Professional Documents
Culture Documents
Report 1
Report 1
A. PREFACE 3
B. ACKNOWLEDGEMENT 4
C. ABSTRACT 5
D.ABOUT NHPC 6
CHAPTER 1: INTRODUCTION 7- 10
1.1WATER POWER
1.2ADVANTAGES OF
HE PLANT
1.3HYDROLOGY
1.4SITE SELECTION
1.5 HYDROELECTRIC
SCHEMES
CHAPTER 2: COMPONENTS OF 11-25
HYDRO PLANT
2
PREFACE
The concept of power plants was conceived in the 1890s due to
the requirements of advanced performance and built-in
intelligence for modern power needs. Since then, the study of
power plants and generators has become a very active research
area in engineering and science. Across the wide spectrum of
power a number of them are considered to be `smart' in
complete examination include generation and irrigation plants
.In particular, power generation and effective transmission is a
relatively well in both . Therefore, this type of system has
attracted substantial attention from researchers in academia and
industry.
In recent years, it seems that research on generation within the
realm of flawless power plant has been overwhelmingly focused
on the analysis of country’s needs. In fact, there are many other
countries using our technologies. However, such applications
are usually studied by researchers in physics and electrical
engineering and may not be known to colleagues working in the
area of power. In view of this, a special issue on power
generation was undertaken.
3
ACKNOWLEDGEMENT
Materials in this report have been drawn from a wide variety of sources
including weekly journals, books, magazine and internet. Sources of
these works are cited where they are discussed in the text, and I hope
that I have made no omissions.
We sincerely extend our deep felt regards for their able guidance
throughout this training period, and NHPC for providing us with
eminent environment and essential resources to complete our summer
training.
4
Sweta Kumari Sonali Chakraborty
(DE/06/EE/06) (DE/05/EE/103)
ABSTRACT
5
ABOUT THE ORGANIZATION; NHPC PIONEER IN HYDRO POWER
DEVELOPMENT:
National Hydroelectric Power Corporation Ltd.,(NHPC) was established in
1975. With an authorized share capital of Rs 15,000 crore and an investment
base of about Rs 24,000 crore, NHPC is ranked as a premier organization in the
country for development of hydro power and aims to become a 10000 MW plus
company by 2012.
So far, NHPC has completed 10 projects with a total installed capacity of 3755
MW which includes 1000 MW Indira Sagar Project, a joint venture of NHPC
with govt. of Madhya Pradesh. Besides this, NHPC has commissioned the 14.1
MW Devighat Project in Nepal, 60 MW project Kurichu Project in Bhutan and
the 5.25 MW Kalpong Project in Andaman & Nicobar Islands as a deposit
work. At present 15 projects with a total installed capacity of 5722 MW are
under execution.
POWER GENARATION-
Power generation from NHPC is increasing year after year. During 2005-06,
NHPC power stations together generated 12567 million units. Over the years,
the machine availability has also increased and during 2005-06, the overall
capacity index achieved was 98.16%.
CONSULTANCY SERVICES-
The technical “know-why & know-how”, proficiency & experience of NHPC
places it in a leading position to offer a wide range of “world class”
consultancy services from” concept to commissioning along with operation and
maintenance”.
RESEARCH AND DEVELPOMENT-
The R&D wing of the Corporation is carrying out extensive experimental
studies for extension of life of underwater components subjected to erosion by
silt in the power stations.
FORTE OF NHPC –
Hydroelectric projects involve Head works related to dams/barrages with
associated structures, power channel etc. and underground works related to
desalting basins, head race tunnel, surge shaft, pressure shaft, power house, tail
race tunnel etc.NHPC has gained expertise in executing these works which is
unmatchable in the country.
6
CHAPTER 1: INTRODUCTION
India is blessed with immense amount of hydro-electric potential and ranks 5th in
terms of exploitable hydro-potential on global scenario. As per assessment made
by CEA, India is endowed with economically exploitable hydro-power potential to
the tune of 1 48 700 MW of installed capacity. The basin wise assessed potential is
as:-
In addition, 56 number of pumped storage projects have also been identified with
7
to various constraints confronting the sector.
In 1998, Government of India announced "Policy on Hydro Power Development"
under which impetus is given to development of hydropower in the country. This
was a welcome step towards effective utilization of our water resources in the
direction of hydropower development. During October 2001, Central Electricity
Authority (CEA) came out with a ranking study which prioritized and ranked the
future executable projects. As per the study, 399 hydro schemes with an aggregate
installed capacity of 1 06 910 MW were ranked in A,B & C categories depending
upon their inter-se attractiveness. During May 2003, Govt. of India launched 50
000 MW hydro initiative in which preparation of Pre Feasibility Reports of 162
Projects totaling to 50 000 MW was taken up by CEA through various agencies.
The PFRs for all these projects have already been prepared and projects with low
tariff (first year tariff less than Rs.2.50/kWh) have been identified for preparation
of DPR.
RUN-OFF
8
It is the part of the precipitation that flows on the ground surface of the
Catchment area & can be used for power generation. Investigations of run-off
form the first phase in the planning of a hydro-electric plant. The factors
effecting run-off are-rainfall pattern, geology of the area, shape & size of the
catchment area, the topography and nature of soil in the catchment area, amount
of vegetation and weather conditions in the catchment area.
STREAM FLOW
A knowledge of the quantity of water flowing in the stream and its variation
with time over a period of time is necessary to estimate the available energy.
The stream flow measurements are generally done on “10 daily basis”. The
measurement are done by stream gauging at site, every ten days, which amounts
to three times a month and 36 times a year. The investigations over a long
period, say 10 years, are necessary to cover the minimum & maximum flow
conditions.
HYDROGRAPH
A hydrograph provides the following information-
1)the discharge at any time during the period under consideration.
2)the maximum & minimum run off during the period.
3)total volume of flow up to any time is given by the area under the curve
up to that time.
Many factors have to be considered in the selection but the following are the
most important:
9
capital cost of the plant is reduced. The head of water depends upon the
topography of the area.
h) Access to site-The site selected should be such that the material &
machinery required could be transported easily.
10
1.5. HYDRO ELECTRIC SCHEMES
• RUN OF RIVER(ROR)
• PONDAGE
• STORAGE
• TIDAL PLANTS
• DEPRESSION PLANTS
• PUMPED STORAGE
Run of river: In this type of hydro electric schemes river water flow is used to
generate power but this system isn’t applicable in seasons when water isn’t
available in full flow that is in offsprings.
ROR with pondage : In this type of system river water is stored in a pond
constructed at some distance from the power house .This pond is known as
forebay and water is transferred from the forebay to power house using
11
penstocks. It provides with enough water in times of peak hours and during lean
periods river flow is used to generate power.
Storage: This type of system is generally meant for multipurpose projects such as
irrigation+flood control + power generation these provide us with enough water
for peak requirements. These are built up with adjacent dam storage so that there
is enough water during peak requirements.
Pumped storage: In this type of scheme water is pumped back using the same
turbine as turbine from the tail race during lean periods, and this water can be
utilized during load requirements.
Tidal plants : These are the plants were the level difference created by the
tides inside the river is used to generate power . These depend totally on the tidal
range available at the site. Tidal range is given by:
Main problem which is encountered at the tidal plants that the power gene
ration at these plants is totally dependent on the geology of the site .
Depression plants : In remote areas vast areas of low level lying land with
water are available , these are used to generate power at the sites. Power is
generated by dropping water in the depression.
Problem faced by depression schemes: That the outlet is a generally not available
therefore there is a lot of problem in the excavation of water through the
depression, and this is more pronounced when evaporation is not enough.
CONCENTRATEDFALL DIVIDEDFALL
12
• CONCENTRATED FALL TYPE: In this type of scheme power station is
adjacent to the diversion structure were water falls i.e. dam type storage is
provided for power plants.
• DIVIDED FALL TYPE: Power station is away from the diversion structure
therefore water is transferred through the penstock from forebay to the
power house.
• MIDGET : 99kw
• LOW CAPACITY PLANTS : 100-999KW
• MEDIUM CAPACITY PLANTS : 1000-9999KW
• HIGH CAPACITY PLANTS : 10,000KW
Interconnected power plants are further classified in to two types based on load
requirements-
INTERCONNECTED
13
POWER STATION
SEMI-OUTDOOR
INDOOR OUTDOOR UNDERGROUND
• INDOOR: Generators are placed inside machine hall having indoor crane.
Generator room is fully enclosed and is of sufficient weight to permit
transfer of equipment by means of indoor crane.
• SEMIOUTDOOR: Generator room with relatively low roof and gantry crane
characterized by outdoor station and transfers equipment.
14
• Less effect of seismic forces.
• Better protection against aerial attacks.
LIMITATIONS
• UNIT BAY : this is the space occupied by the main machine and is known
as machine hall
.
• ERECTION BAY: this is in continuation to the unit bay for handling of
equipment during erection and maintenance.
• CONTROL BAY: this is the space for locating electrical control equipment.
15
CHAPTER 2: COMPONENTS OF HYDRO POWER PLANT
16
BUS
GOVERNOR GENERATOR DUCT GSU
SPIRAL
CASING &
PENSTOCK WICKET TURBINE DRAFT TUBE TAIL RACE
GATE
MAIN COMPONENTS
1. DAM OR BARRAGE
2. HYDRO MACHANICAL EQUIPMENT
3. INTAKE STRUCTURE
4. HEAD RACE TUNNEL OR OPEN CHANNEL
5. PENSTOCKS
6. MAIN INLET VALVES
7. POWER HOUSE INCLUDING TURBINES,
GENERATORS
8. TAILRACE TUNNEL
17
DAM OR BARRAGE
The function of dam in a hydro electric project is to create an artificial head and
storage. It diverts the flow of water so that the same could be used for
generation of power. The selection of dam type for a particular location depends
upon the topography of the site.
A classification of the various types of dam is given below. Of these, the
“solid gravity concrete dam” is most commonly used.
Solid Gravity Concrete Dam: The height of dam depends on the strength
subsoil strata. It relies on its weight for the stability of the dam. The volume of
concrete used in the construction of such a dam is very huge.
DAM
SOLID GRAVITY
ARCH DAM EARTH DAM
CONCRETE DAM
18
Fig 3. URI BARRAGE
Fig.4.SALAL DAM
19
FOREBAY
It is an enlarged body of water at the intake to store water temporarily to meet
the hourly load fluctuations. It may be the enlarged section of the canal or a
pond.
INTAKE
The function of intake is to provide a passage to flow into the water channel or
penstock.
TRASH RACK
Used to block the passage of wood logs or aquatic species through the forebay.
PENSTOCK
It is a channel used to transfer the water to the power house from the forebay. It
may be of low pressure type or high pressure type. Each turbine has a separate
penstock. It may be buried below the earth or exposed.
SURGE TANK
The function of surge tank is to absorb the sudden changes in water
requirements so as to prevent water hammer & vacuum. It should be located as
near the power house as possible.
SPILLWAY
The spillway is designed to discharge the major floods without damage to the
dam but at the same time maintain a permitted head.
Types of spillway –
SPILLWAY
20
TAIL RACE
Channel provided were water which left out after striking the turbine
blades travel to a medium were water could be collected and could be used in
non peak hours .
VALVES
Valves are mechanical devices that are used to isolate, or release fluid, flowing
through pipelines.
TYPES OF VALVES:
1) Butterfly valve (for heads only up to 200m)
2) Spherical valve (for heads above 200m)
APPLICATION OF VALVE:
1) Penstock
2) Turbine inlet valve
NEED:
1. At lower heads, for inspection or maintenance of turbine without involving
the time necessary to drain and refill the penstock.
2. For higher heads, they perform the same function but are also used to
relieve pressure of the wicket gates or needles when the turbine is under
shutdown for an extended time.
DESIGN ASPECT:
21
2. Hydraulic losses are negligible.
3. Closure is good
4. Space requirement are large.
COMPONENT MATERIAL
Valve Body Mild
Steel,Manganese
Steel,Cast Steel
Valve Disc -do-
Trunnion Carbon Steel, High
tensile Steel, Mild
Steel, Cast Steel
Bushes Gun Metal, Bronze
Seal Fibre reinforced
solid rubber
Seal Seat Stainless Steel
22
For very high heads it is usually found desirable to provide spherical valves
upstream of the turbine, for normal unit shut down, as well as butterfly valves at
or near the start of the penstock as a further security measure.
AIR VALVE:
The size of the air valve should be sufficient to release / admission of air
according to rate of filling or draining of water in the spiral casing/ distributor.
23
Fig.5. BUTTERFLY VALVE
24
Fig.6. SPHERICAL VALVE
25
CHAPTER 3: HYDRO TURBINES
T Y P E S O F H Y D R O - T U R B
R E A C T I O N I M P U L
F R A N C IS K A P L A N P R O P E L L E BR U L B P E L T O N
( B A S E D O N F L O W )
A X I A L M I X E D T A N G E N T I A L
( R A D I A L + A X I A L F L O W
K A P L A N F R A N C I S P E L T O N
26
3.2. BRIEF INTRODUCTION OF HYDRO-TURBINES
PELTON TURBINES
A Pelton turbine works under large head and low quantity of water. The
potential energy of water in penstock is converted into kinetic energy in a jet of
water issuing from a nozzle. The pressure inside is atmospheric pressure. The
water jet impinges on buckets fixed on the periphery of rotor and causes motion
of the rotor. After doing the work, water discharges into the tail race. Most of
the Pelton turbines have just one jet though machines with two or four jets are
also used. The rotor or runner is made of cast steel. Buckets are made of cast
iron, bronze or stainless steel. Pelton turbines have usually horizontal
alignment.
FRANCIS TURBINE
A reaction turbine develops power partly due to the velocity of water and partly
due to the difference in pressure acting on the front and back of the runner
buckets. The Francis turbines are built in large sizes and are generally of
vertical type to effect economy in space. The alternator is mounted above the
turbine & thus is free from flooding. A modern Francis turbine is an inward
mixed flow reaction turbine. The motion of water is controlled by movable inlet
wicket gates, fixed around the runner, through which the water passes on its
way from SPIRAL CASING to the runner. After doing the work, water is
discharged to the tailrace through a closed tube known as draft tube which has a
gradually enlarging section. The free end of the draft tube is submerged deep in
tailrace water level.
27
also capable of reverse operation as a pump and is ideally suited for a pumped
storage scheme.
28
Fig.8. PELTON TURBINE
29
Fig.9. FRANCIS TURBINE
30
Fig.10. KAPLAN TURBINE
31
Fig.11. DISTRIBUTOR AND NOZZLES
32
TURBINE SPECIFIC HEAD
TYPE SPEED (m)
(m-kW)
HEAD
SPECIFIC SPEED
EFFICIENCY
OUTPUT
• FOR PELTON
H = MDDL+ 2/3(FRL -MDDL) - TCL - Head loss
33
Specific speed is defined as the speed in revolutions per minute at which a
turbine would run at the best efficiency for full guide-vane/nozzle opening
under a head of one unit and its dimensions having been adjusted to produce
unit power output.
Mathematical expression,
NS= N * (P1/2/H5/4)
Where, N= Shaft speed in rpm, H= Rated head in m, P= Rated output on Kw.
EFFICIENCY OF TURBINE-
KAPLAN – 93%
FRANCIS – 94%
PELTON – 92%
34
Fig.12. OPERATING CHARACTERISTICS OF TURBINES
35
OVERLAP ZONES
Where the head and specific speed fall in the overlap zones, selection is
governed by many other factors. They are:
36
3.6. COMPARISON BETWEEN DIFFERENT TYPES OF HYDRAULIC
TURBINES-
FICTITIVE COMPARISON
Assuming a net head of 100m and power required equal to 100 MW, we find
out the most suitable turbine type as follows-
First, the various turbine parameters, such as suction head, shaft speed,
etc., are calculated.
TURBINE Shaft Runne Suctio Total
TYPE speed r n head turbin
(rpm) diamete (m) e
r width
(m) (m)
PELTON 62.5 6.5 +5 30
37
Then, the turbine with the most reasonable and suitable parameters is
selected. In this case, it turns out to be the Francis turbine. The Francis
turbine is selected due to the following reasons-
1. Pelton:Large size, low speed generator.
2. Bulb: Extreme turbine setting.
3. Kaplan: Turbine setting is too high, Size
equivalent to Francis, higher speed and probably
a cheaper generator.
5. Francis: Therefore, OPTIMUM selection.
ECONOMIC
1. SETTING OF TURBINE
2. UNIT SIZE
3. COST OF GENERATOR
TECHNICAL
1. DIFFERENT SHAPE OF EFFICIENCY CURVES
2. NET HEAD VARIATIONS
MAINTENANCE CONSIDERATIONS
3. PART LOAD OPERATION
38
7. Regulating ring
8. Turbine guide bearing
9. Shaft seal
MATERIAL COMPOSITION-
PELTON 15 to 30 20 to 45
FRANCIS 30 to 35 35 to 55
KAPLAN/BULB 30 to 50 30 to 65
/PROPELLER
39
Fig.13. LOW SPEED AND HIGH SPEED FRANCIS RUNNERS
40
CAVITATION IN TURBINES-
When the absolute pressure at any point in the space occupied by flow reaches
the vapour pressure pertaining to the prevailing temperature, vapour bubbles
develop and voids filled with vapour are formed in the fluid. Bubbles formed on
the back surface of the runner vanes and adhering to them may, because of the
high-speed whirl, eventually reach points of relatively very high pressure where
an explosion like collapse ensues exerting a violent impact upon the surface
adjacent to the void.
41
Fig.15. DAMAGED BLADES OF A KAPLAN TURBINE DUE TO
CAVITATION
42
3.9 .GOVERNOR AND SPEED REGULATION
The function of governor is to keep the speed constant when the load on the
turbine increases or decreases. To maintain the frequency of electric supply
constant, the speed of alternator, driven by the hydraulic turbine, must remain
constant. As the load changes, the governor changes the rate of flow of water to
bring the speed back to the normal speed and maintains a balance between the
power output and input..
43
CHAPTER 4: HYDRO GENERATORS
4.1 INTRODUCTION: These are low speed machine of the salient Pole
type. They have large no. of poles. Rotor is characterized by large
diameter and short axial length. Capacity of such generator varies
from 500 KW to 300 MW. Power factor are usually 0.90 to 0.95
lagging. Available head is a limitation in the choice of speed of hydro
generator. Standard generation voltage in our country is 3.3KV,
6.6KV, 11 KV, 13.8 KV, & 16KV at 50 Hz.
44
1) SUSPENSION TYPE:
In this type, the thrust bearing is located in upper bracket above rotor.
2) UMBRELLA TYPE
In this type, the thrust bearing is located in lower bracket below rotor.
45
Fig.25. SUSPENDED TYPE
46
Fig. 26. UMBRELLA TYPE
47
Fig. 27. SEMI UMBRELLA TYPE
STATOR
The main components of stator are-
STATOR SOLE PLATES
STATOR FRAME
STATOR MAGNETIC CORE
STATOR WINDINGS
48
Withstand centripetal and unidirectional magnetic forces which may result
on account of eccentricity of rotor
Guide the cooling air towards heat exchangers
Allow a good positioning of magnetic core punchings.
Allow stator handling.
Support the connections and terminals
The stator frame is made up of rolled steel sheets supported by vertical beams
of high inertia. The frame is shipped to site in single or several parts depending
upon the handling and transportation limitations of the site.
3) STATOR MAGNETIC CORE –
The punchings are stacked into elementary layers which are separated by
spacers to cater for radial ventilation which enables air circulation for cooling
active parts. The punchings are axially clamped to reach a strong cohesion to
form rigid system and the stacking process is done at different stages
4) STATOR WINDING-
Stator Windings can be of Double Layer Bar Type Wave connected or Coil
type Lap connected. For Hydro generators normally bar type wave
connected windings are used. Each bar is composed of an assembly of
strands of small radial section in order to reduce copper losses. Each strand
is in turn insulated by glass lapped tape with epoxy resin.
Each bar is insulated over its whole length by continuous taping according to
class ‘F’ insulation.
The connection between bars is achieved by means of copper plates brazed
to the individual strands and are insulated by having gaps filled with post
polymerized resin.
The whole winding is totally insulated without any bare point to avoid fault
on account of moisture/polluting agent.
The windings are fastened to the supporting rings to form a homogeneous
and solid assembly.
49
Fig. 27. STATOR SEGMENT
50
51
Fig. 28. STATOR WINDING
ROTOR
ROTOR COMPONENTS
ROTOR SHAFT
ROTOR SPIDER
ROTOR RIM
ROTOR POLES
RING COLLECTORS
1) ROTOR SHAFT-
Rotor shaft has to achieve the following functions:
Provide coupling face for turbine shaft
To transmit the motor or braking torques between the turbine shaft and the
rim through rotor spider.
Provide surface for thrust, upper and lower bearings
To provide for lifting of rotor.
The shaft is made either as a single part or in case of shaft less rotor, then two
stub shafts are connected to the rim at the upper and lower parts for
accommodating thrust bearing surface and coupling flanges.
2) ROTOR SPIDER-
Rotor spider has to ensure following functions:
52
To transmit the motor or braking torques between the turbine shaft and the
rim.
To ensure the centering of the rim and the poles.
To support the braking track and withstand its centrifugal forces.
To ensure the passage of the cooling air flow to the rim.
The spider is composed of discs and ribs welded longitudinally to the shaft.
The ribs are designed to accommodate machined bars for guiding the rim plates
53
Fig. 29. ROTOR SPIDER
54
3) ROTOR RIM-
The rotor rim ensures the following functions:
To accommodate the field poles.
To ensure the magnetic flux path from one pole to the other.
To take part in the fan effect of the radial cooling of the synchronous
machine.
To contribute in providing the required inertia.
The rim constituted by stacking of 3 to 5 mm thick segments made of rolled
sheet. Segments are clamped axially by means of high resistance steel bolts
The stacking is so designed in to numerous overlapped layers so as to permit
provision of radial ducts in the inter-pole axis without reckoning mechanical
resistance. Thus, rim acts as centrifugal fan uniformly distributing air flow over
the whole generator length.
55
5) ROTOR POLES-
The rotor poles ensure the following functions:
Create the induction flux and distribute it properly in the air gap
Suppress the asynchronous flux waves and damp the oscillations (damper
winding)
Transmit the torque from rim to the air gap
The pole cores are constituted of a stack of punched laminations which are
clamped between two end plates traversing the entire length of the pole. The
field coils are made of flat copper strips brazed at each coil edge. The inter-turn
insulation is achieved by strips of epoxy insulation. The coil assembly is hot
polymerized under pressure to achieve required electrical and mechanical
properties. Coil insulation w.r.t. ground is made by wrapping the pole core with
an insulating complex .The poles are weighed and distributed around the rim
during the assembly so as to have same weight diametrically opposite to each
other.
56
BRACKETS-
These are provided for housing of Thrust and Guide bearings. Two types of
brackets are provided for a generator:
Upper bracket
Lower bracket
UPPER BRACKET:
The upper bracket has to ensure the following functions:
Support vertical loads of generator upper floor and the superstructure
To take upper guiding radial forces tangentially to the concrete walls of the
generator pit
To accommodate and transfer the vertical load of the rotor and turbine
assembly in case of suspended type of machine.
To provide path for circulation of air.
The upper bracket is composed of central hub supporting the guide and/or
thrust bearing
The structure is formed by lattice of laminated steel beams resting on upper
part of the stator frame which are anchored to the generator pit either
directly or through radial jacks.
Air baffles fitted on the bottom side of the upper bracket allow proper
circulation of air flow
The upper bracket is shipped in single or several parts and are assembled at
site as per the requirements
LOWER BRACKET:
The lower bracket has to ensure the following functions:
Supports the lower guide bearing and it combines braking and lifting jacks
In case of umbrella / semi-umbrella it may also house the thrust bearing and
therefore need to transfer load of rotor and turbine to the foundations
It is composed of central hub with steel arms welded to it.
The bottom side of the arms are provided with fixing arrangement for fixing
them upon anchoring plates which are embedded in the concrete
The upper side of the arms accommodate for braking and lifting jacks along
with necessary pipeline i.e., oil and air pipelines.
The hub will accommodate for guide bearing and / or thrust bearing as per
the requirement.
57
GENERATOR AUXILIARIES
EXCITATION SYSTEM
AIR COOLING SYSTEM
BRAKING AND JACKING SYSTEM
BEARINGS
FIRE PROTECTION
HEATERS
EXCITATION SYSTEM
Excitation systems supply and regulate the amount of dc current sent to the
generator field winding.
58
EXCITATION SYSTEM – COMPONENTS:
1. EXCITATION TRANSFORMER (DRY TYPE )
2. RECTIFIER SYSTEM
3. AUTOMATIC VOLTAGE REGULATOR
4. FIELD FLASHING UNITS
5. FIELD CIRCUIT BREAKER
6. DISCHARGE RESISTOR
CB BUS-1
BUS-2
GCB
GENERATOR TRANSFORMER
UAT
EXC.TR.
A.C REF. VOL.
PT
G
AVR
GATE CT
F.F CONTROL
FB G
D.C GENERATOR
DR NGT
59
AIR COOLING SYSTEM
Generator is provided with a closed, recirculating air cooling system
The cooling pressure is created by fanning action of rotor spider
The air circulates through radial ducts provided in the rotor rim which
allows a cooling air flow to be distributed radially and uniformly all along
the machine axis
The air circulation path is spider-> rim -> inter-pole areas-> stator winding-
> stator core radial duct-> air coolers-> lower and upper floors-> lower and
upper air baffles-> spider.
STATOR AIR COOLERS-
The heat generated in the generator is cooled in a closed circuit through air
to water heat exchangers (air coolers)
The coolers are equally spaced around the outer periphery of the frame.
Each cooler is composed of finned Cupro-Nickel tubes the extremities of
which are fixed to two drilled end plates connected to water boxes.
Distribution of cooling water through water inlet and outlet pipes is
connected to water boxes.
The number of the air coolers of a generator is designed to allow the
operation of generator with one cooler in out of service.
BEARINGS
60
Vertical hydro generators are normally provided with thrust bearings and
guide bearings
The number of guide bearings depends on the size of the machine
THRUST BEARINGS:
The hydro generators have thrust bearings located either at the top (Suspended)
or at bottom (Umbrella / Semi-umbrella) of the generator to support the rotating
weight of the machine.
Types of thrust bearings:
Tilting pad bearings
Leveling plates self equalizing bearings
Spring bed mattress type bearings
Self compensated diaphragm bearings
GUIDE BEARINGS:
Hydro generators are provided with lower and / or upper Guide bearings for
maintaining the shaft in alignment.
The guide bearing essentially consists of
A set of tilting pads distributed radially.
Support ring for pads.
Wedges for holding the pads.
Oil filled tank for housing the above components with arrangement
for cooling the heated oil by means of oil to water exchanger.
61
Installation of flow meters at cooling water pipe lines
Oil level gauges in bearings
Limit switches for brake and jack operation
Vibration detectors
Speed detectors
CT’s for measurement of fault currents.
SPACE HEATERS
Air heating resistors are provided at the lower part of the generator enclosure to
prevent condensation of moisture near the windings. The space heaters are
equally located along the periphery of the enclosure. The heaters can be
actuated manually or automatically by means of thermostat when the generator
is under stand-still condition.
62
CHAPTER 5: TRANSFORMERS
5.1.TRANSFORMER CONSTRUCTION-
The simple elements of a transformer consist of two coils having mutual
inductance and a laminated steel core. The two coils are insulated from each
other and also from the core. Other necessary parts are: some suitable container
for assembled core and windings, a suitable medium for insulating the core and
its windings from the container, suitable bushings (either of porcelain, oil-filled
or capacitor type) for insulating and bringing out the terminals of windings
from tank.
Constructionally, transformers are of two general types, distinguished merely
by the manner in which the HV and LV windings are placed around the
laminated core. The two types are-
Core type
Shell type
63
Core Type Shell Type
Winding surround aCore surround a considerable
considerable part of core part of winding
64
5.2.CLASSIFICATION-
Based on
Construction – Shell type , Core type
Type of Cooling- Air cooled , Oil cooled
Type of Supply- 1- φ , 3- φ
Type of application – Step up & Step down
Purpose of uses – GSU , UAT , SST,Excitation &Distribution
transformer
65
FIGURE 4 - THREE PHASE TRANSFORMER CORE
W ITH W INDINGS ON THE THREE LIMBS
5.3.COOLING OF TRANSFORMERS-
Air blast- Transformer is cooled by continuous blast of cool air forced through
cores and winding. External fans are used for this purpose.
66
B) ONAN (Oil Natural Air Natural) - The oil is cooled in tubes or
external radiator by natural circulation of air
A) Installation Site-
67
The location and environment where the transformer will be installed is a major
concern and may limit the type of the transformer that can be used. Focus is
given towards following:-
Installation flexibility
Ambient conditions
Environmental Safety
Flammability
Public access restriction
B) Transformer Use
To specify the correct transformer following points are analyzed:
Where the Transformer is 1 - φ or 3 - φ
How will the Transformer be Connected
What is the configuration of the system
C) Transformer Capabilities
The capabilities of a transformer includes
Ratings
Electrical Capability
Mechanical Capability
C) Cost
Cost issue should focus on total cost of the transformer during lifetime which
includes
Initial cost
Hidden cost
68
If cost is the only issue oil filled transformers are most logical solution
having lowest initial cost. However other issue (i.e, Hidden cost which
includes site preparation, maintenance, cleanup, design life, efficiency,
reliability etc.) affecting cost during the transformer lifetime should not be
overlooked.
b) There may be air drawn by the oil pump or coming from an air
pocket which did not get evacuated at the time of commissioning.
It is possible to detect this condition also from Buchholz relay.
c) It also indicates a drop in the oil level below a limit necessary for
the correct operation of the transformer.
69
The principle of operation of the Buchholz relay will be clear, if we
refer to a cross-section of a typical Buchholz relay (Figure - 17).
Fig. 17
The body of the relay contains 2 metal floats b1 and b2, which may pivot
around their respective shafts 01 and 02 and thus control the mercury
contacts c1 and c2. Each of these 2 contacts closes an alarm or a trip
circuit.
70
OPERATION OF RELAY UNDER SERIOUS FAULTS
A violent emission of gas due to serious fault causes the displaced oil to
surge through the relay, causing the bottom float b2 to operate and thus
closing the contact c2. This operates the trip circuit, which controls the
operation of the circuit breaker.
Oil and winding temperature indicators (OTI and WTI) are usually
mounted in the marshalling box when the transformers are installed
outdoor. When the transformers are installed indoor, OTI and WTI can
be mounted directly on the tank wall also. They work on the principle of
liquid expansion and provide local indication of top oil.
71
Fig.8. EXPLOSION VENT
72
CONSERVATOR
As the temperature of the transformer oil increases or decreases, there is a
corresponding rise or fall in the oil volume. To account for this, an expansion
vessel commonly known as ‘conservator’ is connected to the transformer tank. The
oil level in the conservator is indicated by a float type gauge or prismatic level
indicator or both provided on its end covers.
During breathing of transformer the outside air comes in contact with the oil in the
conservator. This tends to add moisture and also dust particles in the oil in
conservator. The connecting pipe work to the tank is so designed that the lower
part of the conservator acts as a sump in which any impurities entering conservator
will collect.
When more than half of the silica gel turns pink from blue, silica gel should be
reactivated/replaced.
73
Fig.
74
A better system of keeping the conservator oil free from contamination will
be to prevent its contact from atmospheric air. This is achieved by using
synthetic rubber bellow or bag in the conservator. Any expansion or
contraction of oil due to temperature variation takes place by the
corresponding inflation or deflation of rubber bag. The conservator is
connected to a silica gel breather in a normal way to take care of the change
in volume of air surrounding the rubber b
EXPANSION AREA
OIL BAG
75
PRESSURE VACCUM VALVE AIR BAG
HAND HOLE
DRAIN VALVE
BREATHER
Fig.20
OFWF COOLERS
A pre-requisite for using water coolers is the availability of a source of
sufficient quantity of water. In most of the transformers for hydro
power stations, OFWF cooling (oil forced- water forced) is used. The
heat from oil is taken out by water passing through a nest of tubes. The
hot oil from the transformer tank is distributed over the cooling surfaces
of the tubes by baffles, which are arranged at regulator intervals along
the tube stack as shown in figure - 21.
76
Figure 14
Fig. 21 OFWF COOLER
It is ensured while designing the cooler and its pipe work that the oil in
the cooler is maintained at a pressure higher than that of the water. This
prevents any leakage of water into the oil system in the event of a fault
developing in the cooler.
The coolers are available for horizontal or vertical mounting. This can
be either floor mounted or directly on the transformer tank wall.
The material used for the cooler tubes stack is stainless steel, copper or
admiralty brass depending upon the impurities present in cooling water.
Generally 2-100% coolers are used, one cooler acting as standby. For
better flexibility, by regulating the various interposing valves, it is
possible to use either cooler with either of the pumps.
To avoid the building up of back pressure in the water circuit, the water
outlet from the cooler should be perfectly free and not obstructed by
valves etc. The preferred form is a pipe emptying into a drain open to
the atmosphere.
OIL PUMP
The oil pump is provided at the oil inlet side of the cooler, taking out
hot oil from the top of the transformer tank and delivering it through the
cooler to the bottom of the tank. This is a closed circuit operation as
shown in the figure - 22.
77
Fig.22. OIL PUMP
The pump is required to develop enough pressure, to overcome the
frictional head loss during the flow of oil in pipe work, cooling
equipment and windings etc.Transformer oil pumps employ special
feature of construction in which the pump and motor is an integral unit.
The pump impeller is screwed and locked on the driving motor shaft.
The motor unit is embodied inside the pump casing completely
immersed in transformer oil and is cooled by the surrounding oil.
78
Fig. 23. SCHEMATIC DIAGRAM OF A FLOW INDICATOR
When liquid starts flowing through the pipe, the vane gets deflected
along with the vane shaft. This deflection is transmitted through a
magnetic coupling to an indicating needle on the dial. The needle
indicates the flow of liquid corresponding to vane deflection. When the
flow in the circuit drops to 70-80% of full flow, a switch provided in
the instrument closes with the help of a cam and initiates the alarm.
79
MARSHALLING BOX
BUSHINGS
The bushings are used for receiving terminals from windings on the oil
side and connecting them to bus duct, transmission lines, feeders etc. on
the air side. Normally, oil filled porcelain bushings are used for
voltages up to 33 KV, though in some cases condenser type bushings
have also been employed . In porcelain type, bushing consists of a
conducting bolt or tube within a porcelain jacket and is filled with oil
having communication with oil in the transformer tank.
The condenser type bushings generally consist of a central metallic
conductor tube enclosed by wound paper condenser layers for field
control. A porcelain jacket is provided on the bushing condenser core
and the space between the porcelain and the core is filled with oil. Air
space is left in the bushing top cap for the expansion of oil. A sight
glass is provided to indicate the top oil level.
VALVES
Each transformer has number of valves fitted on it for meeting different
functions such as oil draining, filtering, sampling, isolating valves in
cooling circuit and other pipe work, radiator opening/closing valves, air
release valves/plugs etc. The valves may be double flanged gate valves,
single end screwed or double end screwed globe type,
built in valves with flat surfaces on both sides. They may be provided
with open-shut indication with or without facility for pad locking.
80
TRANSFORMER DRYNESS PARAMETERS
MOISTURE CONTENT
Degradation of oil and insulation inside a transformer results into
formation of water and gas, which if not tackled at a proper time may
result into failure of a transformer.
Moisture is very important parameter which affects the dielectric
strength of oil particularly when the impurities are also present.
Therefore, it is essential that it is kept within limits. Transformer will
have to be dried using filter machine when the moisture content
becomes high, thus it is one of the parameters, which indicates the
dryness of transformer. Moisture content is measured using Karl
Fischer apparatus. Its measurements are taken at regular intervals
during dry out till the value reaches within acceptable limit.
When the filtration is carried out, first the moisture comes out of oil.
When oil gets starved, the moisture is released from the windings and
this way it goes on till equilibrium is established between the oil and
windings. More the moisture is removed from the oil, the more it will
come out of the windings.
The following table gives the desirable limits of moisture content inside
a transformer and the values at which the filtration should be carried
out.
81
Transformer Desirable limit of Value of moisture content at
Voltage Class moisture content which filtration should be
carried out
145 kV & above 10 ppm max. 20 ppm
82
along with moisture content and BDV of oil gives good indication
about the dryness of transformer. While carrying out the drying out
cycle using streamline filter machine, oil temperature as indicated by
oil temperature indicator should be recorded along with IR values taken
between HV winding and earth, LV winding and earth, and HV and LV
windings. When IR value is taken between one winding and earth, the
other windings should be earthed at that time. Usually these values
may be taken at an interval of 2 hours.
The insulation resistance in mega-ohms varies inversely with the
temperature. Though it cannot be taken as an absolute value but based
on experience it has been found that for every 10oC rise or fall in
temperature, the IR value changes by a factor K which is of the order of
1.6. This can serve as a good guide for conversion of IR values at
different temperatures. The factors thus worked out are tabulated
below:
Difference in temperature OC 10 20 30 40 50 60
Factor K 1.6 2.6 4.1 6.6 10.5 16.8
POLARISATION INDEX.
When the transformer is dry the IR value increases at a faster rate with
the time of voltage application. This property is used as guideline to
judge the dryness. The IR values are measured at 15 seconds and 60
seconds of application of voltage in one go and a ratio of 60 seconds
and 15 seconds values is known as polarization index.
IR Value at 60 seconds
Polarization Index
IR Value at 15 seconds
This index is generally of the order of 1.5 or more but it has been seen
that the winding having tap changer connected to it may have a
polarisation index of the order of only 1.3.
83
DEW POINT
The dew point measurement determines the amount of moisture in the
gas and is stated as the temperature at which it will begin to condense
out. A lower dew point temperature means a dryer gas. The gas to be
tested may be the gas above the oil or it may be the gas in a transformer
which is being transported or being stored. It may also be the gas used
to fill the main tank during drying out process.
Normally the moisture level of the insulation is less than or equal to 0.5
% for a transformer installed in the field.
84
Fig. 24. TRANSFORMER
85
86
CHAPTER 6: DESIGN AND ENGINEERING ASPECTS FOR HYDRO
POWER PLANT
6. GENERATING UNIT – SIZE SELECTION
Selection of unit-size is dictated by the techno-economic considerations
(hydraulic data, effective heat, flow rate, type of purchase, especially
pumped storage schemes, availability for peaking etc.) and transport
limitations. Space constraints for underground power house cavity also limit
the maximum unit-size to be selected for the prevalent hydrological
condition. However, within these constraints, attempts shall be made to
choose the layout & unit size so as to get benefits of economy due to size.
87
Hydro generators of more than 700 MW unit capacity are already in
operation in the world. In India the highest capacity so far is 250 MW in
Tehri & Nathpa Jakhari HEPs. Although, the increased unit sizes reduce the
cost per kW, floor space / kW & weight of the machine, the size of the
Hydro generating units is dictated by various considerations, which are taken
into view while deciding the unit size. The various aspects are:
Hydro generators are generally tailor made to site conditions & the
manufacturer has to examine the availability of sizes, variety & complexity
of various machine tools, implements & facilities.
88
The internal dimensions of the machine hall, width & height are determined
in accordance with the weight & size of the largest assembly. Foundation
construction depends upon the weight & size of the machine.
Site location imposes a limit on weight, height, length & width of any
package. In terms of weight limitation, strength of bridges etc. on the way
has to be critically examined before taking up the decision regarding Unit
size.
With the developments in metallurgy, superior insulation materials & new
methods of cooling, fast response digital governing & excitation systems,
improvement in manufacturing techniques & methods of erection, assembly
at site is gradually over coming the limitations imposed by Transport
conditions. Split type large capacity power transformers, split runners &
forged welded shafts are some of the latest developments which could help
in overcoming the logistical limitations due to transport.
The possible combination of head and capacity, even when speeds are
restricted by synchronous speed are so numerous that identical units can
hardly be used at more than one site.
The hydro projects being site specific, as such the use of standard or off the
shelf units may not be possible. Thus for the selection of turbine, a detailed
case study is carried out considering the various parameters/conditions. The
89
selection of type of turbine is made based on the “Head” and output. The
broad classification is given below:-
The above classification based on head is only a broad guide line and there
is a large overlapping zone, for which the following considerations are
taken:-
- Head variation
- Civil costs
- In flow variation i.e. part load operation
- Maintenance
- Efficiently
New design of turbine runners can increase the efficiency of older plants by
about 2%. Computer programmes help in accurately analyzing deformation and
stresses of structural components. Computer studies provide more reliable and
faster identification and quantification of losses to improve efficiency.
90
Design head (hd) is the net head at which peak efficiency of turbine is desired.
This head must be so selected that the maximum and minimum heads are not
beyond the permissible operating range of the turbine. Design head determines
the basic dimensions of the turbine. Design head (hd) is calculated
approximately by the following equation: -
(hd) : Minimum net head +2/3 (Maximum net head - Minimum net head)
Turbine setting depends on maximum net head, water vapour pressure and
barometric pressure corresponding to the site altitude. Usually, the center
line of the runner is placed lower than the minimum tail water level in case
of reaction turbines to minimize the cavitation effect.
91
Removal of runner from bottom
Normally adopted for high speed turbines with due consideration for runner
diameter.
The inlet valve is placed (connecting penstock to the turbine) just before the
scroll case in the water conductor system. MIV is used for normal operations &
types: -
Pressure rise and speed rise are function of water conductor system, inertia
of generating unit and the governor design parameters.
The permitted speed rise for reaction turbines should not be more than 60%
& for pelton turbine not more than 20%. However, a speed rise of about
50% is normally specified for reaction turbines to minimize vibrations.
Pressure rise shall not be more than 30 to 35% for Francis turbines 30 to 50
% for Kaplan turbines & for Pelton turbines not more than 15%.
92
6.2.10Governing System
- Speed/frequency control
- Load control
- Speed/load control.
Pressure oil system shall be provided for each turbine for operation of
turbine wicket gates/Nozzle/deflector servomotors through governors and
for control of MIV. For major H.E. projects, separate pressure oil system
should be used for turbines & MIVs for reliability consideration.
The trend is towards using higher oil pressure. The pressure of 60 Kg./cm2
often specified allows smaller valves, pressure tanks, pipings and
servomotors.
For higher oil pressure, piston type accumulator with nitrogen bottles shall
be used.
6.2.12Materials
Special care should be taken to choose the material of the under water parts.
The material for runner and guide vane is 13:4 Cr-Ni stainless steel and for
turbine shaft forged carbon steel. The material 16:5 Cr-Ni stainless steel is
also used for manufacture of runner. The other parts like stay ring, spiral
case, top cover, and bottom ring, regulating ring, draft tube liner and pit liner
are made of steel.
93
As most of the rivers in the northern belt of the country are heavily loaded
with silt, it erodes the turbine under water parts. Material Technologists and
the manufacturers are busy world over to develop various types of metallic
and non-metallic coatings to check the problem of silt erosion in parts like
Runner, Guide Vanes, MIV etc. The application of plasma nitriding,
ceramics and polyurethane polymers coatings by Guns, High Velocity Oxy
Fuel system (HVOF), etc. are being tried on parts like runner and guide
vanes. Development of better material and alloys to withstand silt
conditions in Himalayan region have also been identified for Research &
Development.
6.3. GENERATOR
The main important parameters to be specified/ finalized for the design of
the hydro generator are:
94
6.3.2 Rated Speed
The generator rated speed shall be matching the turbine or pump-turbine
rated speed. Speed selection has an extremely significant impact on the
generator/motor-generator design. Rated speed resulting in even number of
pair of poles is normally preferred.
The convention has been to define two sets of reactances with the following
designations:-
95
field and armature ampere turns. It is defined as the ratio of the field current
required to produce rated armature voltage at no-load to the field current
required to circulate rated armature current with the armature short circuited.
Typical values of SCR for large hydro-generators are as follows:-
1.00 1.250
0.95 1.175
0.90 1.100
0.85 1.050
0.80 1.000
96
6.3.9 Fly Wheel Effect
The fly wheel effect is defined by the equation
Fly wheel effect = GD² where
G = mass of the rotating parts (Kg)
D = 2x radius of gyration of the rotor (meters)
The fly wheel effect is expressed in terms of the machine H constant by
the equation:
H = 1.37xGD2xn2 x10–6/rated KVA
There are three possible bearing arrangements for large vertical hydro
electric machines, as follows:-
- Combined thrust and guide bearing mounted on a top bearing bracket
above the rotor. This conventional bearing arrangement (suspended type
97
with the thrust bearing located above the rotor is generally used for small
diameter, long core, high speed machines,
- Combined thrust and guide bearing mounted on a separate bearing
bracket located below the rotor (umbrella type arrangement).
The vast majority of large machines are constructed with the combined
thrust and guide bearing installed on a lower bearing bracket below the
rotor. An upper guide bearing is customarily installed above the rotor
and installed on a separate, light-weight guide bearing bracket mounted
on the top of the stator frame. This type of arrangement is termed as
semi-umbrella arrangement.
6.3.12Cooling System
Cooling of the machine should be as uniform as possible. Two basic
methods for cooling the stator windings of high capacity hydro-electric
machines are commonly employed, as follows:-
- Forced air cooling of the windings using either the natural fan action
of the rotor or with supplementary motor-operated cooling fans.
- Direct water cooling of the windings using de-ionized water passing
through the hollow strands of the windings to remove the heat.
98
Isolated phase bus-ducts is the acceptable method of connecting generators
to the step-up transformers for large sized units in modern power houses.
The isolated phase bus duct is available in both continuous and non-
continuous housing designs.
- The non-continuous design may be used for low-amperage circuit up
to 6000 A.
- The continuous enclosure design is used for higher current ratings.
The continuous housing design has higher losses than the non-continuous
housing design because of the higher enclosure currents circulated in the
continuous housing design. However, the continuous housing design is
always preferred.
- The starting bus for pumped storage plants shall be rated to carry the motor
starting current during start up from VFC or back to back from another unit.
For pumped-storage plants starting on back-to-back synchronous starting the
starting bus duct need be designed for currents as much as 3 times the
starting current required for motor starting by VFC (Variable Frequency
Converter).
All large hydro electric machines are having a wye-connected stator winding
with the neutral brought out of the machine housing and grounded via a
high-resistance circuit consisting of the following components:-
-A single-phase distribution type transformer connected between the
generator neutral and ground. This transformer should preferably be either a
dry-type or epoxy resin, cast coil type having a standard, high-voltage rating
approximately equal to 1.5 times the maximum machine phase-to-ground
terminal voltage rating. This higher voltage rating is recommended in order
to avoid excessive magnetizing inrush current when a ground fault occurs.
The secondary is normally rated 240/120 V.
99
On large, unit connected machines, the windings are connected to the power
system network via step-up power transformers. Voltage surges can only
enter the machine winding via the power transformers which are protected
by surge arresters connected to the high-voltage side of the transformers.
Surge protection comprising surge arresters and surge capacitors shall be
provided on the machine terminals.
100
- Correction for altitude and ambient temperatures
6.4.4 Efficiency
With the improvement in designs, the efficiency obtainable at rated load for
large power transformers is more than 99.7%.
6.4.6 Conservator
101
Diaphragm type oil sealing in conservator to prevent oxidation and
contamination of oil due to contact with moisture is provided. Diaphragm of
conservator shall be able to withstand the vacuum during
installation/maintenance periods. The connection of the air cell to the top
reservoir is by an air-proof seal preventing entrance of air into the
conservator.
Criteria
102
Power house - to be designed to provide a max. 1.0 ohm
resistance to ground.
6.6.3 Illumination
Lighting for each area of the Project is required in order to have illumination
needed to perform tasks normally associated with the area.
Illumination levels are based on BIS/ manufacturers catalog. Type of
luminaries is selected as per the requirement of the area plus aesthetic
factors. System is designed to ensure energy saving/ conservation by
providing suitable sensors etc.
General indoor and outdoor lighting and receptacle are served by 3-Ø, 4
wire A.C. system. Transformers and panels are located so as to optimise
wiring and to limit voltage drops to acceptable values. Fluorescent,
incandescent and high intensity discharge lamps shall be used to obtain
required intensities consistent with lamp life economy and functional
appearance.
103
- Fluorescent lamps are mostly used in interior spaces
- High-intensity Discharge (HD) Lamps:
Sodium vapour lighting fixtures are preferred for outdoor lighting such as
switchyards, spillways and dams, parking areas etc. Automatic switching
via photo electric cells can be adopted for outdoor lighting to optimise
power consumption.
Metal-halide fixtures are used for certain indoor areas such as erection bay,
generator hall, machine shop, turbine pit and other “high-bay” areas where
proper colour rendition is needed and long-life is essential.
Incandescent lamps should be used only for battery powered emergency
lights and for certain places where lights should not be turned on
continuously or where fluorescent fixtures are impractical.
Emergency lighting is deployed in the event that normal A.C. power
distribution system fails. The emergency requirement are at first met from
the diesel generator sets and when all alternatives of A.C. supply fail,
battery powered emergency fixtures provide the minimum requirement of
lighting. The battery should have sufficient capacity to provide 4 hours
uninterrupted illumination independently.
104
For laying of cables in a power house, a broad based system involving cable
gallery, trenches, racks, shafts etc. are provided.
In outdoor switchyards, a cable trench system is provided.
The main considerations/ practices are :
- High frequency cables/ control cables shall preferably be routed in
separate fire resistant conduits.
- Segregation & proper spacing is maintained.
- Proper attention should be given to Ventilation/ heat dissipation aspects
particularly in case of HV cables.
6.6.6 Unit auxiliary A.C. Supply System & Station Auxiliary A.C. Supply
System
To feed the unit essential auxiliaries and the station auxiliaries, unit
auxiliary/station auxiliary supply systems are provided.
105
compressor loads, lift load etc. are determined and maximum demand is
calculated at a diversity factor of 0.75. The availability of input supply is
ensured from sources independent of station generation. In addition,
adequate provision for meeting one unit auxiliaries load during
starting/stopping of unit is also kept and for this purpose the UAB’s are
connected to SSB through tie breakers.
- It is customary to provide 2 Nos. SSTs of equal capacity; one SST
being provided as a stand -by arrangement.
- In the event of A.C. supply failure, the station loads are supplied by a
D.G. Set of suitable capacity.
5.6.7Protection
- Protective relays are used to detect electrical faults and to alarm,
disconnect or shut down the faulted apparatus to provide for personal
safety and equipment protection.
- All relays used are suitable for operation with CTs secondaries rated
for 1 Amp or 5 Amps as per IEC/IEEE standards.
- Electrical faults are detected by protective relays arranged in
overlapping zones of protection so that each fault condition is detected by
at least two systems of protective relays. The relays are connected in two
groups viz Group A & Group B. Group A & Group B protective relays
should operate quickly to detect the fault and trip the appropriate circuit
breakers to interrupt the flow of current to faulty apparatus. Even one
group of relays malfunction, the other group of relays will operate and
clear the fault.
-Group A & Group B relaying systems should be completely separated by
using separate set of instrument transformers, segregated wiring and dual
redundant C.B. trip coils.
- Basic Types of Relays Used in Protection Scheme are: -
a) Over current
b) Over current with voltage restraint
c) Directional over current
d) Directional power
e) Differential relays
106
6.4.1 EOT Crane
EOT Cranes installed in the power station are not used so frequently after
completion of construction work. Therefore, slow-speed cranes which are
slow in hoist and travel are employed.
The span of the crane is determined by power house width in such way that
working range of the crane hooks is sufficient for the assembly and
disassembly of the main equipment in the power house. This working range
is expressed by the range of the travel and lift of the main and auxiliary
crane hook. The top of the lift (upper limit) is decided so that it is possible
to hoist and carry the rotor of the generator and to assemble the transformer
in some cases, without any trouble. The bottom of the lift (lower limit) is
decided to such a height as necessary for assembly and disassembly of the
water turbine.
Cooling water systems caters for the following cooling water requirement of
the unit: -
- Generator Air Coolers
- Shaft Seal
- Turbine and Generator Bearings
- Generator transformer cooling
Penstock Tapping
Penstocks are tapped and a common header is formed to meet the above
cooling water requirement.
- Suitable for pressure around 10 Kg/cm2 in the penstock as most of the
requirement is in the range of net pressure 3 to 5 Kg./cm2. Thus a higher
107
pressure in the penstock prevents the use beyond 10 Kg./cm2. For high
head installation, penstock tapping is not recommended.
- Normally no pumping is required. However, sometimes booster pumps
may be required/provided.
108
- Mulsifyre water requirement for one generator transformer for 40
minutes, plus
- Operation of one hydrant for 60 minutes
Provision of mulsifyre protection for oil filled transformers, water sprinkler
system for oil plant rooms, especially in underground power house & fire
hose cabinets/hydrants for power house indoor as well as transformer floor
shall be made.
Provision of 2 No. of fire pumps each capable of pumping water to meet the
water requirement of mulsifyre system of a generator transformer plus one
hydrant operation shall be made.
The following fire protection measures shall also be provided:
- Portable Fire extinguishers
- Foam Type
- Carbon dioxide Type
-To initiate alarm and give signal for operation for fire control in the affected
area, the following types of detectors are provided:-
- Smoke detectors.
- Heat detectors
- Fusible optical fiber linear heat sensing cable.
- Water based fire detections line with Quartzoid bulbs.
109
6.4.6Power House Lift
Minimum one lift is provided in the power house along with two sets of
staircase for the movement of passengers/goods. The lift can be designed as
goods lift or passenger lift. Generally 10-16 passenger lift is provided in the
power house. The factor of safety for any part of the lift should not be less
than 5.
110
- Isolation of circuit breakers for maintenance
- Isolation of Bus-faults
- All switching should preferably be performed with circuit breakers
- Techno-economics of each alternative considered
6.5.3Circuit Breakers
- Air blast circuit breaker or SF6 gas circuit breakers with standard
voltage and current ratings are generally preferred.
- For voltages below 245 KV, breakers with a common 3 pole operating
mechanism are adopted. System requirements may deem it necessary to
use single pole tripping and at voltages higher than 245 V to improve
system stability.
- Breakers with surge suppression resistors for limiting magnitude of
surges generated during breaker closing are preferred for voltage rating
of 400 kV and above, if system requirement so dictates.
111
protection of sub-station equipment, rotating machinery and other
applications where premium protection is required.
- Surge arrestors are located near the equipment being protected, as per
the requirement of insulation co-ordination studies.
6.5.6 Grounding
Switchyard grounding should be designed to conform to the requirements of
IEEE-80 –‘Guide for safety in substation grounding’.
112
CHAPTER 7: POWER POTENTIAL STUDIES-ROR SCHEME
The input data necessary for optimization study of a ROR plant are-
Reliable and faithful 10-daily river discharge for as many years as available
or at least for the past 10 to 15 years.
Full Reservoir Level (FRL)
Minimum Draw Down Level (MDDL) in case of dam
Tail Water rating curve,
Head Losses in Water Conductor System
Evaporation losses in case of storage plant
Downstream release commitments if any
Reservoir Elevation-Area-Capacity curve
Based on the above data, we work out the installed capacity of the plant. The
study is also known as power potential study through which the hydro power
generation and capacity of the project is estimated. Procedure for determining
the optimum Hydro power plant capacity depends on the type of Scheme
selected i.e., R-O-R scheme or storage scheme.
FOR PELTON:
H = MDDL+ 2/3(FRL -MDDL) - TCL - Head loss
FOR FRANCIS AND KAPLAN:
H = MDDL+ 2/3(FRL -MDDL) - TWL - Head loss
Rated Net Head
• Rated Net Head (Hrated)
Hrated = Hgross– Hloss
where
Hgross : Gross Head (In Meter)
Hloss : Head Loss (In Meter) at Hgross
113
3. Overall Efficiency
Overall Efficiency (η)
where
ηtur : Turbine Efficiency (in %)
ηgen : Generator Efficiency (in %)
114
9. Restricted Energy
( In a particular 10 Daily / Month )
Unrestricted Energy Ures (in MU)
Where
Pres : Restricted Power (in MW) in particular period (10 Daily/
Month)
D : No. of Days in corresponding period (10 Daily / Month)
Where
Ures: Restricted Energy (in MU) in one period (10 Daily /
Month)
11. Load Factor
(for a given installed capacity)
Load Factor LF (in %)
Where
∑ Ures : Total restricted energy in given year (in MU)
PInstalled : Installed Capacity (in MW)
115
CONCLUSION
Though we have achieved considerable heights in power technology but the apex
is still hazy. Power generation is full of unfathomable riddles and so we must keep
striving to decipher the unsolved mysteries as we have been doing in past. William
Burroughs has aptly said,” Man is an artifact designed for power”. He is not
designed to remain in his present biologic state any more than a tadpole is designed
to remain a tadpole”. Our ultimate aim should be attainment of knowledge and we
should be determined to cross any hurdle in the way.
Though there is controversy over the issue of heavy funding of power
generation all over the world and systems policies involved. But then the question
to those who make hue and cry would be: when we can spend millions of dollars in
just setting up our army why can’t we spend money on something which could
pave a new era of human development? There are innumerous reasons and
advantages for so much interest in exploring and knowing about power generation
that everything is very justified if seen from a positive point of view. There can be
a possibility of some flaws which can make humans extinct in future and a
possible attack of power drought though seems hypothetical can never be
neglected. We have developed new technologies to sense any coming havocs and
we are on way to construct nature proof and flawless power plants. There is always
possibility of countries cooperating with each other over power generation, So a
future lies in for us to go ahead and research more and more in this infinite
field .We have advanced substantially in field of generators with help of our
invaluable, and our prolonged determination to look for the perfection makes us
feel we will always continue the same.
116
117