Professional Documents
Culture Documents
A Training Report by Dushyant Kumar Singh
A Training Report by Dushyant Kumar Singh
ON
PHASE-III
Year-2019-2020
Page | 1
Page | 2
ACKNOWLEDGEMENT
I am extremely thankful to Mr. Sanjeev Kumar, Division of Utility Department, for helping me
to undertake this work.
I extremely heartfelt gratitude to my respected Report guide Mr. Vikramjeet for this kind and
inspiring advice which helped me to understand the subject and its semantic significance. He
enriched me with valuable suggestions regarding me topic and presentation issues.
I am also very thankful to my colleagues who helped and co-operated with me in conducting the
training by their active participation.
Page | 3
TABLE OF CONTENTS:
1. Guide Wall…………………………………………………………………..……..……6
1.1 Importance………………………………………………………………………7
2.1 Scope…………………………………………………………………………….11
3.4 Advantages……………………………………………………………………....30
3.5 Disadvantages…………………………………………………………………...30
4. Geotechnical Survey…………………………..………………………………………...31
5. Water Proofing…………………………………..……………..………………………..35
6. Block work………………………………………………………………………………37
Page | 4
Fig.1 Plan showing D wall layout of INA Phase III Metro station
Page | 5
GUIDE WALL
Guide wall is two parallel concrete beams constructed along the side of the wall as a
guide to the clamshell which is made of concrete.
Used for the excavation of D wall trenches. Constructed in situ( natural) typically as
lightly reinforced concrete elements.
It maintains the horizontal alignment and continuity of D wall.
It provide support for upper soil during panel excavation.
Page | 6
Importance:
It is important as the slurry levels vary during construction and the upper few feet or 1m
of wall tends to be unstable
It helps to guide D wall grabs vertically and aid in the positioning of the final structure.
Construction process:
A trench is excavated to create a form for each wall, then filled with slurry. It is kept full
of slurry at all the times.
Function of slurry: It prevents the trench from collapsing by providing outward pressure
which balances the inward hydraulic forces and prevent water flow into the trench.
Page | 7
Reinforcement is then lowered in and the trench is filled with concrete which displaces the
slurry.
The guide walls are constructed on the ground surface to outline the desired slurry trench
and guide excavation.
Excavation is done using a special clamshell shaped digger.
The excavation digs down to design depth, or bed rock, for the first cut.
The excavation is then lifted and moved along the trench guide walls to continue the
trench with successive cuts as needed.
The trench is kept filled with slurry ( usually a mixture of Bentonite and water) at all times
to prevent the collapse.
Page | 8
DIAPHRAGAM WALL
Page | 9
Scope: It includes:
Page | 10
Polymer checking kit
D wall grab
Page | 11
Polymer tank
Page | 12
JCB
Fig. 8: JCB
Page | 13
Stop end
Air compressor
Fig. 10 :Compressor
Page | 14
Material used:
Page | 15
Couplers
General Data:
Page | 16
Maximum length of D wall panel ( shallow): 6390 mm
Minimum length of D wall panel ( shallow): 2500 mm
Construction Method:
A. Pre Excavation:
Prior to the D wall grab starting excavation, the slurry pump must be fully submerged in
Bentonite slurry. To achive this a small initial excavation by grab.
For removing certain obstructions pre excavation is required.
Page | 17
B. Primary panel Excavation:
C. Slurry cleaning:
The supporting slurry fluid must be cleaned so that its properties are within permissible
limit before tremieng the concrete.
With the help of regeneration plant, the slurry is circulated at regular intervals throughout
the construction.
Otherwise, fresh slurry fluid can also be used although this approach is not the most
economical.
Page | 18
Fig. 14: Mixing of Polymer forming Slurry
Page | 19
D. Joint construction between Panels:
Page | 20
E. Reinforcement cage lowering and concrete tremieng:
The reinforcement cage can be lowered after clearing the bottom of trench.
The reinforcement cage is suspended from the guide wall panel and must have enough
transverse and diagonal reinforcement to permit it to be properly lifted and lowered into
place
Sufficient space must be left for atleast two or three tremie pipes so that tremieing can
take place.
Concrete tremieing: It is the process of replacing the supporting slurry with the
permanent concrete with the use of vertical pipes called tremie.
Concreting of D wall starts from bottom and the tremie are lifted progressively as the
concrete level rise.
During this process the tremie are maintained within the freshly poured concrete for a
minimum depth of 0.6 m.
Poor tremieing can result in certain portions of the central in slurry pockets getting
entrapped within D wall concrete.
It leads to excessive and costly underground water leaks or even blowouts.
Check for tolerance and verticality: Tolerance shall be as under: D wall face which will
exposed shall be vertical within a tolerance of 75 mm.
Page | 21
Fig. 16: Reinforcement cage of D wall
o In initial 3-4 panels of D walls , verticality of D walls shall be checked using Koden
equipment.
o Once the confidence level is achieved verticality shall be checked after every 5 m.
o When trenching is done by Hydraulic grab, verticality shall be confirmed for every 5 m.
In case the hydraulic integrated rig with hydraulically operated grab is fitted with
indicator of verticality.
o Whole panel shall be checked at three places along length of panel to re ascertain the
verticality from top to bottom.
o The measuring device Koden which gives analytical graphical representation of
verticality is placed at desired location ( supported over the guide wall with proper safety
measures and the machine is activated with electricity or battery) and the probe is
lowered to desired depth.
Page | 22
Fig. 17: Lowering of cage by using hooks
Page | 23
F. Secondary panel excavation:
Page | 24
SOLDIER PILES:
Soldier pile is some of the oldest forms of retaining system used in deep excavations.
It is successfully being used since the last 18th century in metropolitan cities.
The method is commonly known as “ Berlin Wall” when steel piles and timber lagging
are used.
Alternatively caissons, circular pipes or concrete piles can also be used as soldier piles.
Drilling Machine
Crawler crane
Dumper
Trailer
Steel tape
Page | 25
Material Used:
Steel structure: As per drawing the steel structure should be used at the site such as either
H beam or I beam.
Water: Water used in cement and mortar should be clean, clear and free from salt, acid
and organic matter.
Filling Material: As per drawing the filling material should be sand or mixture of cement
and soil.
Construction Method:
I. Boring:
Page | 26
III. Lowering of H section: The H section for soldier pile with a cage at the lowermost
position shall be lowered into the drilled borehole with the help of the crane.
IV. Concreting:
Pour the concrete of grade M40 with slump in the range of 175+25mm or 175-25mm
upto pile reinforcement.
Concrete shall be placed using tremie pipes.
The other end of the tremie pipe should not be more than 300 mm above the bottom of
pile.
Care should be taken that free fall of concrete shall not be more than 1.5m.
The truck filled with concrete should be joined with the tremie pipe is used for pouring it.
The pipe is taken up as required.
V. Backfilling:
The filling of bore hole is then done with sand or mixture of cement and sand in the ratio
1:10 with the water make a isolated mixture.
After construction of permanent columns the soldier piles are removed by breaking the
hardened cement and soil with breaker.
It should be done safely without disturbing the other work.
The H section is cut down and removed from site or station with the help of crane.
Page | 27
Fig. 20: Cross section of breaked pile
Page | 28
Advantages:
Disadvantages:
Page | 29
GEOTECHNICAL SURVEY
Before any construction at site, various tests should be performed to know the condition
of soil over there.
This should be done to know any differential settlement is going to take place in future.
Page | 30
Fig. 22: Inclinometer at Building to know settlement
Page | 31
Fig. 23: Inclinometer at Tunnel area
6. Ground settlement method: Check the surface of soil by using 150 mm rod.
Page | 32
7. Tilt plate: To check the building tiltness ( in degree)
8. Bi reflex target: This tells us the building Settlement at high level.
9. Beam sensor: It gives the online data at the surface of the area where we can’t reach
easily.
10. Online crack meter: It gives the crack measurement by sensor.
11. UDS: It is a kind of soil testing in tunnel area.
12. Standard penetration test
13. Soil resistibility test
14. Magnetic testometer
15. Piezometre vibrating wire: To measure water pressure.
Page | 33
WATER PROOFING
Procedure:
3. The mixture is applied to fill the gaps in the surface which is known as the first priming.
4. The mixture is applied on the surface by using Compressor.
Page | 34
5. The thickness of this layer is 2.5mm.
6. After priming Insu board are placed along with the black polythene.
Page | 35
BLOCK WORK
Page | 36
The size of block should be chose as per drawing.
The material u8sed for binding the blocks is having 1:6 where 1 is cement and 6 is sand.
After every third layer, reinforcement has been provided having diameter of 10mm.
The thickness of binding material between blocks should not be more than 10 mm.
Page | 37
CONCLUSION
This six weeks training gave me the opportunity to work with
some of the best engineering minds in the country and solve
complex engineering & management problems that occur on
field.
Page | 38
REFERENCES:
Page | 39