1 Disclaimer
Safety instructions, coordination, the interpretation of the test results and the final test report are in the
responsibility of the respective Test Engineer on site. Supervision is either made by the supervisor, the
Commissioning Engineer or other delegated people sent from ABB. However, the test procedure is provided
by ABB testing department. In order to split-up the GIS into testable sections, the maximal capacitive power
of the available test equipment is needed in advance.
2 Introduction
After installation, and before being taken into service, GIS shall be tested with the aim of checking the
dielectric integrity of the completed installation and of detecting potential irregularities. Such irregularities
might include damage during handling, transportation, storage and installation, improper assembly,
presence of foreign bodies, etc. and could cause a disrupt or failure in the subsequent operation. Normally,
dielectric test should be made after the GIS has fully erected and gas filling at the rated density, preferably
at the end of the other tests.
In case of a dielectric breakdown in the GIS, the procedure like pointed out in IEC62271-203 (2003) Annex
C.6.1 shall be followed.
We reserve all rights in this document and in the information contained within. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SAABB
Document type: Status: Revision: Document number: Page:
Test Procedure Released AC Upper Zakum(AE) 3 of 16
200
applied voltage in kV
150
100
50
0
0 1 2 7 8 9 10 13 14 15 16 17 18 19 20 21 22 .
time in minutes
Chart-1: Test sequence for sections S04, S05, S06 and S07
140
120
100
80
60
40
20
0
0 1 2 7 8 9 10 13 14 15 16 17 18 19 20 21 22 .
time in minutes
Chart-2: Test sequence for sections S01, S02 and S03
The ABB HV test engineer reserves the right to modify this test procedure in the interests of personnel and
equipment safety as the site conditions dictate after approval of PED and ZADCO.
We reserve all rights in this document and in the information contained within. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SAABB
Document type: Status: Revision: Document number: Page:
Test Procedure Released AC Upper Zakum(AE) 4 of 16
1 EOT crane
1 gas handling machine
1 step ladder (height ≥ 3m)
1 forklift
The switchgear must be filled with SF6-Gas according to gas schematic diagram approved: P7512-RM-
2000-E-0101-C99-0001
Each phase are selected with a phase switch and tested separately.
The following check list shall be followed.
We reserve all rights in this document and in the information contained within. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SAABB
Document type: Status: Revision: Document number: Page:
Test Procedure Released AC Upper Zakum(AE) 5 of 16
7 Test sections
Below test sections prepared based on the capacity of ABB test equipment and it is subjected to change
based on site situations.
We reserve all rights in this document and in the information contained within. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SAABB
Document type: Status: Revision: Document number: Page:
Test Procedure Released AC Upper Zakum(AE) 6 of 16
We reserve all rights in this document and in the information contained within. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SAABB
Document type: Status: Revision: Document number: Page:
Test Procedure Released AC Upper Zakum(AE) 7 of 16
We reserve all rights in this document and in the information contained within. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SAABB
Document type: Status: Revision: Document number: Page:
Test Procedure Released AC Upper Zakum(AE) 8 of 16
We reserve all rights in this document and in the information contained within. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SAABB
Document type: Status: Revision: Document number: Page:
Test Procedure Released AC Upper Zakum(AE) 9 of 16
We reserve all rights in this document and in the information contained within. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SAABB
Document type: Status: Revision: Document number: Page:
Test Procedure Released AC Upper Zakum(AE) 10 of 16
We reserve all rights in this document and in the information contained within. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SAABB
Document type: Status: Revision: Document number: Page:
Test Procedure Released AC Upper Zakum(AE) 11 of 16
We reserve all rights in this document and in the information contained within. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SAABB
Document type: Status: Revision: Document number: Page:
Test Procedure Released AC Upper Zakum(AE) 12 of 16
We reserve all rights in this document and in the information contained within. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SAABB
Document type: Status: Revision: Document number: Page:
Test Procedure Released AC Upper Zakum(AE) 13 of 16
Mounting Example:
We reserve all rights in this document and in the information contained within. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SAABB
Document type: Status: Revision: Document number: Page:
Test Procedure Released AC Upper Zakum(AE) 14 of 16
9 Test results
9.1 HV test results
R 188
S02
Y 188
(dd/mm/yyyy)
B 188
R 188
S03
Y 188
(dd/mm/yyyy)
B 188
S04 R
235
(dd/mm/yyyy) Y
235
B
235
S05 R
235
(dd/mm/yyyy) Y
235
B
235
S06 R
235
(dd/mm/yyyy) Y
235
B
235
S07 R
235
(dd/mm/yyyy) Y
235
B
235
We reserve all rights in this document and in the information contained within. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SAABB
Document type: Status: Revision: Document number: Page:
Test Procedure Released AC Upper Zakum(AE) 15 of 16
10 Conclusion
Onsite high voltage test and partial discharge checking as per specifications delivered by ABB has
successfully passed.
Endorsed by:-
We reserve all rights in this document and in the information contained within. Reproduction, use or disclosure to third parties without express authority is strictly
forbidden. © SAABB
Document type: Status: Revision: Document number: Page:
Test Procedure Released AC Upper Zakum(AE) 16 of 16
Installation of HV-Test
For HV test
Equipment / Function Check
Retests
Passed
HV-Test / PD Measurement
HV-Test successfully
passed