PR3002 Production Planning & Control, T.Y. B.Tech.

Production, Home Assignments, [Faculty: Rajesh Dhake]

Lab Assignment 11: Operations Scheduling [To be submitted in Word format] [Deadline: October, 2019]

Numerical (Solve numerical allotted to your group)

Group 1: Suppose that five jobs have processing times and due dates as given below:
Job A B C D E
Processing Time 4 7 6 2 3
Due Date 15 16 8 21 9
Find the flow time, tardiness, lateness for each job and no. of jobs delayed, if they are processed according to:
a) A-B-C-D-E (First Come First Served)
b) Shortest Processing Time
c) Longest Processing Time
d) Expected Due Date
e) Critical Ratio

Group 2: Suppose that five jobs have processing times and due dates as given below:
Job A B C D E
Processing Time 7 4 8 12 1
Due Date 15 16 8 21 9
Find the flow time, tardiness, lateness for each job and no. of jobs delayed, if they are processed according to:
a) A-B-C-D-E (First Come First Served)
b) Shortest Processing Time
c) Longest Processing Time
d) Expected Due Date
e) Critical Ratio

Group 3: Suppose that five jobs have processing times and due dates as given below:
Job A B C D E
Processing Time 7 4 8 12 1
Due Date 25 8 14 28 5
Find the flow time, tardiness, lateness for each job and no. of jobs delayed, if they are processed according to:
a) A-B-C-D-E (First Come First Served)
b) Shortest Processing Time
c) Longest Processing Time
d) Expected Due Date
e) Critical Ratio

Group 4: Suppose that five jobs have processing times and due dates as given below:
Job A B C D E
Processing Time 4 7 6 2 3
Due Date 25 8 14 28 5
Find the flow time, tardiness, lateness for each job and no. of jobs delayed, if they are processed according to:
a) A-B-C-D-E (First Come First Served)
b) Shortest Processing Time
c) Longest Processing Time
d) Expected Due Date
e) Critical Ratio

Group 5: Suppose that five jobs have processing times and due dates as given below:
Job A B C D E
Processing Time 6 3 8 8 4
Due Date 15 18 12 10 7
1
PR3002 Production Planning & Control, T.Y. B.Tech. Production, Home Assignments, [Faculty: Rajesh Dhake]

Find the flow time, tardiness, lateness for each job and no. of jobs delayed, if they are processed according to:
a) A-B-C-D-E (First Come First Served)
b) Shortest Processing Time
c) Longest Processing Time
d) Expected Due Date
e) Critical Ratio

Group 6: Suppose that five jobs have processing times and due dates as given below:
Job A B C D E
Processing Time 12 4 6 4 4
Due Date 19 12 11 11 9
Find the flow time, tardiness, lateness for each job and no. of jobs delayed, if they are processed according to:
a) A-B-C-D-E (First Come First Served)
b) Shortest Processing Time
c) Longest Processing Time
d) Expected Due Date
e) Critical Ratio

Group 7: Suppose that five jobs have processing times and due dates as given below:
Job A B C D E
Processing Time 5 7 6 12 4
Due Date 13 18 8 21 19
Find the flow time, tardiness, lateness for each job and no. of jobs delayed, if they are processed according to:
a) A-B-C-D-E (First Come First Served)
b) Shortest Processing Time
c) Longest Processing Time
d) Expected Due Date
e) Critical Ratio

Group 8: Suppose that five jobs have processing times and due dates as given below:
Job A B C D E
Processing Time 17 4 18 2 1
Due Date 35 8 34 8 5
Find the flow time, tardiness, lateness for each job and no. of jobs delayed, if they are processed according to:
a) A-B-C-D-E (First Come First Served)
b) Shortest Processing Time
c) Longest Processing Time
d) Expected Due Date
e) Critical Ratio

Group 9: Suppose that five jobs have processing times and due dates as given below:
Job A B C D E
Processing Time 14 8 7 12 3
Due Date 25 18 13 28 5
Find the flow time, tardiness, lateness for each job and no. of jobs delayed, if they are processed according to:
a) A-B-C-D-E (First Come First Served)
b) Shortest Processing Time
c) Longest Processing Time
d) Expected Due Date
e) Critical Ratio

Group 10: Suppose that five jobs have processing times and due dates as given below:
Job A B C D E

2
PR3002 Production Planning & Control, T.Y. B.Tech. Production, Home Assignments, [Faculty: Rajesh Dhake]

Processing Time 11 13 8 4 2
Due Date 15 18 12 10 7
Find the flow time, tardiness, lateness for each job and no. of jobs delayed, if they are processed according to:
a) A-B-C-D-E (First Come First Served)
b) Shortest Processing Time
c) Longest Processing Time
d) Expected Due Date
e) Critical Ratio