of the tilt zero level position / scan plane tilt
n A leveled RTP phantom is needed. Refer to ( RTP phantom pre-positioning (with light
marker and digital spirit level) / Page 207).
n Register a test patient and perform a TOPOGRAM (standard abdomen mode - eg.
AbdomenRoutine) tube position AP.
Fig. 206: Scan plane tilt not OK Fig. 207: Scan plane tilt OK
Fig. 208: Tilt converter Fig. 209: MCU (gantry left stand)
n If the RTP phantom is positioned exactly and the slots are congruent LINK VON BILD
OK, the tilt zero level position has to be verified.
n Check the Tilt 0 LED ( 3/Fig. 209 Page 197) at the MCU board.
If the LED is on, the tilt zero level position is OK.
If the LED if off, the tilt zero level position has to be corrected. See “Correcting
the tilt zero level postion” stated below.
The gantry may lose stand-by mode when the tilt sensor is moved.
In this case, click "Continue" in the new popup window at the ICS. The gantry will change
to stand-by mode again. Then you can try to find the 0 tilt position again.
7.23.1 Overview
With Zero Angle Correction, a possible horizontal deviation should be balanced in the pa‐
tient image x-axis.
Measurment tip: The “angle tool” cannot display an angle smaller than 1 degree.
While you are raising the angle tool measurement line, the value of the angle changes
from 0 degree to 1 degree. At this moment the real value of the angle is 0.5 degrees.
This enables you to evaluate the value of the zero angle misaligment with higher preci‐
sion.
To rotate the image in CCW direction, enter minus degree values.
To rotate the image in CW direction, enter plus degree values.
Enter the detected deviation value in the Edit field Zero Angle Correction
Press Save
Press Home
Reboot the System
Repeat the measurement and check the result.
The image has to be exactly horizontal.
Use a table load of approx. 20kg at the front of the tabletop and proceed as follows: The
weight is required to press down the tabletop until the two plastic rolls (table front un‐
der the tabletop) contact with the tabletop.
For an RTP patient table with a flat tabletop, you have to tilt the gantry in the negative
n Open the relevant screws and change all three feet by the same height(only atone
table side)
n Bolt the table down slightly without using Loctite
n Repeat the previous step (( Checking the X-deviation: / Page 201)) until the X-devia‐
tion is within tolerance
- The two screws at the center of the table are attached using special washers. To
prevent collisions, the flat side of the washer has be parallel to the travel rails of the
patient table. Refer to ( Fig. 81 Page 72).
- Tighten the screws with 20 Nm
n Tighten the connecting frame at the table and gantry completely. Tighten the scews
( 2/Fig. 75 Page 71) and ( 2/Fig. 51 Page 56).
7.25.1 General
The verification and aligment steps in this chapter have to be performed only for Soma‐
tom Sensation Open RTP systems. The correct gantry tilt, patient table, and laser align‐
ment should be checked via radiation using the RTP phantom.
7.25.2 Tools
n RTP phantom
n Digital spirit level with an accuracy of 0.01˚
(1) Marks for sagittal positioning (Laser line showing the Y-Z plane)
(2) Marks for transaxial positioning (Laser line showing the X-Y plane)
(3) Marks for lateral positioning (Laserline showing the X-Z plane)
After finishing the laser adjustment, the standard value of the light marker timeout has
to reconfigured in the control system.
The standard value is 1 minute.
Do not change the “lightmarker timeout” value in the “Permanent Filesystem”.
RTP phantom pre-positioning (with light marker and digital spirit level)
n Align the RTP phantom orthogonally to the scan plane (rotating laser)
( 2/Fig. 213 Page 205).
n Align the RTP phantom almost to the sagittal laser ( 1/Fig. 213 Page 205).
n Align the RTP phantom almost to the lateral laser ( 3/Fig. 213 Page 205).
Fig. 216: Leveling in the X-direction Fig. 217: Leveling in the Z-direction
n Level the RTP phantom in water while using the phantom feet and a digital spirit level
on the top of the phantom. Correct the RTP phantom adjustment until its perfectly
aligned the in X- and Z-direction (0˚ ± 0.02˚).
n Verify once more the correct position via the rotating lasers.
n Select the range of a spiral scan which includes the complete RTP phantom
( 1/Fig. 218 Page 208). It is important to increase the recon-range to the maximum
left and right border.
Perform a spiral scan (standard lung mode - eg. LungLowDose) with:
slice thickness 2 mm
The light markers are properly adjusted if the laser beam overlaps with the marks on the
RTP phantom.
The light marker must overlap the marks on the nearest side and opposite side of the
phantom.
The light marker is properly adjusted if the laser overlaps the marks at both sides of the
RTP phantom.
The two lateral light markers must be aligned with the marks at the correctly positioned/
anligned RTP phantom and congruent.
Fig. 224: LM adjustment not ok in the Z-direction Not correct in the Z-direction (not in the slice plane)?
Use the adjustment screw for the laser position.
Fig. 225: LM adjustment not ok in the X-direction Not correct in the X-direction (not parallel to the slice
plane)?
Use the adjustment screws for laser rotation.
Fig. 226: LM adjustment not ok in the Z and X-direc‐ Neither Z-direction nor X-direction is o.k.
tion
Use the adjustment screws for laser position and laser
rotation.
Refer to ( Fig. 227 Page 213). The laser can not overlap the marks at the two sides of
the phantom. The laser positioning screw cannot cor‐
rect this misalignment.
Light marker chassis is not correctly positioned in its
mounting slot. This error is possible with the lateral
and the sagittal light markers.
Open the mounting of the light marker chassis at the
front cover and move the light marker chassis to the
correct position.
Fig. 228: Adjustment screws for the sagittal light Fig. 229: Correct position of the sagittal light marker
marker according to the RTP phantom on bottom and top.
The light marker chassis may not be in the correct position. The problem is illustrated in
( Fig. 227 Page 213).
For the solution instructions refer to ( Adjustment of the lateral light markers (Y-
direction, height) / Page 215).
Fig. 230: Adjustment screws for the transaxial light Fig. 231: Correct position of the transaxial light
marker marker according to the RTP phantom on bottom
and top.
Fig. 232: Adjustment screws for the lateral light Fig. 233: Correct position of the lateral light mark‐
marker er according to the left and right side of the RTP
phantom.
The two lateral light markers must be aligned with the marks at the correctly positioned/
anligned RTP phantom and congruent.
For an RTP patient table with a flat tabletop, you have to tilt the gantry in the negative
If the light marker chassis is not in the correct position, refer to failing
( Fig. 227 Page 213). Afterward perform the following steps:
n Open the front cover.
n Open one nut of the mounting and remember the positon of the screw in the slot
( 1/Fig. 234 Page 216), for this purpose you can use a ruler (measure the distance
between slot end and the thread).
n Open the second nut slightly ( 2/Fig. 234 Page 216)and move the light marker chas‐
sis in its mounting slot to the correct position ( 3/Fig. 234 Page 216).
n Tighten the mounting screws of the light marker chassis, close the front cover, insert
the plexi strip and verify the aligment of the light marker again.
n Repeat the LightM tuneup tool. Refer to ( LightM for transaxial light mark‐
er / Page 216).
7.25.4 Verification of light marker adjustment, gantry tilt, and patient table
adjustment with radiation
After the light marker adjustment, the adjustment work has to verified.
For the following tests it is important that the RTP phantom is aligned with help of the
gantry light markers and a digital spirit level (not aligned with radiation) only.
n Switch on the gantry light markers. Position the RTP phantom on the tabletop so that
it is aligned in the Z and X directions ( 1/Fig. 213 Page 205) ( 2/Fig. 213 Page 205).
For this purpose use the sagittal and the transaxial light marker at the front cover. Do
not use the lasers of the rotating lighmarkers in this verification step.
n Move the beginning of the RTP phantom into the scan plane and move the patient ta‐
ble up or down until the lateral marks on the RTP phantom match the lateral light
markers ( 3/Fig. 213 Page 205).
n Move the RTP phantom into the scan plane.
n Measure the horizontal level of the RTP phantom in the X and Z-direction with the dig‐
ital spirit level ( Fig. 235 Page 217), ( Fig. 236 Page 217).
Fig. 235: Leveling in the X-direction Fig. 236: Leveling in the Z-direction
n Correct the RTP phantom position until it is perfectly aligned (0˚ ± 0.02˚).
n Verify once more the correct position via the sagittal, lateral, and transaxial light
markers at the front cover.
n Select the range of a spiral scan which includes the complete RTP phantom
( 1/Fig. 237 Page 218). It is important to increase the recon-range to the maximum
left and right border.
Perform a spiral scan (standard lung mode - eg. LungLowDose) with:
slice thickness 2 mm
feed/rotation 1 (scan card) 1
FOV (Recon card) 500
Recon increment (Recon card) 1,0
n Verify that all 4 measurement holes are clearly visible at the same image position
( 3/Fig. 238 Page 219).
In case only 2 holes are visible at the top or bottom ( Fig. 239 Page 219)
Verify and correct the gantry tilt in the service mode. Refer to ( Verification of
the tilt zero level position / scan plane tilt / Page 195). After this verify this test
again.
In case only 2 holes are visible to the left or right --> the phantom is mis‐
aligned in relationship to the scan plane and is out of the scan plane
( Fig. 240 Page 219).
Fig. 239: Gantry tilt misaligned Fig. 240: Phantom out of scan plane
n Verify the correct vertical position (Y) of the RTP phantom in the isocenter. At the be‐
ginning and end of the RTP phantom, the grid in the images has to exactly hit the ver‐
tical notches ( 2/Fig. 238 Page 219).
n If the notches and the vertical grid are not congruent, move the table to the start posi‐
tion of the spiral scan. Verify the correct position of the phantom again via the sagittal
(Z-laser front cover) light markers and the marks on the patient table.
Fig. 241: Position at the phantom beginning is ok Fig. 242: Position of the phantom holes in the X-
direction is ok
Fig. 243: Position at the phantom end is not ok Fig. 244: Position at the phantom end as detailed
in the figure
n Verify the correct horizontal position (X) of the RTP phantom in the isocenter. The grid
in the images at the beginning of the RTP Phantom has to exactly align with the hori‐
zontal notches ( 1/Fig. 238 Page 219).
The position of the horizontal notches at the phantom end varies as a function of the
patient table incline. If the incline is higher than the notches verify the table align‐
ment, refer to ( RTP table prepositioning / Page 69).
n If the notches and the horizontal grid are not congruent at the beginning of the RTP
phantom, the sagittal and/or the transaxial light marker is not correct aligned. Verify
the ( Light marker adjustment / Page 212).
Otherwise, the phantom is not correctly aligned or the image is turned. Verify the
phantom leveling in the X-direction again. If it is correct, the image is turned (see
chapter: Zero angle correction ( Zero Angle Correction / Page 199).
n Reconstruct the images of the spiral scan. Press the Recon button.
n View the reconstructed image at the beginning which includes the holes.
If the holes appear as in ( Fig. 239 Page 219), the rotating lasers are not mis‐
aligned.
If the holes appear as in ( 2/Fig. 245 Page 222) or ( Fig. 240 Page 219), the
rotating light markers are misaligned.
You can only identify the misaligment of the rotating light marker, but you
should not adjust the laser individually. It is difficult to align the four rotating
light markers.
Otherwise, refer to the document “Replacements of Parts-Gantry”
(CT02-023.841.01.xx.xx), chapter “Rotating light markers” to help with this ad‐
justment work. Or contact the “Headquarter Service Center” for a specific solu‐
tion for this problem.
Measurement explanation
Fig. 246: Measurement example
n You have to check the distance between the left and the right top border of the tab‐
letop. The point of reference is the top border of the tabletop ( 1/Fig. 246 Page 222)!
n Do not use the top border of the plastic strip for the measurement
( 2/Fig. 246 Page 222)!
x is the distance between the left and the right top border of the tabletop
7.26.1 Gantry
For an RTP patient table with a flat tabletop, you have to tilt the gantry in the negative
The table cover comprises 4 sections. Each section is split. The 4 sections must be instal‐
led in the proper order and connected to one another using connecting lugs.
Threaded screws with plastic heads are used to secure the cover. Each section requires
four screws.
The upper and lower sections of the table are mounted directly on a steel table support
plate.
(1) Connecting lugs (on both sides, at each half of the (A) screws M5x10
section) (B) Flat bar
(2) Table switch cover (1) Section 1
(2) Section 2
(3) Section 3
n Attach section 1 directly to the two lower steel plates. From the inside, the lower sec‐
tion is secured with 4 additional M5x10 screws.
n Attach section 2 over section 1 using the flat bar.
n Attach section 3 over section 2 using the flat bar.
n Attach section 4 to the two top steel plates.
Fig. 253: Table cover (front) Fig. 254: Table cover (back)
The gap between floor and underside of the gantry must be between 21 mm and 24
mm.
Otherwise, the “RTP Base Cover” cannot be installed. Refer to( RTP installation (Sensa‐
tion Open only): / Page 47).
n Open all shutters ( 1/Fig. 255 Page 228) from the RTP base cover (horizontal posi‐
tion).
n Attach the differential cover parts justified to the gantry/patient table
( Fig. 259 Page 229).
n Close all shutters ( 2/Fig. 255 Page 228) from the RTP base cover (vertical position)
( Fig. 260 Page 229).
If the shutters cannot remain behind the bottom gantry border, change the correspond‐
ing shutter with the alternative longer shutter (part no. 8873767 included in the deliv‐
ery).
(1) Screwing
(2) RTP cover
(3) Gantry cover (bottom/sidewise)
n Adjust the RTP base cover ( 2/Fig. 256 Page 228) to the bottom/side gantry cover
( 3/Fig. 256 Page 228).
n Attach the RTP base cover to the gantry cover using the screws provided. The screws
are secured through ( 1/Fig. 256 Page 228) the gantry cover.
Fig. 257: Gantry RTP cover (in back) Fig. 258: Gantry RTP cover (side)
Fig. 259: Patient table - RTP cover Fig. 260: Patient table - RTP cover (locked)
n Close the cable inlet at the base of the PDC (cable access)( Fig. 262 Page 229)
- Move the cover forward to minimize the gap at the cable inlet.
- Tighten the two screws ( 1/Fig. 262 Page 229) to secure the cover.
n Close the front door of the PDC cabinet.
n Install the gray metal cover at the base of the PDC cabinet.
- Use 4 screws to secure the metal cover.
- Install the gray plastic caps on the screw heads.
(1) 2 screws
(2) 3 screws
The Acceptance, IEC Acceptance and Constancy routine with their separate tests should
be selected and performed regarding to local regulations and customer requirements.
n The system was optimally adjusted in the factory prior to delivery. All quality assur‐
ance tests were within tolerance. For this reasson, the results of the Constancy, Ac‐
ceptance and IEC Acceptance tests during installation should be within tolerance as
well.
n As a prerequisite, no system components have been replaced since delivery from the
factory.
n The quality assurance tests comprise the Constancy, Acceptance or IEC Acceptance
routines to check the system settings (adjustments).
n The Constancy, Acceptance and IEC Acceptance routines are automatic processes
requiring minimum user input.
n After each individual test, the measurement results and tolerance are displayed in the
results window. Some values must be entered manually.
n After the test sequence is complete, the Report function in the Constancy or Accept‐
ance menu may be used to display a shortened measurement protocol as an image.
The measurement protocol contains no tolerance values; however, it displays values
that are either below (<) or above (>) the tolerance margin.
n For Installations worldwide:
- In accordance with local regulations, it may be necessary to perform the Constancy
Test (IEC standard EN 61223-2-6) as a reference for subsequent constancy tests.
This test contains a CT Dose Measurement Index, requiring two special CTDI phan‐
toms (16 cm and 32 cm in diameter) and a special dosimeter. For details, refer to
the Constancy test in this chapter.
- In accordance with local regulations, it may be necessary to perform the IEC Ac‐
ceptance test (IEC 61223-3-5). For this purpose refer to document “Quality Assur‐
ance System - Acceptance testing according to IEC 61223-3-5” (document no.
CT00-000.820.03.xx.xx).
With SW version VB20 and higher, the quality assurance routines automatically creates
PDF-reports of the tests performed.
You can configure the language of this PDF-report in “Local Service - Configuration -
Technical.” Prior to performing a Quality Assurance test, configure this setting.
n The results protocol of the Constancy or Acceptance test procedures and all phantom
images must be documented on film.
n Prints of the test results may be obtained using the Filming card. Load the images to
document with the patient browser. Select the filming camera and press Expose Film
Task.
n Germany, Switzerland, and Austria only (up to SW version VB19):
The measurement results of the acceptance test must be entered in the “measure‐
ment protocol” (up to SW version VB20 only) of the "Acceptance Test" document
(document number CT02-023.820.01.xx).
- The measurement protocol is part of the document specified above.
- The document is included in the "Acceptance Test" register in the blue "Technical
Documents" binder (up to SW version VB19 only).
n With SW version VB20, you cannot fill out a protocol, however, you can print the auto‐
matically created “PDF quality report files.” The reports are stored in path C:\somaris
\service\pdf\report\pdfreport\
With SW version VB30 and higher, the path to the automatically created “pdf quality
reports” is H:\SiteData\QualityReports\
n The “measurement protocols” / “pdf quality reports” and films must be filed in the "Ac‐
ceptance Test" register in the blue "Technical Documents" binder.
DHHS-CTDI (FDA) Head CT Dose Index measured using the 16 cm PMMA phantom
3
1. Test functions available in Acceptance routine for SW VB20 and higher. Test functions available in Con‐
stancy routine with VB30 and higher.
2. Additional tests in the ACCEPTANCE routine (in accordance to DIN 6868-53) only. Required for installa‐
tions in Germany and some EU countries.
3. Additional tests in the ACCEPTANCE routine only (beginning with SW VA70 and higher). Required for pro‐
duction lines in Germany only. With SW VB20 and higher, the DHHS-CTDI tests are under the DHHS Func‐
tions routine.
4. Additional tests in the CONSTANCY routine in accordance with standard EN 61223-2-6 required for instal‐
lations in Germany and some EU countries.
(1) Holder
(2) Water phantom
(3) Slice phantom
(4) Wire phantom
(5) Low-contast-phantom or Allignment-phantom
To obtain the most optimal results, the water temperature in the water phantom should
range between 19 ˚C and 25 ˚C.
Prior to performing the quality assurance measurements, the system must be at operat‐
ing temperature and calibrated.
The coverage of the separate tests should be selected and performed with respect to lo‐
cal regulations and customer requirements.
Beginning with SW version VB30, the constancy routine is in accordance with IEC
61223-2-6 (Edition 1 and 2).
Equipment required:
n Standard phantom set:
- Water phantom, slice thickness phantom, wire phantom.
n 30 cm water phantom (needed with SW version VB30 and higher). This phantom is
not provided in the delivery volume.
n Local regulations may require additional equipment and CTDI measurements in ac‐
cordance with standard EN 61223-2-6:
- 16cm CTDI-phantom (PMMA)
- 32cm CTDI-phantom (PMMA)
Test procedure:
n Dose meter "PTW DIADOS" with "ionization chamber."
n Move the patient table to a height of 175 mm (panel display). The phantom has to be
positioned in the center of the scan field.
n Switch on the lightmarker.
n Position the slice thickness phantom in the center of the measurement field.
- The lightmarker must be positioned exactly over the intersection of the lines in the
slice thickness phantom.
n Set the horizontal table position at the panel to "0".
n The Constancy routine with SW version VB20 and lower contains the following test
functions:
- Lightmarker
- Slice thickness
- Homogeneity
- Noise
- Contrast
- MTF
- Table position
- Dose/CDTI Air (available since SW VB20)
- For standard EN 61223-2-6: CTDI 16 cm, CTDI 32 cm
n The Constancy routine with SW version VB30 and newer contains the following test
functions:
- Lightmarker
- External lightmarker
- Sag./Cor. Lightmarker
- Prev. Image Position
- Slice thickness
- Homogeneity (* see indications stated below for the IEC Acceptance Test at Sliding
Gantry systems)
- Noise (* see indications stated below for the IEC Acceptance Test at Sliding Gantry
systems)
- MTF
- Table position
- For standard EN 61223-2-6: CTDI 16 cm, CTDI 32 cm
n Select: QualityAssurance => Constancy (in service mode).
n The "Quality Constancy" screen is displayed ( Fig. 266 Page 239).
Fig. 266: Constancy screen (example)
n Next, select "REFERENCE" to the right of the word " Constancy ", meaning that all now
generated values will be used as reference values for each subsequent constancy test
until the next REFERENCE QA is performed.
n " Ref " is displayed to the left of the mark for each function selected
( Fig. 266 Page 239)
n Select: GO.
- Follow the software instructions.
n Press the Start button at the control box to begin the process.
n Follow all additional software instructions in the service window.
n Select: DONE (when the software queries at the end of the measurement) to store the
just generated values.
n Select Local Service - Reports (to check/view the measurement results of the previ‐
ous measurements).
- The report shows the nominal value, maximum tolerance, and actual value for each
test.
n Within the IEC Acceptance test, the Homogeneity/Water and Noise measure‐
ments have to be performed with a 20 cm water phantom at vertical position “175”
and with a 30 cm water phantom at vertical position “180”.
n Since the control software cannot modify the patient table height at Sliding Gantry
systems, the automated IEC Acceptance test fails
Perform the 20 cm and 30 cm water phantom scans within the Homogenei-
ty/Water and Noise measurements one at a time and temporary modify
V4 in T37.
How to proceed:
Fig. 268: IEC Acceptance - Phantom selection
Fig. 269: Loading control table T37 Fig. 270: Modified control table T37
5 6
3
n Activate “CONTROL SYSTEM” (item 1), select T37 (item 2), click “Go” (item 3).
n In control table T37, set value V4_position to 180 [mm] (item 4).
n Make sure "Control System" (item 5) is selected, click “Write”(item 6).
n Leave the additional service window open.
(1) Adapter
(2) extension line
(3) ionization chamber
The following steps refer to DIADOS ( Fig. 273 Page 244), the only valid dosimeter for
the test.
n Position the dosimeter in the control room, switch it on and wait until it reaches oper‐
ating temperature. Ensure that the room temperature is within the specified tolerance
for the CT system. Connect the extension to the ionization chamber and to the CT
adapter. Connect the CT adapter to the dosimeter.
n Position the 32 cm phantom ( Fig. 271 Page 244) on the patient table (body mode)
and center it in the scan field. Later, use the head support for the 16 cm phantom
( Fig. 272 Page 244).
n Insert Plexiglas rods (PMMA rods) in all phantom holes not being used. Insert the ioni‐
zation chamber in the center phantom hole (position A).
n Set the dosimeter as follows:
- "Mode" button to DOSE
- "Range" button to Auto Range,
In accordance with local regulations, it may be necessary to perform the Acceptance test
(DIN 6868-53).
The entire Acceptance test routine is described in the document “Qualitätssicherung Sys‐
tem - Abnahmeprüfung nach DIN6868-53” (CT02-023.820.01.xx.xx).
In accordance with local regulations, it may be necessary to perform the IEC Acceptance
test (IEC 61223-3-5).
For this purpose, the entire IEC Acceptance test routine is decribed in the document
“Quality Assurance System - Acceptance testing according to IEC 61223-3-5”
(CT00-000.820.03.xx.xx).
The separate tests should be selected and performed according to local regulations and
customer requirements.
The Dose Profile test is only needed with Acceptance test according to DIN6868-53.
9.1 Protocols
This document has to be filled out if the mechanical installation was performed by a SIE‐
MENS authorized vendor.
Fig. 275: Attaching tape to Plexiglas strip Fig. 276: Pressing the tape to prevent air bubbles
2
1 1
Fig. 277: Tape attached to Plexiglas strip Fig. 278: Tape - both sides of Plexiglas strip
1
2
(1) Tape
(2) Plexiglas strip
(1) Beginning of the Plexiglas strip
n The end of the Plexiglas strip must be in the 1 o’clock position. There is a threaded
hole at the 1 o’clock position.
Fig. 279: Securing the Plexiglas strips
If it is necessary to open the gantry cover again, a new piece of tape will need to be at‐
tached to the Plexiglas strip.
Fig. 280: End of tape left a bit long for attaching second Fig. 281: Tape - attaching the second part
part
1
1
2
Fig. 283: Safety label position Fig. 284: Example of safety label (various languag‐
es)
The two safety labels in the corrsponding language have to be attached to the left and
right front side of the Sensation gantry.
Attach the "Patient Position" label
Fig. 285: Gantry front left side Fig. 286: Gantry front right side
For a better orientation, one of the labels ( Fig. 285 Page 255)( Fig. 286 Page 255) can
be attached in the controlroom in corresponding to the orientation of the gantry front.
Clean the system prior to transferring it to the customer.
Use only manufacturer-recommended cleaners on the system surfaces.
CAUTION
Flammable sprays.
Consequence: Risk of inflammations!
Only use approved and recommanded cleaning agents as described.
n Do not use sprays. They may seep into components, damage electrical parts, cause
structural changes in various thermoplastics, or form flammable mixtures of air and
solution vapor.
n Do not use cleaning agents with the following properties or containing the following
substances:
- Abrasive cleaning fluids or organic solvents such as aldehyde, acetone, spot remov‐
er, gasoline or alcohol. They may degrade component surfaces or lead to hairline
cracks which may cause the material to be damaged under minimal loads (excep‐
tions: alcohol may be used to clean the monitor screens, and aldehyde-based solu‐
tions may be used as disinfectants for gantry and hard PHS surfaces).
- Agents releasing ammonia by dissociation or decomposition. Ammonia causes
stress corrosion.
- Agents containing silicone. Old silicone may cause subsequent electrical contact
problems.
-
Substituted phenol-based or chlorine-releasing disinfectants which can degrade ma‐
terials.
Approved and Recommended Cleaning Agents
The following agents may be used to clean the table sides, tabletop pad, cushions, arm
and knee supports and head holder:
- Tego, 10% vol.
- Gigasept, 6% vol.
- Somplex Perfekt AC, 2% vol.
- Melsitt, 10% vol.(causes minor discoloration).
-
Peform, 2% vol. (causes minor discoloration).
Gantry / PHS
n Clean the component surfaces with a damp cloth.
ICS / IRS / IES Computer / UPS
n Clean the component surfaces with a damp cloth.
Monitor Screen
n The monitor screen has a sensitive anti-reflective layer.
n Clean the screen with a soft cloth.
n Pure alcohol or alcohol with 1/3 or 2/3 distilled water may be used.
n Do not use cleaning solutions.
healthcare.siemens.com/services
siemens.com/healthcare