Download as pdf or txt
Download as pdf or txt
You are on page 1of 22

Domestic Wiring

Consumer protection using an RCD


15 DOMESTIC The risk of a dangerous electric shock by a
person accidentally coming into contact with a
WIRING bare cable is minimised by the use of an RCD.
RCD’s must be used on all pico hydro schemes.
15.1 Main Issues Ideally each household should have its own RCD.
15.2 Wiring Harness
However RCD’s are expensive and therefore it is
15.3 The Load Limiter
15.4 Load limiter design usual to share an RCD between several
households or on small schemes just to have an
RCD in the powerhouse. The level of protection is
just as high with just an RCD in the powerhouse,
though it is more inconvenient as a fault in one
house trips the supply to all houses. This is
explained in Figure 15-2. This device cannot
however, remove the danger of a serious shock if
someone touches both conductors at the same
time. Local people should therefore be warned
about the dangers of touching the cable,
particularly when non-insulated cable is used for
distribution.

Figure 15-1 Installation of domestic wiring circuit (Nepal)


Supply
L L
15.1 Main Issues RCD
N N 1. A person
The main considerations for house wiring are: 3. In a fraction of a second,
the RCD disconnects the supply
accidentally
touches a live wire.
• Consumer safety and a dangerous electric shock
is avoided.
• Reliability 2. The person is standing in water
and conducts easily to earth.
• Versatility in terms of positioning Current flows though them
and back to the earth electrode.
• Limiting the size of the connected load
• Keeping the cost low
Figure 15-2 The danger of electric shock from a bare
• Ease of installation cable is reduced by fitting an RCD.

Safety 15.2 Wiring Harness


The greatest risk to consumer safety is from
This is a “ready-to-install” domestic circuit. It is
electric shocks and fires. These risks are
assembled by a trained person, is safe and
minimised as follows:
reliable, and contains all the necessary
1) Connect an RCD
components (load limiter, light bulb sockets,
2) Provide an isolation switch for each house
electrical sockets, etc.).
3) Earth all metal cased electrical devices
The use of wiring harnesses is particularly
4) Use correctly-sized double-insulated cable
suitable for village electrification using pico
and a wiring harness for house wiring
hydro. Rural houses rarely require complicated
5) Make sure there is no exposed wiring
domestic circuits. People who receive an
6) Position sockets out of reach of small
electrical connection for the first time usually
children
do not have many electrical appliances which to
7) Use a suitably sized fuse or MCB to
connect. In many cases the only devices used will
protect all wiring.
be light bulbs and a radio or television.
8) Give advice about electrical safety and
Consumers who use many loads will benefit more
position a danger notice on the load limiter
from a fixed wiring circuit as this is likely to be
9) Don’t allow hot light bulbs and cookers to
more cost-effective.
touch materials that burn easily.

pmaher 31/05/01
15-1
Domestic Wiring

live, the RCD will operate and disconnect the


3 metres
To Load Limiter
supply, protecting the user. Otherwise there is a
Live
risk of electric shock. This is explained in Figure
Neutral
15-4
Mains socket 1. Faulty live wire
touches metal
In-line case and makes
switch L it live L
Supply RCD Load
N N
Compact 3. RCD disconnects the circuit
Fluorescent lamp after detecting change in Earth connection
neutral current. to metal case

Figure 15-3 Circuit diagram of a typical wiring harness


2. Current is conducted to earth,
and by-passes the neutral wire.

Design of Wiring Harnesses


Figure 15-4 Protecting consumer loads using an RCD
Flexibility: Many new consumers will want to
change the position of their light bulbs after
they are first installed. This is partly due to a If earthing is required, an electrode should be
lack of experience with electricity. If spare provided near to the consumer house. For
cable is provided and the sockets are already information about earth electrodes, see Section
connected, then the lights can be positioned in a 9.3. The earth cable from the electrode is
variety of ways without risk to the consumer. connected to a spare section of the connection
The harness is installed by strapping the cables block in the service box and the cable junction
securely to suitable wooden beams. Unused cable box. The domestic cable should be of the twin
is coiled up and suspended out of the way. The and earth type. A 3-pin plug and socket is then
amount of cable provided will depend on the size used to connect the device to the supply. The
of the local houses. earth wire should be connected internally to the
Load connected: The number of plug and light metal case of the device.
bulb sockets connected to the harness will
depend on the power that the consumer has
subscribed to. A typical harness such as the one
illustrated in Figure 15-3, has one plug socket
A 3 pin plug
and two light sockets. The connected load could is used to
connect a
be 2 CFL’s lights (9W each) and a radio metal-cased
appliance
connected using the 2-pin socket (2W) giving a
total of 20W. This load is used to determine the The metal case
is connected to
load limiter current rating (see Section 15.4). the earth wire

Cable: The current rating of the cable used for


wiring harnesses and all fixed domestic wiring, Figure 15-5 Metal-cased devices should be earthed
should be at least 40% higher than the current
rating of the fuse or MCB protecting the house To Load Limiter
wiring (see Section 15.3 and 15.4). It should also Live
be double insulated for additional consumer Neutral
safety. Earth

Consumer Earthing
3-pin socket
There is no need for a consumer earth to be for metal-cased
provided unless metal-cased appliances are likely devices

to be used.
Consumer loads that have metal cases such as
cookers, must have an earth connection. Then, if
Figure 15-6 An earth connection must be provided if
a wiring fault develops making the metal case metal cased loads are likely to be connected.

pmaher 31/05/01
15-2
Domestic Wiring

15.3 The Load Limiter 15.4 Load limiter design


Conventionally the consumer is charged for their A low cost design of load limiter is shown in
electricity consumption by means of an Figure 15-7
electricity meter that records the number of Panel-mounting
kilowatt-hours drawn from the supply. This is not fuse holder or
in-line fuse holder
appropriate for pico hydro schemes as it does Positive
Temperature
not prevent overloading of the small generator Coefficient
Thermistor
or encourage consumption of electricity during (PTC)
“off-peak” periods such as at night when Panel-mounting
mains switch
electricity is still available and often goes to (Double-pole with Varistor (metal
insulated lever L N N L oxide varistor)
waste. A better option is a limited current and casing) for lightning
protection of
connection, where the consumer pays a fixed mov electronic loads
(See Section 15)
monthly fee that allows them to draw a current Terminal block

up to a prescribed limit on a continuous basis. Plastic box with


screw-on lid
This prevents overloading and encourages ‘off- (50mm x 75mm)

peak’ power consumption. A load-limiting device Supply from


distribution
prevents the consumer drawing more current system
To junction box

than they subscribe for by temporarily


disconnecting them. Some types of load limiter Figure 15-7 A load limiter should connect the service
reconnect automatically, others must be manually wire from the distribution system to the domestic wiring
reset. The use of load limiters is strongly in the house. A PTC is used as a load limiter if less than
0.5 Amps is drawn.
recommended for the following reasons:
• Load limiters are less expensive and more Selection of PTC’s
easily installed than electricity meters. The PTC has a current level at or below which, it
Consumers cannot draw more power than is guaranteed not to trip (Int). This is used to
they have subscribed to. determine which PTC should be used to limit a
• The collection of revenue from the scheme is particular load.
simplified if the tariff is a fixed amount each The switch allows safe rewiring of domestic
month. circuits and increases the ease of fault
• The total consumer load can be matched to detection by allowing the domestic circuit to be
the generator output. This means that the isolated easily from the supply. A fuse must be
generator will not become overloaded and the connected in series with the switch in the live
system voltage and frequency will be and sized to protect the PTC from high currents
maintained. that could cause it to fail.
• Domestic wiring is automatically protected A double-pole switch is used to ensure that both
from high currents the live and neutral can be disconnected. A
single-pole switch would make faults that caused
The type of load limiter used, depends on the the RCD to trip difficult to isolate because the
amount of current which is drawn: neutral would still be connected. A double-pole
If less than 0.5 Amps is drawn use a PTC switch also offers greater protection to loads
(Positive Temperature Coefficient Thermistor) from lightning strikes, provided that consumer
If more than 0.5 Amps is drawn use an MCB or disconnect their loads using the switch during
an Electronic Current Cut-out (ECC). storms. The current rating of the switch should
be at least two times the rating of the fuse. The
If a PTC is used then a fuse and an isolation voltage rating must be greater than or equal to
switch are also required. The fuse prevents the the generator voltage rating.
PTC from being damaged by high currents. The
switch allows safe rewiring in the house and
Selection of Fuses
makes fault-finding easier.
There are five considerations for fuse selection
to include in a load limiter of the design
described.

pmaher 31/05/01
15-3
Domestic Wiring

to identify whether the fuse wire is still intact.


1) The first consideration is the current rating Ceramic fuses, however, have higher breaking
(Fuse Irated) The fuse must be designed to blow capacity. A fuse with a glass case should
below the PTC maximum current (PTC Imax). The preferably be selected, if available with
current rating must however be well above the sufficient current rating and breaking capacity.
guaranteed ‘no trip’ current of the PTC (Int).
4) The voltage rating of the fuse must be
PTC Int< Fuse Irated < PTC Imax greater than or equal to the voltage rating of
the generator (i.e.250V or 125V as necessary)
2) The second consideration for fuse selection is
the breaking capacity. This is the current at 5) The final consideration is the size of fuse.
which there is a danger of the circuit reforming This depends on the dimensions of the fuse
because of arcing across the fuse contacts. The holder. Ensure that new fuses are always
breaking capacity must be greater than the identical to those being replaced.
highest continuous overload current that the
generator is able to produce. The highest 6) Fuse Type: Fast-acting fuses should be
continuous current occurs when the generator is selected as delay types are too slow to protect
overloaded. This is typically twice its operating the PTC.
current (Iop). Size the fuse as follows, so that
there is no danger of the breaking capacity being
exceeded: Note: Bypass prevention
Some form of protection is required to stop the
Breaking Capacity ≥ 3.0 x Iop load limiter from being bypassed. Suitable
methods are using a seal or a small padlock on
3) Fuses are available with glass and ceramic the service box to discourage tampering.
cases. The advantage with glass is that it is easy

pmaher 31/05/01
15-4
Lightning Protection

This is a very rough guide. To obtain an accurate

16 LIGHTNING estimate about the risk of lightning, talk to


people from the community where the

PROTECTION OF distribution system will be installed to find out if


local lightning is frequent or rare.

PICO HYDRO This section deals with lightning protection from

SCHEMES direct and indirect strikes on the distribution


lines.
16.1 Direct Lightning Strikes
16.2 Indirect Lightning Strikes 16.1 Direct Lightning Strikes
16.3 Lightning Arrestor Types
No equipment exists that provides full
16.4 Protection of Powerhouse Equipment
16.5 Protection of Consumer Loads protection in the event of direct strikes. For
this reason it is essential that the risk of direct
Lightning can cause death and injury and damage strikes is reduced as much as possible by careful
to buildings and equipment. Measures must be routing of the distribution system. The risk of
taken to minimise these risks, especially in areas direct strikes is reduced if the distribution is
of high lightning activity. run through a large area of trees as there is a
good chance that lightning will strike a tall tree
Risk Estimation some distance away rather than the cables
Weighting Factor A: Degree of Isolation themselves. When the number of trees is small,
it is best to keep the distribution at least 10m
Structure located in a large area 0.4
away as the lightning may jump across from a
of structures or trees of the
tree which is struck. This is because cables
same or greater height e.g. in a
provide a lower resistance path to earth.
forest
Structure located in an area with 1.0
Avoid routing the distribution along exposed
few other structures or trees of
ridges, particularly in lightning prone areas. If it
similar height
is essential to do this, then use buried, armoured
Structure is completely isolated 2.0
cable. Whenever possible, route the distribution
or exceeding at least twice the
in valleys.
height of surrounding trees

Note on Overhead Ground Wires (OGW)


Weighting Factor B: Type of Country
Some people have recommended the fitting of an
Flat country at any level 0.3
overhead earthed wire, above the line and
Hill country 1.0
neutral conductors with the aim of conducting
Mountain country between 300m 1.3
lightning discharges to earth. This is not
and 900m
recommended for low voltage distribution
Mountain country above 900m 1.7
networks. The reason is that the lightning may
jump between this wire and the line and/or
Try to identify on the map (Figure 16-4) the
neutral causing a dangerous voltage on these
number of thunderstorm days per year in the
conductors. This approach only works on very
region closest to you. Multiply by Weighting
high-voltage transmission systems due to the
Factors A and B and use the following table to
much larger air gap between the OGW and the
estimate the risk of lightning.
conductors and frequent earthing of the OGW.

Risk Estimation by number of


16.2 Indirect Lightning Strikes
thunderstorm days per year
An indirect strike is where lightning strikes
High Risk More than 100
close to the distribution line as this will induce
Medium Risk 25 to 100
high voltages in the cables. Whilst these
Low Risk Less than 25
voltages are not as high as the ones which can

pmaher 31/05/01
16-1
Lightning Protection

result from a direct strike, they are still becomes an excellent conductor above the
dangerous, particularly for electronic equipment. threshold. They are faster acting and usually
Voltages are induced both between live and clamp to lower voltages than spark-gap
neutral and neutral and earth. The “line-to- arrestors, therefore providing better protection
neutral” voltage surge can be reduced by twisting for electronic equipment such as TVs, CFLs with
the cables together if insulated conductors are electronic ballasts, and generator controllers.
used. For low current ratings, they are very cheap
(about $1) as they are mass-produced for use in
domestic appliances. However, for the higher
16.3 Lightning Arrestor Types current ratings designed for use on overhead
Spark-gap lines, they are expensive ($50 to $100)
especially when compared to spark-gap devices.
The conventional lightning arrestor consists of a
spark gap for the lightning to arc across and a Powerhouse Distribution Consumer
series resistance to limit the flow of current Ballast
System Loads
after the voltage surge. They are generally Induction
Load Lightning
isolation Arrestor Lightning Mains switch
switch on 1st pole Arrestor at consumer
slower acting than more modern arrestors and do Generator
RCD
L IGC L L
connection

not clamp the voltage at as low a value. They


N N N
offer reasonable protection to electrical
500m max.
equipment such as wiring and motors but little Earth L
Connection
protection to electronics. Prices are typically Varistors may
also be connected
$10 to $20. Select the voltage rating so that across the consum
supply if a PTC is
the arrestor does not operate under normal Extra varistors
N used.
connected
voltage conditions but comes into operation if across output
terminals of IGC.
the voltage exceeds maximum setting of the
over-voltage trip on the IGC (see Section 9.6). It
is important the voltage rating is low enough to Figure 16-2 Connection of lightning arrestors to prevent
damage to electrical equipment and reduce danger to
protect the generator but not so low that the
electricity consumers
arrestor is triggered by fluctuations in the
generator voltage (for example, this can happen
if the load is suddenly disconnected). The life of 16.4 Protection of Powerhouse Equipment
lightning arrestors can be shortened if they are A lightning arrestor is connected line-to-neutral
triggered in this way. on the first distribution pole immediately outside
the powerhouse as shown in Figure 16-2. A
single-pole load isolation switch is used instead
of a double-pole one so that the neutral is
earthed even when the load is isolated. This
ensures that there is always a path to earth.
Whenever possible during lightning storms, the
distribution system should be disconnected using
this switch and the generator shut down.

Protection of the IGC


A varistor is fitted (soldered) to the IGC circuit
board to protect the more sensitive electronic
Figure 16-1 Spark gap lightning arrestors components. It is recommended that in medium
and high risk areas, additional varistors are
Varistors
fitted to provide extra protection. These should
Varistors have neither a spark gap or series be connected in parallel across the output
resistance. They consist of two electrodes terminals as shown in Figure 16-2. Several
separated by a material that is a good insulator devices connected in parallel allow greater
below a certain threshold voltage and which

pmaher 31/05/01
16-2
Lightning Protection

current handling to reduce the voltage across that do not contain electronics are reasonably
the sensitive electronic components in the IGC. well protected by spark-gap arrestors. However,
loads that contain electronics, such as TV’s,
The additional varistors should have a voltage radios and CFL’s are much more sensitive and
rating at least 25% above the rated voltage of require varistors for protection. The best
the distribution system. This will avoid them protection is provided by pole mountable
being damaged under normal operating varistors with current rating of more than
conditions. However, their voltage rating should 50,000 Amps as these can withstand very high-
be less than the voltage rating of the soldered energy discharges.
varistor. If they are damaged then they can
easily be replaced on site as they are not A cheaper alternative that works particularly
soldered. For example, if a varistor with an AC well with PTC themistor load-limiters (see Figure
voltage rating of 420V (usually the case) is 15-7) is to fit a disk-type varistor between line
already fitted to the IGC then additional and neutral on the load side of the limiter and
lightning protection can be achieved by have a pole mounted spark-gap arrestor. In the
connecting devices with 320V rating. event of lightning induced surge, the varistor will
clamp the voltage in the house, with the
16.5 Protection of Consumer Loads additional voltage being dropped across the PTC.
It is difficult to specify the number of lightning Once the voltage is high enough, the spark-gap
arrestors required for a scheme as it depends on arrestor will operate and conduct most of the
many factors, including the frequency of current. Note that this puts extra stresses on
lightning, expense of replacing damaged the PTC. However, these are cheaper to replace
appliances and the cost of the arrestors. than most domestic appliances.
Electrical guidelines for micro hydro in Nepal
state that the maximum distance of a consumer During stormy weather, consumers should be
from an arrestor is 500m and less in areas where encouraged to disconnect their supply via the
the risk of lightning strikes is high. When mains switch at the entrance to their house.
selecting the precise location to protect a Note the use of a double pole switch at the
number of consumers, preference should be consumer service entrance to isolate the live and
given to points in the system which are near to the neutral (Section 14.4). This is the most
areas where lightning is more likely to strike. secure method to prevent damage to delicate
loads such as CFL’s. Where the consumer
When fitting arrestors, the neutral is normally premises require an earth, it is important that
earthed at the lightning arrestor to minimise the the consumer earth is separate from the earth
neutral to ground voltage surge, as this can cause to which the lightning arrestor is connected and
the insulation to break down. This is not preferably 10m or more away. This is because
achievable when an RCD is fitted in the high currents to earth can result in dangerous
powerhouse, as earthing the neutral will cause voltage potentials close to the earth connection.
the RCD to trip. However, the neutral can be Earthed
earthed through an additional lightning arrestor, Consumer
as shown in Figure 16-3. Load

Selection of Lightning Arrestors


The neutral-to-ground lighting arrestor can be a
conventional spark-gap type, since it is only
required to prevent insulation breakdown. min. 10m

The selection of the line-to-neutral lightning


arrestor depends on the type and value of the
Figure 16-3 Ensure that the consumer earth
loads to be protected. Loads such as electrode (if used) is at least ten metres from
incandescent light bulbs, motors and heaters the neutral-earth arrestor electrode.

pmaher 31/05/01
16-3
Lightning Protection

Figure 16-4 Map showing thunderstorm days per year


throughout the world (based on World Meteorological
records for 1955)

pmaher 31/05/01
16-4
Testing, Commissioning and Operation

This voltage should rise to approximately the

17 TESTING, •
same voltage as the generator.
Check the ballast meter to ensure that the

COMMISSIONING reading is greater than zero. This indicates


that the controller and ballast are

AND OPERATION functioning. If no voltage is produce or the


ballast meter reading is zero, refer to
Section 18.
17.1 Final Checks • Adjust the position of the nozzle plate to
Check the following before starting the turbine give the highest ballast reading.
for the first time.
• The generator, motor protection switch and 17.3 Generator connection
connecting cable have been correctly sized There are two possible connections for the
(Section 9.8) generator. Only one is acceptable. Continuous
• The generator, capacitors, controller, operation with the wrong connection is likely to
ballast, RCD, motor protection switch and damage the generator.
earth-electrode have been connected • Note the ballast reading when the valve is
according to Figure 9-7 and manufacturers fully open.
instructions. • Close the valve and remove the cover on the
• All connections are tight and cable insulation generator terminal box when the generator
has not be stripped back further than has stopped rotating.
necessary (no bare cable should be exposed • Reverse the connections labelled “L” and “2C”
at connection blocks). (see Figure 9-7).
• The turbine and generator are free to • Replace the cover, start the turbine by fully
rotate. opening the valve.
• Any moving parts such as pulleys and belts • If the new ballast meter reading is greater
have safety guards to protect people in the than before then this is the correct
powerhouse. connection. If not, restore the connections
• The motor protection switch and RCD are to their original position after closing the
switched on. valve and waiting for the generator to stop.
• The tailrace is free from obstruction Note: That with the correct connection the
• The penstock joints are watertight and the generator will run more quietly less hot.
penstock is anchored or buried.
• The penstock filter is free from debris. 17.4 Adjusting voltage and frequency.
• The voltage (indicated by the voltmeter) is
17.2 Start-up set by the controller. Adjust the setting on
• Disconnect user loads connected to the the controller by following manufacturers
distribution system using the mains switch instructions in order to obtain the required
located near the controller (Note: MCB and value.
RCD should be in ON position). • The frequency value should be 49 Hz to 52.5
• Open the gate valve near the nozzle slowly to Hz for a 50 Hz system (59 Hz to 63 Hz for a
about half full flow. Wait 60 seconds to allow 60 Hz system).
any soil and air in the penstock to be flushed • Do not operate below the minimum
out. frequency values given. The life of the
• Turn off the valve and remove the turbine generator and other devices connected will
cover. Inspect the nozzle for any be reduced.
obstructions. If any are found, disconnect • A frequency slightly above these ranges will
the nozzle to remove them. not usually have a detrimental effect unless
• Replace the cover and slowly open the valve. speed dependant motor loads such as pumps
• The generator should excite and this will be or fans are connected.
indicated by a reading on the volt meter.

pmaher 31/05/01
17-1
Testing, Commissioning and Operation

• To measure the frequency use a frequency 17.6 Commissioning the distribution


meter or use a tachometer and calculate system.
from the speed (generator shaft rpm’s) as
• Check all distribution poles and cables to
follows:
ensure that they have been installed safely
paying particular attention to ground
Number of poles Frequency (Hz)
clearance and cable sag.
2 Shaft speed / 63
• Check all house wiring has been safely
4 Shaft speed / 31.5
installed and that consumers have been
6 Shaft speed / 21
instructed about the dangers of electricity.
• If inductive loads such as tube lights or
• Calculating frequency from the speed is
motors are connected, measure the
accurate to about 5%.
frequency when these are operating. If
• The frequency can be adjusted by altering
frequency is too high then apply power
the amount of capacitors connected.
factor correction to the significant inductive
Removing capacitors increases the frequency.
loads.
Twice the amount of capacitance must be
added or removed from the 2C as from C
17.7 Operation
(see Figure 9-7).
• If the turbine will be operated over a range To start the generator:
of flows, then check the frequency over the • disconnect the consumer loads.
whole range and correct if necessary. • open the flow control valve slowly until fully
Note that changing the frequency will effect the open or desired power output is achieved.
power output as it will change the turbine • connect consumer loads.
efficiency and generator efficiency. The change • If a large amount of power is being
is best observed by reading the ballast meter dissipated in the ballast, consider reducing
with no user loads connected. the flow in order to reduce the temperature
of the ballast and increase its life.
17.5 Size of ballast load
To stop the generator:
The ballast meter should read between 40% and
• disconnect the consumer loads
100% when no user loads are connected.
• slowly close the flow control valve until it is
• If below 40% then the ballast is too large
completely closed.
and should be replaced by a smaller one. For
example, some of the resistive elements (e.g.
the cooking rings) can be disconnected.
• If 100% then check that all elements are
heating up. If some elements are cold, check
connections and, if possible, the resistance
of the element.
• If all the elements are working and the
reading is still 100%, increase the size of the
ballast load without exceeding the maximum
rating for the controller or generator.
• If this is not possible, then operate the
turbine at reduced power output.
Alternatively increase the capacity of the
controller and/or the generator.

pmaher 31/05/01
17-2
Fault-finding

18 FAULT-FINDING
Problem Possible Causes Solution
No voltage/low power Insufficient turbine power • Check water supply, nozzle and generator
output speed.
Wiring fault • Check wiring and MCB and RCD are switched
on.
Capacitor values incorrect • Check capacitors are connected as shown in
the wiring diagram.
• Check capacitor values are correct for
generator.
Generator has lost residual • Disconnect consumer load. When generator is
magnetism stationary, connect a battery of 6V or more
across any two generator terminals for one or
two seconds. Re-start with no user load
connected.
Ballast loads not connected • Check for loose or missing connections
Over-voltage trip properly (ballast meter reads • Check that any switches in the ballast circuit
operates 100%) are on.
• Check that all ballast loads become hot. If
not, measure resistance and replace if
necessary.
Generator output higher than IGC • Operate turbine at reduced power output or
rating replace IGC with one of higher rating
Controller damaged and fails to • Check whether fault is due to incorrect wiring
deliver power to ballast (ballast of IGC. If not, then replace circuit board.
meter does not operate or only
over a limited range),
Ballast trip lamp lit Ballast short circuited • Check resistance between ballast leads and
between each ballast lead and earth to test
for short circuits. Repair or replace faulty
wiring / ballast loads.
Ballast load too large • Check that the power rating of ballast is less
than or equal to the power rating of the IGC.
Light bulbs flicker Response speed of controller • Alter setting of response speed
incorrect. potentiometer on circuit board.
Ballast load much greater than • Reduce capacity of ballast load.
generator rating.
Uneven turbine output • Check turbine for misalignment, damage or
blockage.
• Check for badly worn bearings.
Motor protection switch Generator connection incorrect • Check generator connections.
operates
Too much excitation current • Reduce the amount of capacitance connected.
(motor protection switch operates
even when turbine operating at
reduced power output)
Too much load current (motor • Increase rating of motor protection switch
protection switch operates with and generator if necessary.
turbine operating at full power • Operate turbine at reduce power output
output) • Avoid overloading the generator
Short circuit in distribution • Isolate sections of the distribution system
system until the fault is found. Alternatively measure
the resistance at different sections to
identify the fault.

pmaher 31/05/01
18-1
Fault-finding

RCD operates Current leaking to ground either • Disconnect consumer loads and restart to
in powerhouse or elsewhere establish if the fault is in the powerhouse. If
in powerhouse check wiring of earthed
devices (e.g. controller casing) to locate
earth fault.
• If fault is elsewhere in the system,
disconnect all earthed consumer loads
• Check lightning arrestors for short to ground
by temporarily disconnecting.
Individual house Load limiter tripped • disconnect all domestic loads and wait for 5
without power minutes. Reconnect less loads than before
load limiter fuse blown • check fuse.
Wiring fault • check service wire connection
• check domestic wiring
Group of houses Wiring fault • check distribution cable connected to the
without power houses for a fault
All houses without Wiring fault • check wiring of main consumer switch in
power (generator, powerhouse
controller and ballast • check first section of distribution cable for
breaks .
working normally)

Further notes on fault finding:

1. Loss of Residual Magnetism


If consumer loads are left connected when an
induction generator is stopped it is likely that
the residual magnetism will be lost. This small
magnetic field is required to build up the
excitation currents and allow the induction
generator to work at the voltage required. If
excitation does not occur, then the voltage (and
power) will be approximately zero when the
turbine is rotating. If this is the case, then a dc
power source such as a battery should be
connected across any two of the generator
terminals before starting the turbine. A 6V, 9V
or 12V lead acid battery would be suitable for
this or several large torch batteries connected
in series and should be connected for 1-2
seconds only. Note: Care must be taken when
using lead acid batteries not to short-circuit the
terminals as the battery can explode!

2. Check for damaged capacitors


Ideally check the capacitor value with a
capacitor meter. Otherwise the operation of
capacitors can be verified with a multimeter -
measure the resistance (should be high and
increasing as capacitor is charged by meter
battery) A low resistance indicates that the
capacitor is damaged and it should be replaced.

pmaher 31/05/01
18-2
Appendices

19 APPENDICIES
Appendix A Basic Electricity

Voltage, Current, Power


Electricity is a very convenient form of energy.
It can be generated in one place and then
transported to where it is needed. At the flick Series = 2 x voltage
of a switch, it can be made to do useful work Connection of one battery
such as create light, heat or run motors. The
driving force that causes electricity to flow is
called the voltage. The electricity flow itself is
known as current. Electrical power is a
combination of voltage and current. The power,
measured in watts or kilowatts is used to Parallel
Connection
describe the rate at which the energy is used.
= 2 x current
of one battery
Resistance
Figure 19-1 Series and parallel connection of batteries
The amount of current which flows depends not
only on the voltage which is driving but also on
the resistance of the material through which it Direct current at 12V can be produced using a
is passing. Materials such as copper have a low car alternator. The maximum power however, is
resistance allowing current to pass easily. These limited to about 500W.
are called conductors. Materials that have a high
resistance, such as most plastics, are called Alternating current (ac) is used to describe
insulators. electricity that is repeatedly changing direction.
The rate at which this happens is called the
AC and DC Electricity frequency. Induction generators and synchronous
generators produce ac electricity. One major
Direct Current (dc) is the type of electricity
advantage of ac is that the electricity can be
that is stored in a battery. The current flows
generated at a much higher voltage, e.g. 120V or
from positive (+) to negative (-) if the battery is
220V than that of dc systems using batteries.
connected to a load. Battery voltages vary. For
example, they may be 1.5V, 6V, 9V or 12V. If two
Higher generator voltage means that the current
batteries are connected in a line (series), then
required to deliver a certain power is less. If the
the voltage is doubled. If both batteries are
current is less then the power losses in cables
connected in parallel then the currents capability
are also less. This means that with ac, it is
is doubled. Never short the terminals of a
possible to transport electricity efficiently over
battery as they explode.
long distances.

The time over which a particular current can be


The following ac and dc system have been
produced, also varies from battery to battery.
compared for a supply to five 40W light bulbs:
For example, a sixty amp-hour (Ah) battery could
Alternating current system (ac)
produce one ampere of current for sixty hours
1) Power required by load is 200W
or twenty amperes for three hours. Only
2) Voltage is 220V ac
batteries with identical voltage and amp-hour
I = P/V
rating should be connected together in the same
= 200/220
circuit. For more information about battery
= 0.91 Amps
types, see Section 13.1.

pmaher 31/05/01
19-1
Appendices

Direct current system (dc)


1) Power required by load is 200W
2) Voltage is 12V dc Current

V oltage
Pow er

I = P/V
= 200/12
0
π

= 16.7 Amps
High current means high losses in electric cables φ = − 90°

because of the cable resistance.


Figure 19-4 If the load is a pure inductor, then the
AC Waveforms current lags the voltage by 90°. The average power
The AC voltage which is produced by a consumed is still = 0 Watts
synchronous or induction generator has
approximately the same shape as a sine wave.
When a load is connected, the current will have a
similar shape and the same period ( period = time
for one complete wave ). The frequency is the Voltage Power C urrent

number of complete waves in 1 second. For 0


π

example, the complete wave shown in Figure 19-2 φ = −30°

is repeated 50 times in one second if the


frequency is 50 Hertz.

If the load is purely resistive (for example a


Figure 19-5 General circuits are combinations of
heater or light-bulb), then the current then the
resistance, capacitance and inductance. Here the current
current will alternate at exactly the time as the lags the voltage by 30° as the load is both resistive and
voltage. The current and voltage are said to be inductive. The power factor (cosφ
φ) is close to 1 and the
“in phase” amount of reactive power consumed is small but must still
be supplied by the generator.

V oltage
Real and Apparent Power
The basic formula for power is current times
Pow er voltage:
0

19.2 Power (apparent) = I x V


φ = 0° π /2 π 3π / 2

Current

However, for ac circuits this is not the whole


story as this is only the apparent power. To
calculate the real power an additional factor is
Figure 19-2 AC waveforms can be approximated to a sine needed called the Power factor.
wave. If the load is a pure resistor, then the current
Using the Power factor (Pf) the real power can
which flows is in phase with the generated voltage
be calculated:

Power (real) = V x I x Power factor


V oltage

Current Real power is measured in Watts (W) and


Pow er
apparent power in Volt-amps (VA).
0

π
The reason for this difference is that there are
φ = 90°
two types of electrical loads; resistive loads and
reactive loads. With resistive loads the current
is in phase with the voltage as shown in Figure
Figure 19-3 If the load is a pure capacitor, then the
current leads the voltage by 90° and the average power
19-2 and in this case the power factor=1 and the
consumed = 0 Watts real power equals the apparent power. Reactive

pmaher 31/05/01
19-2
Appendices

loads may be either inductive or capacitive.


Purely reactive loads draw current consume no
net power as shown in Figure 19-3 and Figure
Apparent Power S (VA)
19-4 as for half a cycle the power dissipated is
positive and for half a cycle it is negative. In Reactive
these cases the power factor=0 and real Power Q
power=0. The combination of resistive and (VAR)
reactive requirements of a particular circuit is φ
referred to as the impedance. A leading power
factor (p.f. > 1.0) indicates that a load is more Real Power P (Watts)
capacitive than inductive. A lagging power factor So
(p.f.<1.0) indicates that the load is more P= S x cosφ
inductive than capacitive. (Power factor = cosφ)

When the power factor equals 1.0, then the net and
requirement for reactive power is zero and only
resistive power is supplied. Power factor
S = P2 × Q2
correction means to bring the power factor Figure 19-6 Power triangle showing relationship between
closer to one and reduce the reactive power real and apparent power.
consumption. In practice this usually means
connecting capacitors in parallel with an inductive
Power Factor Correction
load to raise the power factor.
Circuits which have a lagging power factor
Since the reactive power does not show up on an caused by inductive loads (see Figure 19-4) such
electricity meter, domestic consumers are not as electric motors or fluorescent lamps, require
normally charged for reactive power. However a supply of reactive power. For small loads
this extra reactive power must still be provided connected to the electricity grid, this does not
by the generator. So to prevent a pico hydro present a problem as the reactive power can
system from becoming overloaded, power factor easily be supplied. However, this may not be the
correction is often an important consideration case with small stand-alone induction generators.
for the developer. Power factor correction is sometimes necessary
in these situations to allow the most efficient
A power factor of 1.0 means that a load is purely use to be made out of the power available.
resistive. No reactive power is used and real and
apparent power have the same value. If the The term “power factor correction” means to
power factor is less than one, then the load is increase a lagging power factor towards 1 so that
partly inductive. Power factors of some typical the amount of reactive power required by a
loads are given in the following table: circuit is reduced (see Figure 19-5.). This can be
achieved by connecting capacitors across the
load. Capacitance causes the current to lead the
Load Power factor
voltage rather than lag behind. This can be
Incandescent lamp 1.0 understood by comparing Figure 19-3 and Figure
Fluorescent lamps 0.5 - 0.7 19-4. The net effect of this is that the total
Motors 0.2 - 0.95 reactive power requirement of the circuit is
Table 19-1 Variation of power factors for common loads reduced. Additional considerations are the
availability and cost of suitable capacitors and
how much capacitance to connect. These may
Power Triangle
determine to what extent the power factor can
The relationship between real and apparent
be corrected. However, it is important to avoid
power and power factor can be summarised in a
over-correction of the power factor. Selection
“power triangle.”
of capacitors for power factor correction is
explained in Section 13.1.

pmaher 31/05/01
19-3
Appendices

Appendix C Turbine Operating Speeds for A useful guideline is to use the synchronous
Mechanical Loads speed of the motor. This will be slightly less than
the operating speed when the generator is being
A Operating speed under driven (synchronous speed + 3% slip) This will
mean that under normal conditions of operating
heavy mechanical load
Power (kW)

(synchronous speed - 10%)


Pelton turbine B Operating speed under the mechanical load electricity will not be
speed characteristic light mechanical load
under changing load (syncronous speed) generated, but the turbine will still be deliver
Pmax
C Operating speed when
generator only is connected maximum power. The synchronous speeds for 2
(syncronous speed + slip)
pole (3000rpm), 4 pole (1500rpm) and 6 pole
(1000rpm) induction machines have been used in
the “Power per Belt” tables (Table 13-5 and
Table 13-6)

Appendix D: Additional Notes on Belt


A B C Speed (rpm)
Sizing
Figure 19-7 Ideal operating speeds of Pelton turbine The guidelines given in Sections 13.5 and 13.6 are
under different load conditions sufficient for approximate matching of pulleys
and belts to loads. However, the following two
If the speed of the turbine for driving the
factors have not been taken into account in the
mechanical load is carefully chosen, then it is
“Power per Belt” tables.
possible to allow the induction generator to be
used as a brake for the mechanical load thus
1) Long belts can deliver more power than short
regulating its speed. This reduces wear and has
ones.
advantages during processes such as milling, for
2) A pulley ratio which is speed reducing (a
example, producing a more evenly ground flour.
small pulley is driving a larger one) can also
Any surplus power, not required by the
deliver more power than a drive which has
mechanical load will be dissipated in the
two pulleys of equal size.
generator or ballast, preventing the load and
turbine from over-speeding.
Ratio SPZ SPA SPB
The operating speed of an induction generator is 1:1 >550 >760 >1050
typically the synchronous speed +3%. This is the 2:1 >600 >850 >1150
speed when electrical power is delivered to the 3:1 >600 >850 >1200
controller and consumers. At about 10% below 4:1 >650 >900 >1260
the synchronous speed, there is no net 5:1 >650 >950 >1260
generation of electricity. Table 19-2 Add 5% to power per belt if Centre
Distance (mm) is greater than the above value.
The use of an induction generator controller
The pulley belt can be sized to a greater level of
regulates the turbine speed under both varying
accuracy if Table 19-2 and Table 19-3 are used.
mechanical and electrical load conditions. When
For a belt which is longer than the values given in
the mechanical load is reduced causing the speed
Table 19-2 (values in mm), 5% can be added to
of the turbine to increase, the controller begins
the power. For example, If an SPZ belt is used
to divert the excess power to the ballast. This
on a pulley system that has a ratio of up to 2:1,
increases the load on the turbine and therefore
the power can be increased by 5% when the
is able to control its speed. The action is similar
centre distance is greater than 600 mm.
to a mechanical brake.

So what speed should be chosen as the design


speed for the turbine shaft when sizing a pulley
system for a mechanical drive?

pmaher 31/05/01
19-4
Appendices

SPZ SPA SPB


rpm’s of
turbine
shaft

1000 0.15 0.39 0.81


1500 0.23 0.58 1.21
3000 0.46 1.17 2.42
Table 19-3 Additional kW per belt if Ratio is 1.95
or greater and turbine pulley smaller than the load
pulley

If the pulley ratio is 1.95 (1.95:1) or greater,


then the power can be increased by the amount
shown in Table 19-3. For example, if an SPA belt
is chosen and the turbine speed is around 1500
rpm, the power which that belt can deliver
increases by 0.58 kW if the ratio is 1.95 or
more.

pmaher 31/05/01
19-5
20 USEFUL REFERENCES AND ADDRESSES
References:

1. Harvey, A. et al. ‘Micro Hydro Design Manual,’ Intermediate Technology Publications, 1993.

2. Inversin, A. ‘Mini Grid Design Manual,’ ESMAP, World Bank, 2000.

Editorial Address
Micro Hydro Research Group
Department of Electrical and Electronic Engineering
The Nottingham Trent University
Burton Street
Nottingham
NG7 4BU

Tel. +44 (0) 115 848 2885


Fax: +44 (0) 115 948 6567
Email: phillip.maher@ntu.ac.uk
Web: http://eee.ntu.ac.uk/research/microhydro/picosite

Intermediate Technology Publications


103-105 Southampton Row
London WC1B 4HH

Tel: +44(0) 171 436 9761


Fax: +44(0) 171 436 2013
Email: orders@itpubs.org.uk
Web: http://www.oneworld.org/itdg/publications.html

ESMAP
C/o Energy, Mining and Telecommunications Department
The World Bank
1818H Street, NW
Washington, DC 20433
U.S.A.

pmaher 31/05/01
20-1
21 GLOSSARY
Abney level a device used for measuring the incline of a slope; can be used to calculate the head

ac alternating current; electric current which changes direction at frequent intervals .e.g. at 50Hz or
50 times per second

Altimeter a device which uses air pressure to calculate difference in vertical height between two points

Ballast load usually an electrical heating element which consumes any unused power produced by the generator

Battery used for storing dc electricity; re-chargeable batteries (e.g. lead-acid, Nickel Cadmium) can be used
to light houses which are too far from the generator to have a connection

Belt drive system for transferring rotating mechanical power from one shaft to another using pulley wheels and
belts

Bucket method method of flow measurement using a bucket of known volume and a stopwatch

Canal can be a practical and low cost method in some rural areas of transporting water to the forebay and
reducing the length of penstock required

Capacitor electronic device used to allow induction motors to work as generators; also used for power factor
correction; capacitance is measured in micro Farads (μF)

CFL Compact Fluorescent Lamp; energy efficient light bulb requiring less power than other varieties

Current the rate of flow of electrons through a circuit; measured in Amps

dc direct current; electric current flowing in one direction

Demand survey Assessment of the power requirements and ability to pay of a community

Distribution system wiring system which connects houses to the generator

Distribution pole supports for distribution cable

Domestic wiring electrical system inside a house

Earth-fault a wiring fault allowing current to leak to the ground

Efficiency the word used to describe how ell the power is converted from one form to another; it is the ratio of
the output power to the input power expressed as a percentage; the efficiency of a pico hydro
system is usually about 45%.

Emergency lighting tube light with rechargeable battery which can be switched on when the electricity supply fails

Energy storage energy storage may be required if the flow of water cannot be guaranteed to be high enough
throughout the year; batteries and reservoirs are examples of how energy can be stored

Flow measurement of the quantity of water flowing past a point in one second; measured in metres per
second or litres per second and used to calculate the hydraulic power

Forebay structure which is sometimes used for pico hydro at the start of the penstock ensuring that the
water is sufficiently deep

Frequency the switching backwards and forwards of alternating current; measured in Hertz (cycles per second)

Fuse electrical safety device which prevents damage to circuits or appliances caused by short circuits or
overloading

pmaher 31/05/01
21-1
Head the vertical drop of a water in a stream or in the penstock; measured in metres

IGC Induction Generator Controller – and electronic device used to keep the voltage and frequency steady

Incandescent lamp simple lamp with a wire filament

Induction generator source of ac electricity

Induction motor electrical machine which can be used to drive mechanical loads

Intake point where water enters the penstock

Lighting package an electricity supply suitable for one lamp and possibly a radio

Lightning arrestor a device which allows current surges caused by lighting strikes to be conducted away to ground

Load a device which uses the power produced by the generator

Load control a system to keep the amount of load on the generator constant

Load limiter a device which prevents too much current being taken by a consumer

Low-pressure pipe can be used as a cost-effective alternative to a canal to bring water to the mouth of the penstock

MCB Miniature Circuit Breaker; alternative safety device to the fuse with the advantage that it can be
reset after tripping due to a short circuit or overloading

Meter device which displays the level of generator voltage or ballast power

Motor Protection Safety device which disconnects if too much current is drawn. Unlike an MCB, which operates at only
one current level, the tripping current can be selected from a range, e.g. 6 to 10 amps.
Switch
Over-voltage trip protection circuit built into the IGC which automatically disconnects the supply to protect the
consumer loads if the voltage rises too high

Pelton turbine rotating wheel with buckets around the outside which absorb the power of a water jet and convert it
into rotating mechanical power; most Pelton designs require a head of 20 metres or more to work
efficiently

Peltric Set design of pico hydro unit which is popular in Nepal

Penstock pipe containing water under pressure: brings water from forebay to powerhouse

Pico hydro hydro power with a maximum electrical output of 5kW

p.c.d. pitch circle diameter; diameter line around a Pelton turbine at the centre of jet interaction

PTC Positive Temperature Coefficient Thermistor; electronic device which can be used as a low-cost form
of load limiting

Power measurement of energy supply and demand; given in Watts(W) or Kilowatts(kW); may be hydraulic
power, mechanical power or electrical power.

Power factor reducing the reactive power requirements of loads such as induction motors and fluorescent lighting
by connecting capacitors of certain value across the supply.
correction

Powerhouse building which contains the turbine, generator and any directly driven mechanical loads

RCD Residual Current Device; used to disconnect the supply in the event of an earth
fault

Reservoir small scale energy storage; sometimes used during the dry season if flows are insufficient; water

pmaher 31/05/01
21-2
collected during the day so that the turbine can be run in the evening for lighting

Resistance property of materials related to how well they conduct electric current e.g. plastic has a high
resistance and is called and insulator, copper has a low resistance and is called a conductor;
resistance is measured in ohms (Ω)
Salt Gulp method of flow measurement by adding salt to the water and measuring the conductivity change

Stand-alone system Electricity system which is not connected to the National Grid

Transformer A device with allows the voltage of an ac circuit to be changed up or down by a fixed amount
(e.g. 240v to 12v) Sometimes the distribution voltage is raised so that houses further than 1km from
the generator can be connected. Higher voltage reduces losses in the cables.
Turbine nozzle restricts the flow of water at the end of the penstock to produce a high velocity jet

Valve device used to regulate the flow of water in the penstock. A gate valve is preferred

Voltage measurement of “electrical pressure” which is required in order for current to flow around a circuit;
measured in volts (v)

Voltage drop loss of voltage across the distribution system because of the cable resistance. A voltage drop of up
to ±6% is acceptable

pmaher 31/05/01
21-3
22 INDEX
Abney Level (Clinometer), 7-1, 7-3 mechanical, 2-3, 9-9, 12-3, 13-1, 13-7, 13-8, 13-
Ballast Heaters, 9-5 12
Battery charging, 5-4, 9-3 Meters
Canals, 6-3, 10-1, 10-2, 10-4 ballast meter, 9-6
Capacitance voltmeter, 9-6
excitation, 9-3 Miniature Circuit Breaker (MCB), 9-8, 9-9, 13-6,
power factor correction, 13-2, 13-3, 13-4 14-3, 14-7, 14-13, 15-3, 17-1, 18-1
Current, 8-2, 9-1, 9-8, 13-3, 14-8, 14-9, 14-10, Over-voltage trip, 9-6, 18-1
15-3, 18-2 Pelton turbine, 1-1
Distribution Peltric Set, 8-1, 8-2
cable, 14-1, 14-3 Penstock
layout, 14-2 diameter, 11-1
poles, 14-1, 14-4 materials, 11-2
service connections, 14-7 pressure rating, 11-1
Distribution System, 2-3, 14-1 Penstock Filters, 10-2
Domestic Wiring, 15-1 Pico hydro, 1-1, 2-1, 2-2, 4-1, 5-4, 8-1, 8-2, 9-3
Earth-fault protection, 9-1 Pipe
Efficiency, 2-2 drainage, 6-3, 10-4, 10-5
Energy storage, 6-3, 10-6, 13-4 flushing, 10-6, 11-2
Flow measurement, 7-1, 7-4, 7-9 Pitch circle diameter (p.c.d.), 8-3
Forebay tanks, 2-1, 6-2, 7-1, 7-2, 10-5, 11-2 Positive temperature coefficient thermistor
Frequency, 9-5, 9-7, 17-2 (PTC), 15-3
Fuses, 15-3, 15-4 Power
Head measurement, 7-1, 7-2 electrical, 2-2, 2-3, 4-1, 9-8, 9-9, 14-11
IGC hydraulic, 2-2, 2-3, 8-3, 9-8
installation of, 9-11 mechanical, 2-2, 2-3, 4-1, 8-2, 8-3, 10-7, 13-7,
Induction Generator Controller (IGC), 9-5 13-8, 14-11
Induction generators, 1-1, 9-3, 9-5, 9-7, 14-12 Power factor correction, 13-2, 13-3, 13-4
Induction motors, 1-1, 8-1, 9-3, 9-8, 9-9, 13-6, Powerhouse, 12-1
13-7, 13-9, 14-12 Reservoirs, 2-1, 6-3, 10-1, 10-2, 10-6, 10-7, 12-3
Intake design, 10-1 Residual current device (RCD), 9-1, 9-2, 9-9, 9-
Lighting 10, 15-1, 15-2, 17-1, 18-1, 18-2
compact fluorescent, 13-2, 13-4 Safety, 9-1
emergency, 13-5 Salt Gulp Method, 7-4, 7-7
incandescent, 13-1, 13-4 Scheme
packages, 5-2 layout, 6-1
tube, 7-2, 13-1 Scheme layout, 6-1
Lightning Arrestors, 9-9, 12-3, 18-2 Survey
Load Control, 9-1, 9-5 demand, 5-1
Load limiters, 15-3 site, 7-1
Loads Turbine nozzle, 2-1, 2-2, 8-2, 8-3, 9-5, 10-2, 11-1,
consumer, 2-3, 14-10 11-2, 11-3, 17-1, 18-1
electrical, 2-2, 2-3, 9-1, 9-2, 13-1, 13-4, 13-7, Voltage, 9-5, 13-3, 14-3, 14-9, 14-10, 14-12
14-8 Voltage drop, 14-8, 14-11
Water source, 2-1, 5-3, 6-2, 11-1, 14-1

pmaher 31/05/01
22-1

You might also like