TUTORIAL - II
1
Department of Civil Engineering
Indian Institute of Technology Kanpur
Crashing of Network
2
Department of Civil Engineering
Indian Institute of Technology Kanpur
BACKDROP
In this lecture, let us look the concept of reducing the project duration
by reducing the durations of critical activities in the project by increasing
resources. 3
Department of Civil Engineering
Indian Institute of Technology Kanpur
• Direct cost
Expenditure that is specific to a project, i.e. cost of materials,
labour, equipment etc.
• Indirect cost
Expenditure like tariff for infrastructure facilities, rent etc.
constitute indirect cost.
4
Department of Civil Engineering
Indian Institute of Technology Kanpur
Cost-time trade-off
Source :- http://osp.mans.edu.eg
5
Department of Civil Engineering
Indian Institute of Technology Kanpur
Crashing an activity:
Expediting an activity to an earlier time by mobilizing more resources is
known as crashing
6
Department of Civil Engineering
Indian Institute of Technology Kanpur
7
Department of Civil Engineering
Indian Institute of Technology Kanpur
Problem:
A project consists of SIX activities A to F. The interdependencies, normal durations, crash
durations and cost slopes for all the activities are shown in Table 1.
Activity Predecessors Normal Crash Cost slope
duration duration (INR/day)
(days) (days)
A --- 18 14 4000
B --- 23 22 2000
C A 8 5 6000
D A 10 6 4000
E B, C 3 2 8000
F E, D 8 6 5000
You may also note the following information regarding this project: The total normal
project cost (if durations of all the activities are their respective normal durations) is
1,00,000 INR. The indirect cost for the project is 8000 INR/day.
What is the minimum cost using which the project can be completed? Also,
determine the corresponding project duration. 8
Department of Civil Engineering
Indian Institute of Technology Kanpur
Recovery of delays
Early availability of the resources for other projects
Receive early completion bonus
Avoidance of seasonal issues which may affect
productivity
Improved project cash flow
9
Department of Civil Engineering
Indian Institute of Technology Kanpur
REFERENCE BOOKS
10
Department of Civil Engineering
Indian Institute of Technology Kanpur
:: Thank you ::