Midterm (Compro)

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3

PROGRESS OF WORK MONITORING

JULY AUGUST
ITEM DESCRIPTION % OF WORK REMARK
18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 GENERAL EXPENSES
0.008081 0.008081 0.008081
Temporary Facilities 5,000.00 2.42% AS PER PLAN

0.001496 0.001496 0.001496 0.001496


Stacking and Layour of Structure 1,234.00 0.60% AS PER PLAN

0.014545 0.014545
Mobilization 6,000.00 2.91% AS PER PLAN

Demobilization 10,000.00 4.85% AS PER PLAN

0.009091 0.009091 0.009091 0.009091 0.009091 0.009091 0.009091 0.009091


Supervision 15,000.00 7.27% AS PER PLAN

2 EARTHWORKS
0.00303 0.00303 0.00303 0.00303 0.00303 0.00303 0.00303 0.00303 0.00303 0.00303 0.00303 0.00303
Excavation 7,500.00 3.64% AS PER PLAN

0.008081 0.008081 0.008081 0.008081 0.008081 0.008081


Backfilling 10,000.00 4.85% AS PER PLAN

0.002191 0.002191 0.002191


Embankment/Compaction 1,356.00 0.66% AS PER PLAN

3 CONCRETE WORKS
0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475
Concreting 17,634.00 8.55% AS PER PLAN

0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088
Rebar Works 3,590.00 1.74% AS PER PLAN

0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039
Form works 4,500.00 2.18% AS PER PLAN

Slab on Grade 12,350.00 5.99% AS PER PLAN

4 METAL WORKS
0.002769 0.002769 0.002769 0.002769 0.002769 0.002769 0.002769 0.002769
Steel Erecting and Framing 4,569.00 2.22% AS PER PLAN

5 MASONRY
0.00207 0.00207 0.00207 0.00207 0.00207 0.00207 0.00207 0.00207
CHB Laying 3,415.00 1.66% AS PER PLAN

0.005656 0.005656 0.005656


Plastering 1/2" thick 3,500.00 1.70% AS PER PLAN

6 DOORS AND WINDOWS

Louvered Door/Roll Up Door 4,500.00 2.18% AS PER PLAN

Flush Door 2,145.00 1.04% AS PER PLAN

PVC Door 3,659.00 1.77% AS PER PLAN

Cabinets 12,000.00 5.82% AS PER PLAN

7 FINISHES

Ceiling Works 15,000.00 7.27% AS PER PLAN

Painting Works 3,459.00 1.68% AS PER PLAN

Tile Works 13,000.00 6.30% AS PER PLAN

8 PLUMBING WORKS (SEWER LINE)


0.011636 0.011636 0.011636 0.011636 0.011636
Plumbing Roughing Ins 12,000.00 5.82% AS PER PLAN

0.048483
Plumbing Installation 10,000.00 4.85% AS PER PLAN

9 TINSMITRY

Roof Installation 2,345.00 1.14% AS PER PLAN

Wall Installation 5,500.00 2.67% AS PER PLAN

10 ELECTRICAL WORKS

Electrical Roughing Ins 9,000.00 4.36% AS PER PLAN

Electrical Installation 8,000.00 3.88% AS PER PLAN

TOTAL AMOUNT 206,256.00 100.00% Duration of Work 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45


18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul 28-Jul 29-Jul 30-Jul 31-Jul 1-Aug 2-Aug 3-Aug 4-Aug 5-Aug 6-Aug 7-Aug 8-Aug 9-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug
2% 3% 1% 1% 1% 0% 0% 1% 1% 1% 0% 2% 1% 1% 2% 1% 1% 0% 1% 0% 0% 1% 1% 1% 0% 1% 0% 1% 1% 2% 1% 0% 1% 1% 0% 3% 2% 1% 0% 1% 1% 2% 2% 0% 6%
Monitoring of Daily Progress (AS PER PLAN)
2% 5% 6% 7% 8% 9% 9% 10% 11% 12% 12% 14% 14% 16% 18% 19% 19% 19% 21% 21% 22% 23% 24% 25% 26% 27% 27% 28% 29% 31% 32% 32% 33% 34% 34% 37% 39% 40% 40% 41% 41% 43% 45% 46% 51%

PROGRESS OF WORK MONITORING

60%

50%

40%

S-Curved

30%

20%

10%

0%
0 5 10 15 20 25 30 35 40 45 50
GENERAL EXPENSES
Temporary Facilities 5,000.00

Stacking and Layour of Structure 1,234.00

Mobilization 6,000.00

Demobilization 10,000.00

15,000.00
Supervision
EARTHWORKS
7,500.00
Excavation
10,000.00
Backfilling
1,356.00
Embankment/Compaction
CONCRETE WORKS
17,634.00
Concreting
3,590.00
Rebar Works
4,500.00
Form works
12,350.00
Slab on Grade
METAL WORKS
4,569.00
Steel Erecting and Framing
MASONRY
3,415.00
CHB Laying
3,500.00
Plastering 1/2" thick
DOORS AND WINDOWS
4,500.00
Louvered Door/Roll Up Door
2,145.00
Flush Door
3,659.00
PVC Door
12,000.00
Cabinets
FINISHES
15,000.00
Ceiling Works
3,459.00
Painting Works
13,000.00
Tile Works
PLUMBING WORKS (SEWER LINE)
12,000.00
Plumbing Roughing Ins
10,000.00
Plumbing Installation
TINSMITRY
2,345.00
Roof Installation
5,500.00
Wall Installation
ELECTRICAL WORKS
9,000.00
Electrical Roughing Ins
8,000.00
Electrical Installation
TOTAL AMOUNT 206,256.00

You might also like