Professional Documents
Culture Documents
Why Cost Cutting Fails To Deliver: by J de Vries
Why Cost Cutting Fails To Deliver: by J de Vries
Why Cost Cutting Fails To Deliver: by J de Vries
Abstract
Over the past decade most, if not all participants in the resources sector have been involved in
initiatives to improve margins, reduce costs and improve business profitability. In many cases the
initiatives undertaken have fallen short of their stated objectives, and in some cases have resulted in
terminal declines of the underlying business. In reviewing why many such initiatives fail, a common
theme of arbitrary cost reduction and a focus on minimising cost as opposed to maximising value and
cashflow emerges.
This paper proposes a structured process that allows mine owners and managers to develop an
understanding of their cost structure and optimise production and cost outcomes from the business.
The broad objective of cost optimisation is to create value by getting more out of existing and new
assets by focussing on operational areas, particularly production and maintenance. The paper uses
practical examples to highlight the application of cost driver trees as a mine improvement tool.
improve the transparency and calibration of mine cost Figure 2 – Detailed driver tree
structures. The common failure of many implementations is the
inability to readily reconcile the observed cost structure to Cost/ person
observed physical activities. Under such circumstances
management has very limited capacity to assess the relative
value for money being achieved. The lack of transparency also People
makes it difficult to understand the relationship between Productivity/
($/drifter m)
person
physical activities and the cost outcomes.
Cost/ rig
Unfortunately most ERP’s are accounting platforms and are
simply not designed as continuous improvement tools.
Additional software, involving data warehousing and similar Development
Equipment
processes needs to be integrated into the ERP before the drilling ($/drifter m)
($/drifter m) Productivity/
platform has enough data to be transparent. This next step is rig
still a few years away.
tree. Where depreciation and amortisation are associated with However, the cash flow must make adequate provision for
ongoing expenditure such as fleet replacement, they should be future capital.
considered as cash proxies ensuring the full cost of operations
are recognised. A final word on expansions. It is more important to consider if
a proposed expansion is simply making an inefficient mine a
Expansion or contraction options pose unique issues for bigger inefficient mine, or is the expansion doing something
inclusion or exclusion of depreciation and amortisation. A at about structural inefficiencies within the mine. It is not possible
times heated debate exists over inclusion or exclusion of to answer this question without a detailed review of the cost
historical capital is assessing future mine options. structure.
Figure 3 – Cost behaviour types Volatility, Capacity Costs and Scales of Economy.
A premise articulated by many mine owners is that expansion
30
or simply being big will permit better utilisation of fixed and
capacity costs. With capacity costs typically representing 60%
20 to 70% of total cost for most underground mines, the
Total cash
expensed “economics of scale” argument is reasonable.
10
Even those mines with a “schedule of rates” contractor have a
0 significant capacity cost. This normally becomes apparent as
0 20 40 variance claims or stand by charges when operating rates fall
Unit of production below some agreed level.
An accounting view would suggest that undepreciated capital Annaul production (kt)
represents historical expenditure of shareholder funds. A
A second risk of expansion strategies is that working stocks are
decision to ignore this expenditure during an analysis of future
consumed at a rate faster than they can be replaced. As stocks
mine options is equivalent to writing the value off a mine’s
are diminished, production volatility rises, as ore available for
balance sheet. Conceptually, residual capital should be thought
production becomes increasingly scarce. These mines are
of as being the part of a loan advanced by equity holders that is
characterised by high instantaneous rates of production,
still outstanding. Depreciation and amortisation may be thought
interspersed with lengthy low production periods. In cost
of as the principal repayments of the loan, with profits forming
structure terms, these mines are paying for capacity, but not
the interest component.
using it. In such a scenario, industry practice of making a
marginal mine bigger will results in increased losses.
The authors experience is that at the end of the day “cash is
king”. Models should consider cash flow on an after tax basis.
Production volatility may be defined in a number of ways. A million tonnes per annum. Maximum monthly production
definition used by the author is simply the ratio of actual to achieved was 110 kt. On an annualised basis, capacity (as
planned outcomes. Such a ratio measures the stress induced on defined by the best monthly hoist) was 32% above the annual
management by production shortfalls. production rate. Historical development requirements were
approximately 180 metres per month. Poor productivity in
Production volatility is related to both stock levels and development required a combination of owner mining and short
distribution of stocks. Where adequate stocks exist, and are term contracts.
appropriately distributed, a mine is able to cover a production
shortfall from any one source by supplementing production Owner jumbo development was characterised as being both
from other sources. slow and expensive. Monthly advance averaged 140 metres per
month, with occasional peaks of up to 200 metres per month.
Figures 5 and 6 illustrate the relationship between total stock Owner development costs were in the order of $3 100 per
availability and its distribution and the capacity to maintain metre. Distributed overheads contributed another $600 per
production. Clearly, having alternative sources of ore available metre. Development shortfalls were made up with short-term
is an important cost management strategy for a mine. contracts. Contractor unit costs were similar, however after
amortisation of mobilisation charges and allocation of owner
Reducing volatility to an acceptable level is an ideal avenue for supplied ground support, contract costs on an equivalent basis
reducing costs. If volatility can be lowered, capacity can be were estimated to be $3 900 per m.
reduced, or utilisation increased, resulting in lower unit costs.
As part of the re-engineering, a significant short term increase
When an expansion is considered there must be a planned in development rates was required. Development rates were
increase in working capital (ie developed and drilled ore) to required to rise to 400 metres per month for six months, and
sustain the increased production rate. then drop to 150 metres per month, for the next couple of years.
Figure 5 – Metal output volatility vs mine inventory Ground conditions ranged from moderate outside of sheared
levels ground to very poor in and around fault and shear zones. The
mine is deep, and subject to closure in and around zones of
Metal Volatility poor ground. Ground support methodology involved jumbo
80.0% scaling, meshing and subsequent rockbolting.
70.0%
60.0% The key decision in the restructure was a change in the primary
50.0%
ground support methodology. Primary support was altered to
install surface control first. This involved fibrecreteing
40.0%
followed by split sets. Mesh is only applied where required.
30.0%
Scaling was limited to large slabs and obviously loose rocks.
20.0%
The revised support methodology was applied to all headings in
10.0% ore and waste with the exception of the decline.
0.0%
0 50 100 150 200
The results of the re-engineering are illustrated in Figure 7.
Inventory or Mine Stocks weeks Average monthly advance increased from 140 metres per
month to 250 metres per month. Direct costs fell from $3 100 to
$2 500 per metre advance.
Figure 6 – Tonnage outcomes as function of stope
availability Figure 7 – Restructuring impact on monthly advance
350
140.0%
Actual tonnage
as a percentage 300
Monthly advance (m)
120.0%
of budget
100.0% 250
80.0% 200
60.0% 150
40.0% 100
20.0% 50
0.0%
0
0 2 4 6 8 10 12
Aug- Dec-99 Mar-00 Jun-00 Oct-00 Jan-01 Apr-01 Jul-01 Nov-01 Feb-02
Average number of stopes on line during study period
99
The case study relates to restructuring of jumbo development • Ground support cycle involving the jumbo reduced
for a medium to large underground mine in Australia. It from 4.0 to 5.0 hours to approximately 1.0 to 1.5
examines the use of driver trees to isolate problems with the hours. This effectively doubled the time available for
productivity and cost structure of jumbo development. face drilling;
• Elimination of jumbo scaling and rockfall during the
The mine in question, budgeted approximately 1.2 million ground support component of the cycle. This in turn
tonnes per annum yet achieved an anualised production of 1.0
eliminated the need to re-bog the heading prior to gaps to be identified. Typical gaps include poor operator
face drilling; productivity, high maintenance costs, and poor utilisation.
• Rockfall damage to jumbo reduced, lowering
maintenance costs and increasing availability; While the mine in question had all of the above, the most
important feature identified was the high percentage of drilling
• Shotcrete reduced rock surface deterioration, effort devoted to rock bolting. Close examination of the data
lowering re-support requirements, increasing the suggested that not only did the jumbo spent a lot of time
amount of time available for face drilling. rockbolting in development headings, it also spent a lot of time
rehabilitating older development. It was estimated that 37% of
In developing the solution the cost structure was mapped. Costs drilled metres were devoted to rockbolting. Of this
within the jumbo development cost centre were broken down approximately one third was associated with rehabilitation.
into individual behaviour types. With the cost centre now
dismantled into its individual components, the impact of Another feature of the data was high unit drilling costs ($ per
increased development rates and alternative operating scenarios metre drilled). Drilling costs are related to rockbolting effort.
could be readily modelled and communicated to mine Figure 9 is illustrates the relationship between unit drilling
management. A summary of the cost structure prior to costs and rockbolting effort. The relationship simply states that
restructuring illustrated in Figure 8. jumbo tramming, scaling, and single boom drilling is clearly
less productive for a jumbo than development drilling.
After mapping the cost and productivity structure, it was
compared to peer mines. Comparison to peer mines permits
Figure 8 – Detailed development cost driver tree before restructure. Zcost components are grouped by behaviour type
Metres Drilled
Cost / person ( 110,866 m per annum )
( 90,554.0 $ per person ) ( 1,441.2 $ per person )
People
( 6.53 $/m drilled )
Productivity / person People ( 8 )
( 13,858 m per annum ) Operator ( 8 )
Nipper ( )
Maintenance labour Other ( )
Jumbo drilling ( 2.27 $/m drilled )
( 13.56 $/m drilled ) Maintenance
Jumbo development ( 746 $ per m advance ) ( 4.31 $/m drilled )
( 3,158 $ per m advance ) Parts / supplies & contracts
( 2.04 $/m drilled )
Blasting
( 111 $ per m advance )
Supplies & Consumables
( 2.72 $/m drilled )
Materials handling
( 348 $ per m advance )
Allocated drilling
( 34.18 $ rockbolt )
Services & supplies
( 769 $ per m advance ) Rockbolts Rock bolts
( 635 $ per m advance ) ( 38.77 $ rockbolt )
Cablebolts
( 224 $ per m advance ) Shotcrete
( 550 $ cubic metre )
Shotcrete
( 138 $ per m advance )
Application rate
( .25 cubuc m per m advance )
Figure 9 – Relationship between jumbo cash cost and Similarly, maintenance costs are related to rockbolting effort.
rockbolting effort The key conclusion here is that maintenance costs for jumbos
are driven by the amount of rockfall damage the machine
experiences.
Jumbo cash cost ($\m drilled)
18
16
14 While it is obvious the rockbolting rate was high and was
12 contributing to the high unit cost of development, the solution
10 was less obvious.
8
6 On a high level, rockbolting was costing $635 per metre, or $73
4 per installed bolt. Applying a 25mm layer of fibrecrete was
2
estimated to cost $140 per metre. To break even, application of
0
fibrecrete would have to reduce rockbolting from 8.7 bolts per
0% 10% 20% 30% 40% 50%
metre to 6.7 bolts per metre. Most mines would stop the
Percentage of jumbo drill effort related to rockbolting analysis at this point. The decision to proceed would be
assessed as marginal. Adoption of fibrecrete would be a 50/50
Ground control costs were assumed to be variable, and a 3. Ward, D and McCarthy, P, 1999. Startup
function of metres developed. Unit ground support costs were Performance of New Base Metal Projects, in Adding
estimated using 5.7 bolts per metre, 20% of existing mesh rates Value to the Carpentaria Mineral Province,
and 0.30 m3 of fibrecrete per metre developed. Total ground Australian Journal of Mining, April.
support costs were estimated to fall from $1 184 per metre to
$780 per metre
The study estimated that total costs would fall by between $500
to $600 per metre and development rates rise to between 200 to
220 metres per month. The result was a drop of almost $600 per
metre, and development rates rose to 250 metres per month.