Professional Documents
Culture Documents
Tie Beams and Grade Beams
Tie Beams and Grade Beams
I '
F---5
Unlike tie beams, grade beams can carry walls and other loads. See
Fig. 11.2.
Grade beams are larger in size than tie beams, since they carry loads.
After construction of pile caps or column footings, the next step
is to construct tie beams and grade beams. Qualified personnel must
supervise the placement of rebars prior to concreting. See Fig. 11.3.
150 Geotechnical Engineering Calculations and Rules of Thumb
Note that the contractor should provide rebars jutting out prior
to concreting of pile caps. That way, when the grade beams are
constructed, continuous rebars could be provided.
Construction Procedure
9 Concrete a section (as an example, concrete from point A to point B
in Fig. 11.4).
9 Wait a reasonable time period for the concrete to contract.
9 Concrete the n e x t section.
9 This w a y a n y c o n t r a c t i o n in the concrete is eliminated.
9 Typically, engineers r e c o m m e n d c o n s t r u c t i o n joints every 60 to 100 ft
of beams.