OUTLINE
A. Considerations during Fabrication
B. Installation Sequences for CHS Kingpost
C. Challenges Faced and Adopted Solutions
D. Concluding Remarks
2
A. Considerations during Fabrication
1. Deliver in 1-piece? → need to check access to
construction site
Conical
toe
cover
plate
9
Existing Ground
Temporary Casing
KP Top Level
Cast Concrete
for Bored Pile
Plan View
Sectional View
B. Installation Sequences for CHS Kingpost 10
Existing Ground
KP Top Level
Plan View
Sectional View
B. Installation Sequences for CHS Kingpost 11
Existing Ground
KP Top Level
King Post
Plan View
Sectional View
B. Installation Sequences for CHS Kingpost 12
King Post
Dolly
Existing Ground
KP Top Level
King Post
Plan View
Sectional View
B. Installation Sequences for CHS Kingpost 13
Existing Ground
L shape bracket
tag-welded to KP
& Guide frame to
support the dolly KP Top Level
Plan View
Sectional View
B. Installation Sequences for CHS Kingpost 14
OUTLINE
A. Considerations during Fabrication
B. Installation Sequences for CHS Kingpost
C. Challenges Faced and Adopted Solutions
D. Concluding Remarks
15
King post
Verticality
allowable
1:200
Bored pile
Verticality
allowable
1:75
Guide
bars
Top
cover
plate
19
D. Concluding Remarks
1. Considerations during design stage to facilitate smooth installation:
• Clear space between KP shear studs and inner-most layer of rebar cage
• Distance of pile cut-off-level from working platform level
• Use load-transfer mechanism other than shear studs (end bearing plate?)
D. Concluding Remarks 20