MIS - Project - Construction Phase
MIS - Project - Construction Phase
Salable Area : 1,63,864 Sq.ft Area for Green : 1086.96 Sq. mtr.
Fire Recommendations
Memo No – WBFES/3913/16/Hoog-RB/1272/15 dt. 12-06-16
Management Information System July’2019
Master Project Key Approval Baseline Schedule Project Budget
Content Plan Brief Stakeholders Status Schedule Tracking Budget Tracking
Gallery
Tower wise
Project Tracking
Progress
indices Result Click Here
Cost Varience = EV - AC 2 (-) 3 4.995 Cr Under Spend
Schedule Varience = EV - PV 2 (-) 1 -14.697 Cr Behind the Schedule
Cost Performance Index = EV/AC 2 (/) 3 1.741 Under Spend
Schedule Performance Index = EV/PV 2 (/) 1 0.444 Behind the Schedule
Project Tracking As
on 31St July, 1991
BAC Planed Value (PV) Earned Value (EV) Actual Cost (AC)
weigh 1 2 3
Activity Heads Budget At
tage Plan Progress (Upto July'19) Actual Process (Upto July'19) Bill (Upto July'19)
Completion
Budget % Completion % Completion Cost Cost % Completion
2% Enabiling 0.631 Cr 0.631 Cr 100% 30% 0.189 Cr 0.235 Cr 37%
23% Sub Str & Basement 8.758 Cr 8.758 Cr 100% 99% 8.670 Cr 4.015 Cr 46%
26% Super Structure 9.598 Cr 9.598 Cr 100% 29% 2.800 Cr 1.992 Cr 21%
28% Finishing 10.421 Cr 7.444 Cr 71% 0% 0.000 Cr 0.280 Cr 3%
20% Services 7.469 Cr 0.000 Cr 0% 1% 0.075 Cr 0.201 Cr 3%
2% Landscape 0.570 Cr 0.000 Cr 0% 0% 0.000 Cr 0.015 Cr 3%
100% Total (Lac) 37.447 Cr 26.431 Cr 11.734 Cr 6.738 Cr
Management Information System July’2019
Master Project Key Approval Baseline Schedule Project Budget
Content Plan Brief Stakeholders Status Schedule Tracking Budget Tracking
Gallery