Professional Documents
Culture Documents
Midterm (Compro)
Midterm (Compro)
Midterm (Compro)
JULY AUGUST
ITEM DESCRIPTION % OF WORK REMARK
18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 GENERAL EXPENSES
0.008081 0.008081 0.008081
Temporary Facilities 5,000.00 2.42% AS PER PLAN
0.014545 0.014545
Mobilization 6,000.00 2.91% AS PER PLAN
2 EARTHWORKS
0.00303 0.00303 0.00303 0.00303 0.00303 0.00303 0.00303 0.00303 0.00303 0.00303 0.00303 0.00303
Excavation 7,500.00 3.64% AS PER PLAN
3 CONCRETE WORKS
0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475 0.00475
Concreting 17,634.00 8.55% AS PER PLAN
0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088 0.001088
Rebar Works 3,590.00 1.74% AS PER PLAN
0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039 0.001039
Form works 4,500.00 2.18% AS PER PLAN
4 METAL WORKS
0.002769 0.002769 0.002769 0.002769 0.002769 0.002769 0.002769 0.002769
Steel Erecting and Framing 4,569.00 2.22% AS PER PLAN
5 MASONRY
0.00207 0.00207 0.00207 0.00207 0.00207 0.00207 0.00207 0.00207
CHB Laying 3,415.00 1.66% AS PER PLAN
7 FINISHES
0.048483
Plumbing Installation 10,000.00 4.85% AS PER PLAN
9 TINSMITRY
10 ELECTRICAL WORKS
60%
50%
40%
S-Curved
30%
20%
10%
0%
0 5 10 15 20 25 30 35 40 45 50
GENERAL EXPENSES
Temporary Facilities 5,000.00
Mobilization 6,000.00
Demobilization 10,000.00
15,000.00
Supervision
EARTHWORKS
7,500.00
Excavation
10,000.00
Backfilling
1,356.00
Embankment/Compaction
CONCRETE WORKS
17,634.00
Concreting
3,590.00
Rebar Works
4,500.00
Form works
12,350.00
Slab on Grade
METAL WORKS
4,569.00
Steel Erecting and Framing
MASONRY
3,415.00
CHB Laying
3,500.00
Plastering 1/2" thick
DOORS AND WINDOWS
4,500.00
Louvered Door/Roll Up Door
2,145.00
Flush Door
3,659.00
PVC Door
12,000.00
Cabinets
FINISHES
15,000.00
Ceiling Works
3,459.00
Painting Works
13,000.00
Tile Works
PLUMBING WORKS (SEWER LINE)
12,000.00
Plumbing Roughing Ins
10,000.00
Plumbing Installation
TINSMITRY
2,345.00
Roof Installation
5,500.00
Wall Installation
ELECTRICAL WORKS
9,000.00
Electrical Roughing Ins
8,000.00
Electrical Installation
TOTAL AMOUNT 206,256.00