DAILY REPORT - BLASTING & PAINTING Updated on : 20/11/2019

PENDING JOBS STATUS PLAN FOR THE DAY PLAN FOR TOMORROW

Area of the surface (sq.m) Paint Availability INTER INTER


Sl. Job Received Started on Qty PRIMER FINISH INSPECTION PRIMER FINISH
No on Date Date Job No Item (No.) BLASTING PAINTING BLASTING COATING MEDIATE COATING CLEARANCE BLASTING COATING MEDIATE COATING
Blasting Primer Inter Finish Yes / No COATING COATING
mediate

1 20/11/2019 J2072 E House - Bottom 1 30 Yes √

2 20/11/2019 J2072 Door 3 20 Yes √

3 20/11/2019 J2072 HVAC unit 6 5 Yes √

4 20/11/2019 J2009 Chamber Air Duct 1 200 Yes √

5 20/11/2019 J2009 L Duct 2 1 Yes √

6 20/11/2019 J2009 Combustion Air DUct 01 Set 40 40 Yes √ √ √

7 20/11/2019 J2009 Quencher Duct 01 Set 15 15 Yes √ √ √

8 21/11/2019 J1989 Silencer 3 20 Yes √

9 21/11/2019 J2052 Silencer 6 45 45 Yes √ √


Updated on : 20/11/2019

PLAN FOR TOMORROW

INSPECTION
CLEARANCE