Download as pdf or txt
Download as pdf or txt
You are on page 1of 21

ASME_Ch68_p001-021.

qxd 7/28/08 4:33 PM Page 1

CHAPTER

68
DESIGN OF INDIAN
PRESSURIZED HEAVY WATER
REACTOR COMPONENTS
H.S. Kushwaha, K.K. Vaze, and K.B. Dixit
68.1 INTRODUCTION provided of the development and the use of leak-before-break
(LBB) criterion to eliminate the need for installation of pipe
The Nuclear Power Program in India at present is based mainly whip restraints. Results of experiments conducted to determine
on a series of Pressurized Heavy Water Reactors (PHWRs). load-carrying capacity of cracked pipes and the results of fatigue
Starting from Rajasthan Atomic Power Station, comprising of two crack growth rate tests in support of LBB criteria are discussed.
units of 200 MWe Canadian-designed PHWRs in 1973, the pro- As a further example of the research and development work con-
gram has come a long way with 15 PHWR units (which includes ducted in India related to nuclear power plant applications, the
two units of 540 MWe PHWRs) in operation and 3 units under development of a modified B2 stress index (used in NB-3600-
construction. Narora Atomic Power Station commissioned in type stress analyses) for pipe elbows and curved pipes and quan-
1991 marked major indigenization and standardization of PHWR tification of additional safety factors to account cyclic tearing in
designs. The current design plans include 700 MWe capacity LBB assessment are discussed.
units. The choice of PHWRs in the current stage of India’s
nuclear power program is based on long-term objectives to be
achieved in the available uranium resources and industrial infra- 68.2 INDIAN PHWR
structure. These reactors use natural uranium as fuel and heavy
water as moderator and coolant. The nuclear power stations in 68.2.1 Introduction to Indian PHWR [1]
India are generally planned as twin-unit modules, sharing com- The first PHWRs at Rajasthan Atomic Power Station #1 and 2
mon facilities such as service building, control building, turbine and Madras Atomic Power Station #1 and 2 were of Canadian
building, spent fuel storage bay, and so on. design (based on Douglas Point). When design work for the third
The Indian PHWR design has evolved through a series of PHWR station, Narora Atomic Power Station #1 and 2, was taken
improvements over the years in progressive projects. Such up in the early 1970s, major modifications were incorporated with
improvements have been driven by, among others, evolution in the objectives of upgrading the designs in line with the interna-
technology, feedback from experience in India and abroad, tionally evolving safety standards and to cater to the seismic load-
including lessons learnt from incidents and their precursors, ing. Narora Atomic Power Station design was the first opportunity
evolving regulatory requirements, and cost considerations. to apply India’s operating experience with PHWRs, including
Valuable experience gained in design, manufacture, construction, aspects such as ease of maintenance, in-service inspection (ISI)
operation, maintenance, and safety regulation has enabled contin- requirements, improved constructability, increased availability,
ual evolution, improvement, and refinement in the PHWR concept and standardization of the unit. In Narora Atomic Power Station,
in a progressive manner. some of the new designs were incorporated with the objective to
In Indian PHWRs, the design, fabrication, testing, and inspec- serve as stepping stones for the design of subsequent larger 540
tion of all mechanical components basically follow the require- MWe PHWR.
ments of appropriate sections of the ASME Boiler & Pressure Some of the significant design improvements made in Narora
Vessel Code (ASME B&PV Code). Atomic Power Station included adoption of an integral calandria
Other international codes used are (1) Canadian Code CAN/ (reactor vessel) and end shields assembly, two independent fast
CSA N285.4-05 and IAEA Safety Guide 50-SG-02 for ISI and acting reactor shutdown systems, a high-pressure Emergency
(2) French Code RCC-G for containment design. This chapter Core Cooling System, and a double containment with suppres-
first provides a general overview of the Indian PHWR design and sion pool.
its evolution. The design approach, material selection, and fabri- Subsequent to Narora Atomic Power Station, Kakrapar Atomic
cation practices are described for major components such as Power Station #1 and 2, Kaiga Atomic Power Station #1 and 2,
calandria, headers, steam generators, and piping. Details are and Rajasthan Atomic Power Station #3 and 4 saw further
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 2

2 • Chapter 68

TABLE 68.1 DESIGN FEATURES: IPHWR – 220 MWe [1]

Design data
A. General
(i) Rated output thermal 756 MWt
(ii) Rated output electrical 220 MWe
(iii) Fuel Natural UO2
(iv) Moderator and reflector Heavy water
(v) Coolant Heavy water
(vi) Type Horizontal pressure tube
B. Reactor
(i) Calandria shell Horizontal stepped cylinder
welded to extensions of end
shield
(ii) Calandria shell material SS-304L
1. Calandria shell 11. Main shell assembly
(iii) End shields Cylindrical box-type
2. Overpressure relief device(OPRD) 12. Tube sheet F/M side
structure integral with 3. Shutdown system #1 13. Tube sheet cal. side
calandria shell 4. Shut down system #1 14. Lattice tube
(iv) End shield material SS-304L 5. Moderator inlet 15. End-shield support plate
(v) Calandria tubes 6. Moderator outlet 16. End shield cooling inlet pipes
7. Vent pipe 17. End fitting assembly
(a) Quantity 306 8. Coolant channel assembly 18. Feeder pipes
(b) Material Zircaloy-2 9. End shield 19. Outer shell
(vi) Coolant tubes 10. End shield support structure 20. Support lug
assembly
(a) Quantity 306
(b) Material Zirconium–2.5% niobium FIG. 68.1 INTEGRAL ASSEMBLY OF CALANDRIA AND END
alloy SHIELD (CUT-AWAY VIEW OF REACTOR) [1]
C. Steam generators
(i) No. of steam generators 4
(ii) Type Vertical U-tube with The calandria is housed in a steel-lined vault filled with light
integral steam drum water that serves as shielding as well as provides cooling to the
(mushroom-shaped) calandria.
(iii) Material Incoloy-800 The Primary Heat Transport (PHT) system uses heavy water
(iv) Steam pressure 3.923 MPa under forced circulation in a figure-of-eight loop. Figures 68.2
(v) No. of tubes per SG 1834 and 68.3 show the schematic of the system.
(vi) Total steam flow 370 kg/s The main circuit of 220 MWe units has four branches on
to turbine each side.
For the latest 220 MWe units, PHT system is valveless.
(vii) Steam temperature 25 ⬚C Elimination of these valves along with general reduction in the
(viii) Maximum moisture 0.25% number of components has helped to decongest the layout in the
content pump room, facilitating better maintenance approachability, less
maintenance, and lesser manrem.
The primary heat transport system pressure control in 220
MWe units is based on the “feed and bleed” concept. During nor-
mal operation, the average pressure of both outlet headers is con-
improvements leading to standardizations in design and layout for trolled at a set pressure of 8.53 MPa to keep the system “solid,”
220 MWe PHWRs. Table 68.1 lists the design features of Indian that is, no bulk boiling is permitted. Operational transients such
standard 220 MWe PHWR. as turbine trip, load rejection, boiler feed pump trip, reactor
power setback, and so on cause “swell” or “shrinkage.” The feed
68.2.2 Description IPHWR or bleed control valves actuate to counter these swells/shrink-
The reactor consists of a low-pressure horizontal reactor vessel ages. Though the system is ‘solid’ there is some finite compress-
(calandria) containing heavy water moderator at near ambient ibility of the system, which keeps the pressure changes within a
pressure and temperature. The calandria (Fig. 68.1) is pierced by fairly narrow band. The feed is provided by two feed control
a large number (306 in 220 MWe and 392 in 540 MWe PHWR) of valves located on the discharge side of primary pressurizing
coolant tubes, which contain the fuel bundles, and through which pumps, which take suction from storage tank. Two bleed control
pressurized heavy water coolant circulates. The calandria houses valves are connected to reactor inlet header. The hot bleed is
all reactivity and reactor shutoff devices in the low-pressure, low- depressurized, cooled and returned back to storage tank via
temperature environment. purification system.
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 3

COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 3

FIG. 68.3 PERSPECTIVE VIEW OF STEAM GENERATOR


AND PHT SYSTEM [1]

load combinations pertaining to both limit state of serviceability


and limit state of strength is checked. The various limit states
FIG. 68.2 PHWR SIMPLIFIED FLOW DIAGRAM [1] specified in the French Code RCC-G [4] along with the support-
ing documents BPEL [5] and BAEL [6] are adopted for design-
ing the structural elements of the inner and outer containment
structures.
In 540 MWe PHWR, a pressurizer has been introduced for pri-
mary heat transport system pressure control, while feed and bleed
is retained for inventory control.
68.2.4 Regulatory Structure [7]
Current Indian PHWRs use a double containment principle. The Atomic Energy Regulatory Board (AERB) is the national author-
annular space between the primary and secondary containment ity to ensure safety of nuclear power plants (NPPs). AERB fulfills
envelopes is provided with a purging arrangement to maintain a its mission by stipulating and enforcing rules and regulations
negative pressure in the space. This arrangement significantly concerned with nuclear and radiological safety. AERB has devel-
reduces the ground-level releases to the environment during acci- oped safety documents that lay down requirements for meeting
dents involving radioactivity release into the primary containment. safety criteria for activities related to nuclear energy and provide
Figure 68.4 shows the schematic of containment. guidance on methods for fulfilling the requirements.
The containment structures are made of concrete. The primary Safety documents published by the International Atomic
containment is a prestressed concrete structure, consisting of a Energy Agency (IAEA) and regulatory bodies of other countries
perimeter wall topped by a prestressed concrete dome. The outer are appropriately used as reference material for the purpose.
or secondary containment is a reinforced concrete cylindrical wall Safety Codes establish objectives and set minimum require-
topped by a reinforced concrete dome. The primary containment ments that have to be fulfilled to provide adequate assurance for
uses epoxy coating as liner on the inner surface for enhanced safety in nuclear and radiation facilities. Safety Guides provide
leak-tightness and ease while decontamination. Because of the guidelines and indicate methods for implementing specific
use of double containment, incorporation of a steel liner is not requirements as prescribed in the codes.
considered necessary. As on date, AERB has published 5 Safety Codes and 45 Safety
Guides concerning various aspects of NPPs and 51 other safety
support documents. Several other documents are under various
68.2.3 Design Codes stages of preparation. All these safety documents are being exten-
The design, fabrication, testing and inspection of all mechanical sively utilized in developing designs, operating procedures and in
components are as per the appropriate sections of ASME ASME regulation activities including safety reviews by AERB. A short
B&PV Code [2, 3]. list of documents related to NPPs is given in Table 68.2.
The design philosophy of the containment structure is based For design of mechanical components such as vessels, pumps,
on limit state concept where the response of the structure under and piping, use of appropriate ASME Codes is permitted.
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 4

4 • Chapter 68

FIG. 68.4 CONTAINMENT BUILDING [1]

68.3 DESIGN OF INDIAN PRESSURIZED of the end shields in this condition is assessed in detail; from the
HEAVY WATER REACTOR second unit of Madras Atomic Power Station onward, the end-
COMPONENTS shield material has been changed to SS-304L, which is resistant to
radiation embrittlement due to fast neutrons.
68.3.1 Calandria End Shield Assembly In the current design (Narora Atomic Power Station onward)
The calandria end shield assembly consists of calandria vessel (Fig. 68.1), the calandria and two end shields constitute an integral
with main shell and small shell connected by an annular plate. assembly, supported from the reactor vault walls, unlike earlier
The vessel houses 306 coolant tubes, reactivity mechanisms, and designs wherein the calandria and end shields were separately sus-
shutdown assemblies. At the two ends, the calandria vessel is con- pended by support rods. This design allows common tube sheet
nected with end shields. The end shields limit the radiation dose between calandria and end shield. It also simplifies alignment
in the fuelling machine vaults adjoining the calandria vault. They requirement between calandria tubes and end-shield lattice tubes,
also support and locate the calandria tubes and primary coolant and is more suited to conditions at seismic site.
channel assemblies in which the fuel resides. In the original
design of end shield (Rajasthan Atomic Power Station #1 and 2
and Madras Atomic Power Station #1), the end-shield material of 68.3.2 Main PHT System Components
construction was 3.5% Ni-steel. However, it was found that nil The main PHT system consists of steam generators, primary
ductility transition temperature (NDTT) crossed the operating circulating pumps, pressurizer (for 540 MWe PHWR), headers,
temperature within a short period of operation. While the stability feeders, and interconnecting piping.
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 5

COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 5

TABLE 68.2 PARTIAL LIST OF REGULATORY DOCU- reduction in manufacturing time and lower D2O side pressure
MENTS RELATED TO NUCLEAR POWER PLANTS [7] drop. The shell of SG is provided with a manway. Secondary side
of the tube sheet is provided with suitable holes to blow off and
S. No. Title of Safety Document remove concentration of impurity in the secondary side water.
Both primary and secondary sides of the steam generators are
1. Code of practice on quality assurance for safety in
designed and manufactured to the requirements of the ASME
nuclear power plants
B&PV
2. Code of practice on design for safety in pressurized Code Section III, Subsection NB, Class-1 components.
heavy water reactor-based nuclear power plants
3. Code of practice on safety in nuclear power plant operation 68.3.2.2 Primary Coolant Pumps The primary coolant pumps
(PCP) are vertical, single stage, single suction, double discharge,
4. Code of practice on safety in nuclear power plant siting
centrifugal pumps. Each pump is driven by a vertically, totally
5. Code of regulation of nuclear and radiation facilities enclosed, air and water cooled, squirrel cage induction motor.
6. Safety classification and seismic categorization of A spacer type rigid coupling connects the pump shaft to the
Structures, Systems, and Components (SSCs) motor shaft. Each motor is supplied with a single piece flywheel
so that the total rotational energy of pump motor unit prolongs the
7. Design basis events for pressurized heavy water reactors operation of the pump after loss of motor power and the rate of
8. Primary heat transport system flow approximately matches the power run down following a
9. Loss of coolant accident analysis for pressurized reactor trip.
heavy water reactors The pump has capability to operate without external injection
(gland coolant external injection) but with process water available
10. Safety guide for quality assurance in the design of from high pressure cooler. During hot standby condition when the
nuclear power plants pumps are unavailable, high pressure coolers which are located at
11. Safety guide for seismic studies and design basis an elevation higher than the seal location provide necessary ther-
ground motion for nuclear power plant sites mosyphon flow to ensure that temperature in seal areas do not
increase.
12. Civil engineering structures important to safety of
The pump casing design is in accordance with the requirements
nuclear facilities
for class-1 components of ASME B&PV Code Section III.
13. Design of concrete structures important to safety of Primary circulating pump motor unit is a vertical assembly, with
nuclear facilities dead weight being supported at two locations; 80% on two spring
14. Design, fabrication, and erection of steel structures hangers located on boiler room floor and 20% on pump room
important to safety of nuclear facilities floor through straight pipe piece attached to suction elbow. To
reduce stresses in heavy water pipes under operating conditions,
15. Design, fabrication, and erection of embedded parts and
sliding support has been provided at the bottom of pump suction
penetrations important to safety of nuclear facilities
elbow. To mitigate large displacements of pump motor unit under
earthquake, two horizontal snubbers each of 100 Te safe shut-
down earthquake (SSE) rating have been provided at pump motor
C.G. location in two mutually perpendicular directions. The pump
68.3.2.1 Steam Generator The steam generator (SG) design is bottom support is designed to resist vertical loads during the
of mushroom type. This design has the advantage of a single inte- earthquake.
gral unit with provisions of manholes on primary head to enable
in-service inspection of the tubes. Four identical steam generators 68.3.2.3 Pressurizer In 500 MWe PHWRs pressurizer is incor-
transfer heat from the heavy water reactor coolant on the primary porated into the PHT main circuit to reduce onerous demand on feed
side to the ordinary feedwater on the secondary side. The steam and bleed system to control inventory and pressure of the system. In
generators consist of an integral inverted vertical U-tube bundle in these reactors, feed and bleed system mainly acts as inventory con-
shell. Moisture separators and driers are housed in the upper end trol system and backup for pressure control when pressurizer is not
of the shell. available. Pressurizer is connected to Reactor Outlet Header (ROH)
The primary side of the steam generator consists of primary of each loop through one common isolation valve and two isolating
head, the primary side of the tube sheet and the primary side of valves, one for each loop. The flow path is from ROH to steam gen-
the tube bundle. A partition plate separates the inlet half of the erator to Primary Circulating Pump and then to Reactor Inlet Header
primary head from the outlet half. The U-tubes are welded to the (RIH). Pressurizer is located in the pump room.
primary side of the cladded carbon steel tube sheet and rolled into The heat transport medium is kept in a pressurized liquid state
the tube sheet. The steam generator primary shell and head are by a pressurizer (surge tank) backed up by control valves, which
made of low alloy steel. feed or bleed heavy water from the system including pressurizer.
The secondary side of the steam generators consists of the Pressurizers are fabricated and machined from carbon steel
shell, moisture separators and driers, the tube bundle shroud, the forgings with nonintegral nozzles for piping connections. The
secondary side of the tube sheet, the secondary side of the tube forgings of the vessel conform to SA 508 Cl.3 and in-house speci-
bundle, and tube support egg-crate grids. Low alloy carbon steel fication, and are made from vacuum degassed, Electro Slag
is the principal material of construction. Remelted (ESR), killed fine grained steel. The forgings are deliv-
The SG tubes are of 19-mm outer diameter (OD) and incoloy- ered in normalized heat-treated and fully machined condition. The
800 material. The 19-mm tubes, when compared to 16-mm tubes in-house specification imposes special requirements on chemical
of 220 MWe PHWR SG, offer advantages in ease of fabrication, composition and notch toughness for these forgings. Pressurizer is
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 6

6 • Chapter 68

in accordance with the requirements for Class-1 components of Subsection NB requirements. SA 333 Gr.6 seamless carbon
ASME B&PV Code Section III, Subsection NB. steel pipes are intended even for the low-temperature application
and have been preferred over SA 106 Gr. B piping used in
68.3.2.4 Headers In 540-MWe reactor there are four outlet NAPP and earlier reactors because of inherent fracture tough-
headers, two in each loop of PHT main circuit. Each outlet header ness property.
receives flow from 98 outlet feeders and directs the flow to the In all standardized 220-MWe and 540-MWe PHWRs, the three
steam generator via two inlet pipes. There are also four inlet head- important segments of PHT piping are running from ROH to SG
ers, two in each loop of PHT main circuit. Each inlet header inlet nozzle; SG outlet nozzle to suction nozzle of PCP, and from
receives flow from the primary coolant pump and distributes the discharge nozzle of PCP to RIH. The dead weight of outlet head-
flow to 98 inlet feeders. er, feeders, and heavy water SG inlet pipes would cause undue
Headers in 540-MWe PHWR are machined from single-piece large moments on SG inlet nozzle because of offset between SG
carbon steel forgings with integral nozzles for feeders and other and outlet header along N-S axis. To reduce these moments,
piping connections, and the ends are closed by ellipsoidal caps. sliding guide supports resisting vertical loads have been incorpo-
The single-piece forgings are made from the material conforming rated in heavy water pipes connecting outlet header to SG inlet
to SA 350 LF2 and in house specification. Also, these are made nozzles.
from vacuum degassed, Bohler Electro Slag hot topping process
(BEST) killed fine grained steel forgings and are delivered in nor- 68.3.4.1 Design Philosophy All the components of main PHT
malized heat-treated and fully machined condition. The in-house system are categorized as Class I components and hence have been
specification imposes special requirements on chemical composi- designed in accordance with ASME Section III, Division I NB.
tion and notch toughness for these forgings. Reactor headers are Detailed design by analysis approach has been adopted for all
designed to meet the requirements for Class-1 components of Class I components. All the components have been designed for
ASME B&PV Code Section III, Subsection NB. six sets of conditions. These six service levels and the loads con-
In principle the reactor outlet headers are floating assemblies sidered for each of them are summarized below:
and govern the design/behavior of the rest of the circuit. Each out-
let header is mainly suspended through two steam generator inlet Design Conditions Internal pressure ⫹ Dead weight (cold
(SGI) lines connected to SG’s inlet nozzle and resting on sliding flooded)
guide supports. Each of the reactor inlet headers is suspended Level ‘A’ Service Loadings (Normal Operation) Internal
through two pump discharge lines (PDL) connected to discharge pressure ⫹ Thermal loads ⫹ Operating cycles.
nozzles of main circulating pump. Level ‘B’ Service Loadings (Up-set Condition) Internal pres-
To reduce large displacement due to inertial loading under sure ⫹ Thermal loads ⫹ operation basis earthquake (OBE)
earthquake, two snubbers each of 200 KN capacities have been (inertial) ⫹ OBE (Seismic anchor movement) loads ⫹ oper-
provided at each outlet header. ating cycles. Operation basis earthquake inertial and OBE
seismic anchor movement loads have been combined on
68.3.3 Feeders absolute sum basis.
There are 784 feeders in all, 392 at each end of the reactor, in Level ‘C’ Service Loadings (Emergency Condition) Internal
540-MWe PHWR. The 392 feeders at each end of the reactor run pressure ⫹ Dead weight
from the fuel channels vertically up the face of the reactor and Level ‘D’ Service Loadings (Faulted Condition) Internal
thereafter horizontally across and above the fuelling machine area pressure ⫹ Dead weight ⫹ SSE Inertial load.
to the reactor headers. Test Conditions Test pressure ⫹ Dead weight
In order to achieve uniform outlet temperature, the feeders
range in four sizes, namely, 80-mm Nominal Bore (NB), 65- mm 68.3.5 Coolant Channel Assembly
NB, 50-mm NB, and 40-mm NB. These are inside diameter (ID)- Coolant channel assemblies house the fuel bundles and contain
controlled pipes. the hot pressurized heavy water coolant flowing through them.
The feeders are of seamless carbon steel pipes conforming to Each coolant channel assembly consists of a Zr-2.5% Nb coolant
SA 333 Gr.6 material and in accordance with the requirements for tube, two martensitic stainless steel end fittings–one each at either
Class-1 components of the ASME B&PV Code Section III, end, and associated hardware. The coolant tube is rolled to end
Subsection NB. fittings at both ends. Each coolant tube is thermally isolated from
The feeder pipes are arranged in banks, with a maximum of 10 cold heavy water present in the calandria vessel by a seamless- or-
feeders in a bank. The feeders are connected to end fittings by seam-welded concentric Zircaloy-4 calandria tube, which is rolled
high-pressure pipe couplings at lower end and are welded to into the tube sheet of the end shield assembly at both ends.
header stubs at upper end. On the basis of analytical studies car- Calandria tube envelops coolant tube forming an annulus space
ried out on feeders, it is observed that maximum stress occurs, in between the two tubes. Calandria tubes are manufactured out of
general, either at elbow after the coupling or at the pipe bend Zircaloy-4 material either by seamless route involving hot extru-
location near header end. Thus, to take care of higher seismic sion and cold pilgering or by seam welding cylindrically formed
load, the elbows at these ends have been strengthened by increas- tubes from strips. Both types of tubes would meet the specified
ing the wall thickness. longitudinal and transverse mechanical properties such as ulti-
mate tensile strength (UTS), yield strength (YS), and elongation
68.3.4 Piping percentage. Calandria tubes are vacuum annealed to minimize
All of the piping in the main primary heat transport system is residual stresses.
of seamless carbon steel, ASME SA 333 Gr. 6, and designed and Coolant tubes that are the most important structural components
fabricated in accordance with ASME B&PV Code Section III, in the reactor core are manufactured from Zr-2.5% Nb alloy.
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 7

COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 7

Coolant tube is attached at either end to a stainless steel (type AISI- Coolant tube outlet pressure 115.82 Kg/cm2
403 modified) end fitting by a roll-expanded joint. These joints are Coolant tube outlet temperature 304 ⬚C
of zero-clearance type and this feature helps in controlling the
residual stresses in the joint region to a low level, providing neces- Since the pressure and temperature vary along the length of the
sary safeguard from delayed hydride cracking of coolant tube. coolant tube, the design condition is established by evaluating
Coolant tubes are seamless tubes produced by hot extrusion stresses at several locations along the length to determine which
and cold pilgering followed by stress relieving (autoclaving) in a location requires the largest wall thickness. Minimum required
steam atmosphere. The ends of the coolant tubes require special coolant tube wall thickness calculated on this basis works out to
finishing operations to obtain stringent dimensional control neces- 4.3 mm, inclusive of corrosion and wear allowance of 0.2 mm,
sary for zero-clearance rolled joints. The inlet and outlet end of with critical section of the tube being the inlet end.
coolant tube is roll expanded to end fittings made of martensitic Coolant tubes are designed in accordance with the intent of
stainless steel (type 403 modified) solid forgings. End fitting is an ASME Section III, Subsection NB requirements. As per ASME
open-ended tubular body of approximately 164 mm outside diam- Code, design stress intensity for coolant tubes should be the
eter and 2516 mm length. It has an integral side opening (feeder lowest of
hub) to which the feeder pipe is attached. (a) 1/3 of the specified minimum UTS at room temperature,
Although zirconium alloys are not ASME Code approved mate- (b) 1/3 of UTS at temperature,
rials, attempts have been made to follow all the requirements of (c) 2/3 of the specified minimum YS at room temperature, and
the ASME Code for each component. Rolled joints are also not (d) 2/3 of YS at temperature.
covered by ASME Code. However, detailed development work
and evaluation have been carried out to qualify these joints for Of the above criteria, the governing quantity deciding coolant
reactor application and to establish that these joints satisfy all tube design stress is the 1/3 UTS at operating temperature.
design requirements. Neutron-irradiation-enhanced creep deformation is one of the
important factors deciding the life of coolant tube in PHWRs.
68.3.5.1 Calandria Tube The ends of calandria tubes are joined Based on the present level of understanding, the coolant tube
with calandria side tube sheet of end shield assembly by means of is estimated to undergo a diametric creep strain of the order
a special type of rolled joint called sandwich rolled joint. This joint of 3% and an axial elongation of 2.5% during the life of the
is developed for a thin tube and low-pressure conditions. If the reactor. The potential life limiting concerns due to creep are as
calandria tube is directly rolled into a plain or grooved tube sheet, follows:
the joint would not develop the required seating pressure and hence (a) Diametral expansion causing bypass of coolant flow around
the required leak tightness. Due to this limitation, a sandwich type the fuel bundles, and
of joint is adopted where calandria tube is squeezed (sandwiched) (b) Relative sag between coolant tube and calandria tube caus-
between an inner-landed sleeve insert of stainless steel Type 410 in ing possible contact.
a full annealed condition and the outer stainless steel tube sheet.
The ends of the calandria tubes are flared to a larger diameter to Corrosion and Hydriding. Zr-2.5% Nb alloy has good corro-
accommodate the landed sleeve insert and to provide design clear- sion resistance in high temperature water as long as oxygen con-
ances between the coolant and calandria tubes anywhere along tent is held extremely low. The predicted corrosion rate is expected
the channel axis. Joint configuration with PIWR (percentage insert to be about 0.1 mm over the operating life of the reactor. A corro-
wall reduction) of 6.5 – 7.5 is selected after development work. sion and wear allowance of 0.2 mm is provided on the coolant
Calandria tube rolled joints have a minimum pullout load of tube. Moreover, finished tubes are autoclaved in steam atmosphere
31 metric tons and a leak tightness of 3 ⫻ 10⫺6 cm3/s. at 400 ⬚C for 24 h to form a protective layer on the tube surface.
During normal operation, calandria tubes are subjected to a The presence of 1% oxygen in the circulating annulus gas moni-
temperature of 75 oC and maximum external pressure of 1.45 toring system helps in maintaining a constant oxide layer thickness
Kg/cm2, corresponding to the lowermost row of calandria tubes in at the tube OD.
the calandria vessel (hydrostatic head of 0.85 Kg/cm2 ⫹ modera- The more complex part of the corrosion reaction is the absorp-
tor helium cover gas pressure of 0.6 Kg/cm2) . In addition, calan- tion of hydrogen evolved in the oxidation reaction of heavy water
dria tube is subjected to (i) garter spring loads, (ii) Buoyancy with zirconium. Hydrogen is evolved in this reaction and a portion
force, (iii) direct pressure load on the tube sheets causing a tensile of this hydrogen is absorbed by the zirconium alloy; this phenome-
loading on all tubes, and iv) stresses due to differential thermal non is termed “hydrogen pickup” by the alloy. If the hydrogen
expansion of calandria tubes and calandria shell. concentration in the tube exceeds the solubility limit, then it pre-
Calandria Tube Collapse Pressure. The calandria tubes are cipitates as zirconium hydrides.
designed on the basis of neutron economy and collapse due to The solid solubility of hydrogen in zirconium alloys is very low
external pressure. The wall thickness is set at a minimum value, – below 150 ⬚C. Hence, more zirconium hydrides will be present
satisfying the requirement of stability against collapse pressure. at lower temperatures. Hydrogen when in solid solution in zirco-
The design also caters for postulated accident conditions where nium alloys can be driven in directions of thermal stress and con-
overpressure of the calandria vessel is assumed. Calandria tube centration gradients. Hydrogen in excess of solubility limits pre-
collapse pressure works out to be 2.85 Kg/cm2. cipitates as zirconium hydrides. As zirconium hydrides are brittle,
this can lead to failure of coolant tube by initiation and propaga-
tion of a crack in the radial axial plane due to phenomenon of
68.3.5.2 Coolant Tube The temperatures and pressures at the
delayed hydride cracking. Delayed hydride cracking is the
inlet and the outlet considered in design are as follows:
process of formation of hydrides and their cracking aided by the
Coolant tube inlet pressure 124.18 Kg/cm2 presence of tensile hoop stress (including residual stress) and
Coolant tube inlet temperature 260 ⬚C defects in the tube.
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 8

8 • Chapter 68

Following remedial measures have been implemented in the 68.4 DEVIATIONS FROM ASME CODE
design of a coolant tube against embrittlement effects and hydriding:
All the Indian PHWR components are, in general, designed, fab-
(1) Zero-clearance rolled joints, which will significantly ricated, commissioned, and tested as per the ASME Code require-
reduce the tensile residual stresses in the neighborhood of ments. However, there are some areas in PHWRs where deviation
rolled joint region. from the ASME Code requirements is unavoidable due to the basic
(2) Stringent Inspection and quality control, consisting of both, design of the reactor. Still, in such areas, the basic intent of the
angle beam and normal beam ultrasonic examinations as ASME Code is maintained. The following are such areas:
well as a supplementary eddy current examination.
(3) Control of impurities, such as hydrogen, chlorine, phos-
phorous, and carbon.
68.4.1 Calandria
(4) Autoclaving of coolant tube that produces hard adherent
68.4.1.1 Material of Calandria Tubes Material of calandria
oxide layer of about 1 ␮m thick on the tubes, which acts as
tubes is Zircaloy-2/ Zircaloy-4. This material has not been
a barrier for hydrogen ingress from annulus gas side.
approved by ASME Code Section III as Class I material. Since the
(5) Addition of oxygen in the annulus gas to avoid deteriora-
calandria tubes are present in reactor core, due to neutron econo-
tion of the oxide film.
my, choice of material for calandria tubes is restricted to
(6) Avoidance of cold pressurization to improve the flaw toler-
Zirconium alloys. ASME B&PVCode Section III has been devel-
ance at low system temperatures.
oped for PWRs and boiling water reactors (BWRs) designed and
Leak-Before-Break Methodology. Achieving leak before built in the United States. These reactors do not have calandria
break depends on the difference between the time available to tubes. For heavy water reactors, calandria tubes are inherently pre-
detect a leaking crack and time required to detect a leaking crack. sent, and thus this violation of code is unavoidable. However, the
The time available to detect a leak is estimated from design, manufacturing, and inspection follow Section III, Class I
philosophy.
Time available Ta (in hours) is given by
(C ⫺ 7W ) 68.4.1.2 Rolled Joints Between Calandria Tubes and
Ta ⫽ Calandria Side Tube Sheets This type of joint is not approved by
2V
ASME Code Section III for Class I components. The reason for
using this type of joint is that Zircaloy-2 cannot be easily welded
where C is the critical crack length (CCL), 7 W is the leakage size
to stainless steel. This violation of code also takes place due to
crack and V is the delayed hydrogen cracking velocity in the axial
presence of calandria tubes and thus is unavoidable. However, this
direction.
joint has been so developed that its pullout strength is at least equal
During service, CCL reduces and the DHC velocity increases
to tensile strength of calandria tube. Moreover, this joint is so
and the time available to detect a leaking crack decreases. If
designed that it is not falling on boundary of heavy water–light
hydrides are present and a defect does initiate DHC, then the time
water. Moreover, this joint has been experimentally proven satis-
available to detect the leak would be in the range of 11 – 12 h.
factory for strength and leak-tightness requirements.
Thus, a sensitive leak detection system called annulus gas moni-
toring system is implemented in the design that enables leak
68.4.1.3 Use of Rupture Disc for Overpressure Relief
detection and safe shutdown in less than 5 h.
Overpressure in calandria develops when rupture of a coolant
channel occurs in calandria vessel. During this condition, prima-
68.3.5.3 End Fittings End fittings are manufactured out of
ry coolant that operates at high temperature and high pressure
AISI-403 (modified) stainless steel. coolant tube and end fittings
gets liberated in moderator that operates at low temperature and
are connected by means of a rolled joint. To have a leak tight rolled
pressure. This results in pressurization of calandria vessel. Four
joint at all temperatures, end fittings need to have coefficient of
relief pipes having diameter of 500 mm are provided on calandria
thermal expansion as close as possible to that of the coolant tube.
vessel for relieving the pressure. The ends of these pipes are
End fittings also require comparable values of mechanical proper-
closed by rupture disc assemblies. In case of a coolant channel
ties such as hardness with respect to coolant tube and liner tube for
rupture in calandria, these rupture discs break open and over-
rolled joint integrity. AISI-403 (modified) material can be heat
pressures in calandria are restricted.The use of rupture discs as
treated to attain the required mechanical properties.
the primary pressure relief device is not allowed by ASME
Results of fast neutron irradiation damage on AISI 403 materi-
B&PVCode Section III, Subsection NB. As per this subsection,
al at 304 ⬚C show that there is a change of NDTT from 40 ⬚C to
the rupture disc may be used in conjunction with safety valves.
about 100 ⬚C during the life of the reactor. The presence of trace
However, for the accident condition described above, the flow
elements such as copper, vanadium, antimony, aluminium, and
rate required for the pressure relief is so large that use of safety
arsenic can increase the shift in NDTT. Hence, these trace ele-
valves is not adequate.
ments are controlled to the extent possible in the end-fitting
It may be mentioned here that the reactors that are mainly
material. Presence of trace elements such as copper, vanadium,
addressed by ASME Code are light water reactors (LWRs). In
antimony, aluminium, and arsenic are controlled to a maximum
these reactors, the functions of moderator and coolant are per-
of 1450 ppm out of which copper alone is controlled to a maxi-
formed by the same fluid. There are no coolant channels in these
mum of 600 ppm.
reactors, so that the type of accident that is being considered for
End-fitting material is specified with the following impact
PHWR calandria is not relevant for these reactors. Overpressures
properties:
in the reactor vessels of these reactors occur mainly due to system
Longitudinal: 2.8 Kg/min at 20 ⬚C transients, and these can be relieved using safety valves and thus
Transverse: 2.1 Kg/min at 66 ⬚C the use of rupture disc is not necessary in these reactors.
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 9

COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 9

Normal operating pressure of the helium cover gas that is at the (0.65 mm) minimum in a Cv test conducted at lowest service tem-
top of the calandria is low, that is, 0.3 kg/cm2(g). There is a relief perature (LST).
valve in the system, which opens when the system pressure rises A series of tests were conducted jointly by Nuclear Power
above 0.5 kg/cm2(g). This relief valve has a capacity of 2348 stan- Corporation (NPC) and Indira Gandhi Centre for Atomic
dard lpm, which is sufficient to take care of changes in volume of Research (IGCAR) to obtain data on this aspect of unirradiated
moderator due to swelling or other minor causes. The rupture disc end fitting material. From the results, it is clear that this material
set pressure is 1.4 kg/cm2(g), which is not close to the relief valve is capable of meeting this code requirement at temperatures above
setting. 60 ⬚C. Nil ductility transition temperature of this material in unir-
So, the OPRDs come into action only when there is an accident radiated condition corresponding to 15 ft. lb. absorbed energy in
involving coolant tube rupture. The size of opening is such that Cv test is 40 ⬚C. The shift in NDTT due to irradiation effect gets
one OPRD is sufficient to relieve the pressure in calandria in case saturated at a fluence of about 6.5E19 n/cm2. The maximum shift
of coolant tube rupture accident. For redundancy, four identical is about 55 ⬚C. Further, a test was conducted at low temperature
rupture discs have been provided for each calandria. to simulate radiation damage, in which an artificially produced
The sample rupture disks are tested in shop for burst pressure [electrical discharge machining (EDM)] notch defect in the high-
and cycle testing. The accepted range of burst pressure is 1.26–1.40 ly stressed rolled joint area was extended by fatigue and the end
kg/cm2(g). fitting was tested up to burst. The end fitting could withstand
nearly three times the design pressure.
68.4.2 End Shields Therefore, end-fitting material is safe for all conditions of reac-
tor operations, as it always operates at 265 ⬚C. However, as a pre-
68.4.2.1 Tri-Junction Welds The design of end shield meets all caution, hydro-test during manufacture and at precommissioning
requirements of ASME Code Section III, Class 2 in all respects stage is conducted at a minimum temperature of 65 ⬚C and also
except for inspection of joint among lattice tubes, baffle plates, and cold pressurization is prohibited in the reactor, where during start-
calandria side tube sheet. However, ultrasonic technique has been up, pressurization starts at a temperature of 130 ⬚C.
developed for this purpose. In addition to ultrasonic examination, Inspection of End Fittings. There are some areas of end fitting
dye penetrant (DP) examinations are carried out after each weld- (at the top of the nozzle and some portion of side) that are not
ing pass. Mock-up weld passes are carried out everyday before covered by bidirectional ultrasonic examination during manufac-
start of welding to ensure good quality. These mock-ups are sec- ture. At these places only straight beam technique is used.
tioned and inspected if found necessary.
68.4.4 Inaccessibility for In-Service Inspection
68.4.2.2 Monitoring of Intermetallic Joint (Diaphragm The reactor components such as end shields and calandria are
Plates) Diaphragm plates are provided in the calandria side tube not accessible to periodic ISI. However, during design and fabri-
sheet and the fuelling machine tube sheet. The diaphragm plates cation stage, all precautions are taken to see that no regular ISI is
have lower thickness compared to the tube sheets to provide the needed for this component. Stress analysis for all the components
flexibility required to allow thermal expansion of the calandria has been done as required by the code.
tubes. There are weld joints between the diaphragm plates and the
tube sheets. Total thermal neutron flux at this joint is 1.08 E11
n/cm2/s. This is not expected to cause embrittlement of the material
over a period of 30 FPY. Stress analysis shows that stress level in 68.5 SEISMIC QUALIFICATION,
this zone is very low. Quality control procedure assures no defect in LEAK-BEFORE-BREAK, ISI,
this joint (100% radiography in addition to root pass DP). Thus, no CONTAINMENT DESIGN
failure is expected during service. The water level in expansion tank
and makeup rate are monitored continuously. 68.5.1 Seismic Qualification
The various structures, systems, and components in NPP are
68.4.3 Coolant Channel Components classified into three categories [8]. Category I systems are those
Material of Coolant Tubes. Zirconium–Niobium alloy has not whose failure could lead to release of activity into containment or
been used as a material for the pressure-retaining components in in the environment (e.g., reactor containment structure, PHT sys-
LWRs. Here also, the intent of ASME Code is followed in the tem and so on) and are designed for S1 (equivalent to OBE)- and
design, manufacture, inspection, and testing of the tubes. S2 (equivalent to SSE)-level earthquakes [9]. Category II struc-
Rolled Joint Between Coolant Tubes and End Fittings. The tures (e.g., waste management building) are designed for S2-level
reasons for using rolled joint here are same as those for the joint earthquake and Category III structures (e.g., turbine building,
between calandria tube and the calandria tube sheet. turbo-generator and so on) are designed for earthquake resistance
Material of End Fitting. Material of end fittings is marten- as per national practice [10].
sitic stainless steel AISI 403 (modified), hardened and tempered. Due to the numerical difficulties associated with use of
The essential elements of modification are (i) controlled range of plate/shell elements for complex geometries, the present practice
C and Cr to achieve consistent mechanical properties with same is to carry out separate analysis for the entire reactor building
heat treatment parameters and (ii) low level of residuals to using 3D stick model, in which the inner containment (IC) is
reduce the shift in ductile to brittle transition temperature due to modeled using a separate 3D stick connected to the reactor build-
irradiation. ing raft. In this method, the structure is modeled using 3D beam
This material has been approved by ASME, vide Code Case properties based on strain energy equivalence between 3D finite
No. N-4-11 (approval date 13.7.81), as a pipe material, where the element model and 3D beam model. Lateral torsional coupling
toughness requirement as per NB-2332 applies. Accordingly, this and the effect of flexibility of floors, offset, and partial support of
material is required to exhibit a lateral expansion (LE) of 25 mils walls are accounted for. In this method, the beams are located at
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 10

10 • Chapter 68

OCW
ICW 10
1 9
1 4
2 24 8

Damping Ratio
6 VT
3 8 EW 7
5 6
10
7 5
12 NS 4
9 14 3
11 19 2
13 24 IS
1
18 28 17 0
LINK 44700 16 45
23 35 20 0 10 20 30 40
15 21 25 Frequency in Hz
27 40 26 29
11 34
34 30 CV FIG. 68.6 FREQUENCY DEPENDENT DAMPING VALUES
46 36 49
37 41 33 (ASME CODE CASE N 411-1)
39 71
56 50
42 48 38
45 30000
47 50 44
62 51
55 52 51 57 54
58
The floor-mounted equipment and piping are analyzed using
72 52 64 24000 60
61
67 66 63 74 floor response spectra. For this purpose, time history of the floor
59 70
71 78 58 81 82 motion is generated by performing a time history analysis of the
73
69 65
75 80
19000 76 RCB. The resulting spectra are broadened ⬰15% for use in equip-
77 58 83 86
88 79 57 ment design.
84 89 92
87 59 14250 For active equipment, such as electrical relays, switches, con-
94 85 60 95 101 tacts, shut-off rod drives and others, whose functioning solely
93 90 96
91 99 63 104 107 depends on the actuation of some parts within them, it is neces-
103 97
98 7500 81
102 100 64 105 110 sary to demonstrate their operability during an earthquake event
116
109 106 112 FLEXURAL CENTRE by testing on shake table. In addition, the equipment must with-
108 111 113
114 119 stand the effects of a number of OBEs prior to the SSE. The pro-
117 118 115 120 AREA CENTRE
cedures given in IEEE-344, 1987 for the assessment of integrity
23 44 121 69 126 000
122 NODES and operability are adopted for testing. For heavy equipment such
123 124 82
130
70
127 129 as primary heat transport pumps, it is acceptable to qualify by
RAFT 83 128 xxx ELEM detailed finite element analysis wherein the bearing stiffness, gap
131
between the casing and the impeller, and so on, must be consid-
FIG. 68.5 BEAM MODEL OF PHWR BUILDING ered in a mathematical model.

68.5.2 In-Service Inspection Philosophy


shear centers [11, 12] and the masses ate located at mass centers As an integral part of quality assurance during operation, a
with a rigid link joining the two (Fig. 68.5). Beam models are periodic program of in-service inspection has been instituted to
used for obtaining the global seismic responses. cover all critical items important to safety [17]. This program has
These are finally applied on the 3D finite element model for been formulated on the basis of guidelines given in IAEA Safety
evaluating the design stresses. The seismic analysis model was Guide 50-SG-02 entitled “In-service Inspection for Nuclear
supplemented by an axisymmetric model to evaluate the stresses Power Plants” [18] and the Canadian Code CAN/CSA N285.4-05
at the shell/dome interface. In the current design being carried out and 8-05 [19, 20].
for 700 MWe project, the seismic forces on the containment struc- In formulating this program, the following special characteris-
ture will be computed from a detailed 3D FE model developed tics of PHWRs have been taken into consideration:
using beam/shell/solid elements.
For aspects such as soil–structure interaction, decoupling crite- • Use of a large number of coolant channel assemblies (306 for
ria, and damping in concrete structures, guidelines of ASCE are 235 MWe unit and 392 for 500 MWe unit) in place of a reac-
followed. The application of the decoupling criteria has resulted tor pressure vessel and leading to a multicomponent primary
in a model of the reactor containment building, which includes cooling system.
beam elements representing calandria vault, calandria, and the • Use of a variety of material requiring different kinds of exam-
end shields. ination techniques.
The application of the decoupling criterion to the complex • Strict requirements in limiting leakage of primary coolant
structure such as containment structure is not straightforward. from the point of view of safety and economy.
Modifications have been suggested [13] that make the criteria applic- • On-power refueling, which reduces the frequency of outages.
able to the complex structure such as reactor containment structure.
This criterion is also not applicable for multiconnected equipment. Examples of the components and methods of examination nor-
A new criterion [14, 15] was developed that can be used for checking mally considered for the ISI program are listed in Table 68.3.
the decoupling requirement of multiconnected equipment. The inspection areas and degree of inspection required for each
For damping in piping, higher values such as the PVRC damp- system or component are determined by the inspection category,
ing [16], as shown in Fig. 68.6, are also used. which in turn is based on two factors: stress intensity (SI) ratio
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 11

COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 11

TABLE 68.3 COMPONENTS AND METHODS


Low Medium High
OF EXAMINATION [17]
Fatigue Fatigue Fatigue
Factor Factor Factor
Items to be Examined Methods

Stress Intensity Ratio, RS


High
Vessel and piping Visual, volumetric, and integrative
C1 B A Stress
Pump and valve. Intensity
– weld Visual, volumetric, and integrative Medium
– interior surface Visual and surface (if material is sub- C1 B B Stress
jected to stress corrosion or erosion) Intensity
Support Low
– weld Visual, surface, and volumetric C2 C1 C1 Stress
– others Visual Intensity

Rotating machinery Visual, surface, and volumetric 0 0.01 0.1 1.0

Mechanical couplings Fatigue Usage Factor


– bolt Visual, surface, volumetric, and
integrative FIG. 68.7 DETERMINATION OF INSPECTION CATEGORY [17]
– stud
– nut
All components procedures adopted are generally in conformance with ASME
– corrosion UT Thickness gauging Section V and XI Codes.
– erosion The results of the preservice inspection (PSI) of the compo-
nents prior to the start of operation of the plant establish the base
Heat exchangers/steam line data required for comparison during subsequent ISI. This
generator examination is carried out using the same methods and techniques
– shell Visual, surface, and volumetric and types of inspection instruments as those, which are planned to
– tube Volumetric be used for in-service inspection. In the case of many components
and systems, the inspection data collected during manufacture
Coolant tube PT–CT Gap, Garter spring location,
serve as baseline data. PSI is performed either
volumetric, dimensional, and
hydrogen pickup (a) after the hydrostatic pressure test but before start up of the
reactor; or
Feeder pipe Visual, feeder gap, volumetric, and
(b) before the hydrostatic pressure test provided that a confir-
thickness
matory examination is performed after the component
hydrostatic pressure test and the results indicate no signifi-
cant change.
In order to minimize the radiation exposure of inspection per-
(Rs) and fatigue usage factor. There are three levels of stress
sonnel and keeping in view the fact that a large number of compo-
intensity, namely, high (ⱖ2/3), medium, and low (ⱕ1/3).
nents used are identical, a sampling approach has been taken for
working out the inspection program. For identical welds of identi-
Calculated SI
cal components, the number of welds to be inspected may be
reduced to FA. The value FA is taken from Fig. 68.8.
SI Ratio (Rs) ⫽
The in-service inspection intervals are chosen such that any dete-
Allowable SI rioration occurring in systems and components is detected well
before any failure takes place. The first inspection is carried out
Similarly, there are three levels of fatigue usage factor, namely, commencing from the end of the first year to the end of the fifth year
low (ⱕ0.01), medium, and high (ⱖ0.1). Based on different after going into commercial operation with the examinations spread
combinations of stress intensity ratio and fatigue usage factor, as evenly as practicable over the period. The subsequent in-service
four levels of inspection categories A, B, C1, and C2 in the inspections are scheduled at intervals of 10 years (Table 68.4).
decreasing degree of examination requirements have been arrived Acceptance Standards for Visual, Surface, and Volumetric
at (Fig. 68.7). Examinations are Same as Those in ASME Code Section XI.
Inspection category A requires examination of all welded While the components of primary heat transport system do
points and adjacent base metal. Category B requires examination receive the inspection commensurate with their importance, the
of at least one-third of the inspection areas. For Category C1, no major challenges faced by the Indian PHWRs are (i) Life man-
examination is required if the metal is ductile and creep resistant agement of coolant channels, and (ii) thinning of feeders and sec-
and the effects of neutron irradiation are not significant. For cate- ondary side piping due to flow accelerated corrosion (FAC).
gory C2, no examination is required. The inspection methods are These challenges have been successfully met through ISI and
of non-destructive type such as visual, dye penetrant, ultrasonic, maintenance/replacement strategies. The coolant channels suffer
radiography, acoustic emission, and hydro and leak testing. The from degradation due to irradiation creep resulting in increase in
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 12

12 • Chapter 68

As far as replacement is concerned, India has successfully


100 completed en masse coolant channel replacement in four reactors
where Zircaloy-2 pressure tubes were used. Also, feeder replace-
Number of Identical
Components/Welds

ment has been successfully completed in three reactors.

10 68.5.3 Leak-Before-Break
Leak-before-break approach has been applied to primary heat
transport system piping of 500-MWe Indian PHWR as per
NUREG-CR-1061, Vol.3 [21], and IAEA TECDOC-710 [22].
Parallel to these analyses, a comprehensive Component Integrity
1 Test Program has been initiated to address some of the issues in
0 1 2 3 4 5 6 7
the fatigue and fracture analyses. These issues include the trans-
Number of Components to be inspected
ferability of the specimen fracture parameters to the component
level, the effect of cyclic/ dynamic load (that may occur during an
FIG. 68.8 INSPECTION SAMPLE FOR IDENTICAL COMPO- earthquake) on fracture properties, the effect of system compli-
NENTS/WELDS [17] ance on the load-bearing capacity of piping components and so
on. For in-depth understanding of these issues, 70 fatigue/fracture
tests have been conducted so far on full-scale piping components.
TABLE 68.4 INSPECTION SCHEDULE FOR PRESSURIZED
Apart from these, probabilistic methodology has also been used to
HEAVY WATER REACTOR
address the uncertainty associated with the input parameters used
in the LBB analysis. The present paper discusses the LBB qualifi-
Inspection period cation of PHT system piping of 500 MWe Indian PHWR and
indicated as Minimum addresses some of the issues not considered in LBB concepts by
calendar year of percentage of Maximum above standards.
plant service from examinations percentage of The LBB concept is basically demonstrated through fracture
Inspection commencement of required to be examinations mechanics analysis that there is negligible chance of catastrophic
Interval operation completed credited break of PHT pipes without giving prior indication of leakage. This
1st 0–2 16 34 involves detailed fracture mechanics studies of different piping
(5 years) 2–5 100 100 components such as straight pipe, elbow and branch tee. Leak-
before-break is ensured by demonstrating three levels of safety
2nd 5–8 16 34
assessment against sudden double-ended guillotine break (DEGB).
(10 years) 8–12 50 67
Level 1 is inherent in the design philosophy of ASME Code Section
12–15 100 100
III [2], which is normally followed in piping design. Ductile and
3rd 15–18 16 34 tough materials are widely used in nuclear power plant piping due
(10 years) 18–22 50 67 to their high resistance against nonductile rupture. The design is
22–25 100 100 done with a well-defined factor of safety of code- specified 95%
4th 25–28 16 34 exceedance probability on strength. It does not permit the presence
(10 years) 28–32 50 100 of any defect larger in size than allowed in ASME Code Section III
32–35 100 100 for girth welds. The demonstration of Level 2 safety consists of
postulating a surface crack mostly in the weld, which may go unde-
Note Plant life is assumed to be 40 years. tected during the nondestructive examination. It is then shown that
there is insignificant crack growth of this surface crack during the
entire life period of the reactor. In this crack growth study, one
should consider all the possible crack growth mechanisms such as
diameter and sag; deuterium pickup resulting from corrosion corrosion, erosion, fatigue, creep, flow-induced vibration, and so
reaction lead to loss of fracture toughness. The ISI program for on, whichever may be operative for the particular piping system.
coolant channels consists of the following: From the operating experience of various PHWRs, it has been
observed that under the controlled environment of PHT piping sys-
(a) Nondestructive examination for flaws including flaws in
tem, fatigue is the only crack growth mechanism which cannot be
the rolled joint region.
totally ruled out. Hence, one should perform the fatigue crack
(b) Channel CT–PT gap, wall thickness, axial elongation,
growth study of the postulated surface flaw in the PHT pipes. In the
channel sag, and so on.
Level 3 safety assessment, a through-wall crack is postulated at the
(c) Eddy-current detection for location of garter springs.
maximum stress location with the worst material properties. The
(d) Measurement of gap between coolant tube and calandria
size of the crack is chosen so as to ensure the predicted leakage is
tube.
detected by the leak monitoring devices. Finally, it is shown that
(e) Sliver sampling for measurement of hydrogen content.
this crack will withstand the maximum credible load that may act
BARC In-service inspection System (BARCIS) and sliver sam- during a safe shutdown earthquake.
pling scraping tools are some of the important tools developed for
ISI of coolant channels. 68.5.3.1 Fatigue Crack Growth Tests Fatigue crack growth
Flow accelerated corrosion has become another focused area tests [23] have been conducted on pipes till the crack depth has
following some recent incidents. Thickness measurement is regu- reached through-wall. During the tests, crack depth and number of
larly carried out at a large number of locations. cycles have been recorded. Maximum crack depth and number of
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 13

COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 13

cracked pipe under reversible cyclic loading conditions. The


experiments covers a wide range of pipe sizes (NPS: 6⬙, 8⬙, 12⬙,
16⬙), crack sizes (2␪: 60⬚, 90⬚, 120⬚), material (low carbon man-
ganese steel, stainless steel), crack location (base, weld), loading
mode (load controlled, displacement controlled), and loading para-
meters (load ratio, load amplitude, displacement increment etc.).
The cyclic test results have been compared with the corresponding
monotonic pipe fracture test results to quantify the damage (loss in
load-carrying capacity) due to cyclic loading as a function of num-
ber of load cycles, and a simplified master curve has been generat-
ed to include the cyclic tearing damage in LBB assessment. The
master curve is a plot of the cyclic load amplitude (given as per-
cent of maximum load recorded in corresponding monotonic frac-
ture test) versus number of load cycles to failure (Nf) as shown in
FIG. 68.9 MAXIMUM CRACK DEPTH VERSUS NUMBER Fig. 68.11. Few available results on similar tests (on 4⬙-pipe,
OF CYCLES FOR DIFFERENT INITIAL CRACK DEPTH AND STS410 Japanese carbon steel) from literature of Central Research
R ⴝ 0.5 [23] Institute of Electric Power Industry (CRIEPI), Japan [25] have also
been plotted in the master curve and are in good agreement with
the results of the present tests series. The curve is independent of
crack sizes as well as pipe sizes since all experiment data lie with-
406MM OD Pipe and pipe weld in a narrow scatter band.
20 PBSC16-1 This curve gives the load reduction factor as a function of num-
PBSC16-2
PBSC16-3 ber of load cycles and is applied on the monotonic critical load.
14 PBSC16-4 The curve suggests an additional safety factor “␤c” of 4/3 for SSE
PBSC16-5 loading and 3/2 for OBE loading over the monotonic critical load
PBSC16-6
for LLB assessment. For an OBE, the factor is relatively higher in
2C/a

12
view of its higher frequency of occurrence than a SSE.

8 68.5.3.3 Compliance Effect on Load Carrying Capacity of


Piping Components A phenomenon mitigating the effect
described in the preceding section is the role of system compliance.
4
It means the stiffening effect of the connected piping on the cracked
section is negligible. Moreover, in these analyses the LBB assess-
0.2 0.4 0.6 0.8 1.0 ment is based on the maximum load, irrespective of the location at
a/t which they are acting. However, in the real situation, the local com-
FIG. 68.10 VARIATION IN ASPECT RATIO WITH CRACK- pliance of the cracked section and the global residual compliance of
GROWTH FOR 324-MM OUTER DIAMETER PIPE [23] the piping system may have significant effect on the load-carrying
capacity of the cracked pipe. These compliance effects must be
included while evaluating the safety margins. This is due to the fact
that the load acting on the cracked section changes, during crack
cycles for given stress ratio (R) and initial crack depth in pipes growth, because of indeterminacy of the piping system. Thus, a
have been shown in Fig. 68.9. Maximum crack depth and number purely load-controlled condition, representing the case of a piping
of cycles calculated analytically have also been shown in Fig. 68.9 system with infinite compliance, changes into a mixed mode, that
and shows a good comparison. Figure 68.10 shows that crack is, partly load-controlled and partly displacement-controlled. As a
growth in depth direction is more rapid compared with circumfer- result the crack section sheds some of the load during the crack
ential direction and the limiting value of the aspect ratio is between growth, and this load is picked up by the connecting piping system.
2.5and 5. This is essential for verification of Level 2 LBB. The load redistribution may increase safety margin. For simplified
fracture mechanics calculation, an analytical expression is pro-
68.5.3.2 The Cyclic Loading Effect on Load-Carrying posed [26, 27] to evaluate actual moment at the cracked section in
Capacity of Piping Components Leak-before-break assessment a 3D piping system equation:
is based primarily on the monotonic fracture tearing instability.
The effect of cyclic loading has generally not been considered in
the fracture assessment of nuclear power plant piping. The pipe
fracture analysis used in present LBB considers the seismic load-

Mu 1␴
Lc
Leff冥
Mc ⫽
冤1␴ LL I 冥
ing as a one-time applied load of magnitude equal to peak load at c I
the postulated flaw location during the earthquake event. The
eff eff
assessment of pipe with flaw (or crack) is based on the monotonic
tearing instability or Net Section Collapse (NSC). There is no
explicit consideration of the cyclic damage or the number of Here Mu is the uncracked moment and Mc is the actual moment at
applied load cycles during earthquake event. the cracked section. Lc and Ieff are the length and effective
An experimental and analytical investigation [24] was carried moment of inertia of the equivalent piping element used to simu-
out by conducting tests on full-scale circumferential through- wall late crack. The Leff is the equivalent length of the pipe modeled
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 14

14 • Chapter 68

Basis of βc factor in Proposed LBB Design Criteria


95
QCSP-8-60-L3-CSB Load Controlled Cyclic Tearing Tests
QCSP-6-60-L2-SSB

C-4 (2θ=60) 90

Cyclic Tearing : Load Amplitude (Given as %


SA333 Gr.6 Carbon Steel

of Monotonic Experimental Fracture Load)


QCSP-8-60-L2-CSB
QCSP-6-60-L3-SSW Base Metal
QCSP-16-120-L1-CSB
C-1 (2θ=30°) SA333 Gr.6 Carbon Steel 85
Weld Metal
QCSP-8-60-L2-CSW QCSP-12-90-L6-CSB
QCSP-6-60-L1-SSB STS410 Japanese Carbon
QCSP-6-60-L3-SSW C-6 (2θ=60°)
Steel Base Metal 80
QCSP-8-60-L4-CSW QCSP-6-60-L4-SSB
QCSP-8-90-L6-CSB SS 304 L Stainless Steel
QCSP-8-60-L1-CSW C-2 (2θ=30°) Steel
βc = 0.75 QCSP-8-60-L5-CSB
75
C-6 (2θ=30°)

QCSB-8-60-L4-CSB
QCSP-6-60-L3-SSB
70
Safe LBB
Design 67
25 Tests were conducted on Straight
65
Pipes: 6 ″, 8 ″, 12 ″, & 16 ″ NB Pipes of
Carbon and Stainless Steel Material
60
0 20 50 80 100 120 140 160 180

FIG. 68.11 MASTER CURVE FOR CYCLIC TEARING ASSESSMENT [24]

with fixed-end conditions, which simulates piping system com- Load-Displacement Plot
pliance at the crack element. The I is moment of inertia of the 1
pipe. Crack initiation load
Actual tests were performed on reactor grade pipes to validate 0.8
theoretical studies regarding the effects of system compliance on System Test
fracture integrity. Seven fracture tests have been conducted in 0.6
P/Po

which system compliance was simulated by fixed ends and it was Component Test
0.4
varied in terms of L/R parameters. The main conclusions of this
experimental study can be summarized as follows: 0.2
Crack initiation load
• Fracture load of a piping system having even very large 0
crack size is very near the collapse load of an uncracked pip- 0 50 100 150 200 250
ing system (as shown in Fig. 68.12), thereby proving that Actuator Disp. (mm)
large plastic straining occur at uncracked ends before the
FIG. 68.12 COMPARISON OF COMPONENT AND SYSTEM
system collapse.
LOAD DISPLACEMENT BEHAVIOUR (PO REFERS TO LIMIT
• A large margin was observed between crack initiation load
LOAD OF UNCRACKED COMPONENT/SYSTEM)
and the maximum load that the piping system has sustained.
It is worth noting that in conventional fracture tests (infinite
compliance), crack initiation load is usually very near to the given in ASME Section XI [3] is used. Table 68.5 shows the vari-
maximum collapse load. ous transient events and the number of excursions of each event
postulated for the entire design life period of the reactor. It was
68.5.3.4 LBB ASSESSMENT of 500 MWe PHWR PIPING seen that the fatigue crack growth is very small (original crack
Fatigue Crack Growth Analysis of 500 MWe TAPP 3&4 depth of 25% increased to 27%) over the entire design life period
PHT Piping (Level 2). A part-through semi-elliptical circumfer- of the reactor.
ential flaw at the inside surface of pipe is postulated. The depth Fracture Assessment (Level 3). The fracture assessment of
of flaw is conservatively assumed to be 25% of wall thickness of PHT system pipes, with postulated through-wall circumferen-
pipe based on ASME Code Section III, Appendix G recommen- tial and axial flaws, was carried out using the concept of a
dation. The flaw aspect ratio is assumed to be six, which is repre- two-criteria failure assessment diagram (FAD) [28], which
sentative of typical flaw found in service. Cyclic loading due to describes the interaction between fracture and collapse and is
normal operating condition (Service Levels A and B) is consid- documented as the R-6 procedure. The results obtained have
ered to calculate the fatigue crack growth. Paris power law as been used to qualify leak-before-break criteria of PHT pipes.
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 15

COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 15

TABLE 68.5 VARIOUS TRANSIENT EVENTS POSTULATED The Section III of ASME B&PV Code allows for design by sim-
FOR ENTIRE DESIGN LIFE OF 500 MWe TAPP 3&4 plified analysis (NB-3600) using stress indices. The B2 index is used
for calculating the primary stress intensity due to bending load.
Sl. No. Event No. of cycles Using margin consistent definition, the ASME Code expression
⫺2
for B2 can easily deduced as 1.3␭ /3 from the lower bound in-
1 Operation basis 50 (5 events, each
plane limit moment expression for the elbow as 0.8␭0.6MLPipe given
earthquake causing 10 cycles)
by Spence and Findlay [31]. However, The ASME Code has typi-
2 Heat-up from cold 1000 cally defined B2 as two-third of C2 index. Thus, the stress index
shutdown to hot standby value of 1.3 for B2 in the ASME Code is equal to 2/3 of 1.95. The
3 Start-up from hot 3500 ASME Code C2 index is based on Dodge and Moore [32] investi-
standby to full power gations on the stress intensities in curved pipe under combinations
of in-plane, out-of-plane, and torsional moments. He found that a
4 Power maneuvering 15,000 C2 index of 1.95/(h2/3) would conservatively predict the maximum
at full power stress intensity for any resultant moment.
ASME B2 index is found to be in good agreement for extra
large bend-radius elbows. However it is very conservative for
standard elbows (rb /R ⫽ 2 and 3). Based on these investigations,
The R-6 method was also used to perform sensitivity analysis a new B2 index (Eq. 68.1) is proposed, which eliminates undesir-
for reserve margins with respect to different input parameters able conservatism in the present ASME B2 index equation and it
such as material properties, material test temperature, initial can be used for elbows of any bend radius. Figure 68.13 shows
crack length and so on. the conservatism of present B2 index equation as well as com-
The margins (FL ⫽ critical load/applied load) obtained for the pares the limit load equation with other literature equations as
different piping segments using R-6 method and accounting for Caladine [33], Touboul [34], Chattopadhyay [35], and Kim [36].
the cyclic loading effect, range from 1.7 to 3.4 against a minimum Similar equations are also proposed for opening bending, clos-
required value of √2. ing, and opening bending for elbow with circumferential through-
wall crack.
68.5.3.5 General Limit Load and B2 Stress Index Equation
for Pipe Bends under In-Plane Bending The limit load assess-
68.5.4 Containment Design
ment is essential to prevent the pipe or pipe bends to fail by
The containment design has evolved from single containment
excessive deformation or collapse. Currently available limit load
in Rajasthan Atomic Power Station to full double containment in
equations have a limited range of applicability and do not cover
all the current designs with the provision of openings in the dome
the wide range of bend geometries that are used in power plant
of reactor building for erection of steam generator. The design
piping. Ideally, the elbow limit load equation should approach
follows the guidelines of French Design Code RCC-G [4].
straight pipe limit load with increasing pipe bend radius. Keeping
this fact in mind, finite element analyses of around 65 elbows
having different geometric parameters were performed. The 68.5.4.1 Design Against Membrane Stresses The major loads
parameters considered were elbow bend radius (rb) to mean considered for the design of containment structure are dead load,
radius (R) ratio (2, 3, 6, 9, 12, and 18) and pipe radius (R) to prestress loads with appropriate losses, internal pressure on account-
thickness (t) ratio (5, 7.5, 10, 15, 20, and 30). postulated design basis accident scenario, temperature loads under
One quarter of elbow was modeled using three-dimensional 20 test, normal operating and design basis accident conditions, envi-
nodded brick elements and elastic perfectly and a plastic analysis ronmental loads, namely, seismic (both operating basis earthquake
was performed, which included the geometric nonlinearity. The and safe shutdown earthquake) and wind loads. Appropriate live
analyses have been carried out for both in-plane closing and open- loads under normal operating condition as well as during construc-
ing bending, and limit load for each case was determined using tion process are also considered while carrying out the design of
the twice elastic slope method. A relational study was performed containment structure.
to understand the dependence of limit load on the R /t, rb /R and The prestress loads that are imparted on the structure to counter
elbow characteristic h. The study addressed the weakening factor the tensile stresses generated during design basis accident condi-
(Wf ), that is, the normalized limit loads (ratio of limit load of tion vary both spatially as well as in time domain on account of
elbow to limit load of corresponding pipe). A simple expression short-term and long-term losses. The short-term losses are due to
for weakening factor (or limit load) is proposed [29] for “closing friction and wobble effect, anchorage draw-in, and elastic short-
bending,” which covers the entire domain of the parameters and ening of concrete structure due to stagewise stressing of cables
provides a good prediction of limit load for nonstandard elbows. during the process of prestressing. Shrinkage and creep of con-
A margin consistent definition [30] for B2 index defines it as the crete and relaxation (creep) of prestressing steel contribute toward
ratio of the pipe collapse load to the collapse load of correspond- the long-term losses of prestress loads.
ing elbow. Finite element analysis is carried out in order to evaluate the
membrane forces due to various types of loads for the inner con-
MLElbow ⫽ Wf MPipe
L ⫽ Wf (4R2 ␴o) tainment structure. Normally, the IC structure can be modeled
using thick shell elements, which can take care of the shear defor-
Limit moment of an equivalent pipe 1
B2 ⫽ ⫽ mation. In order to obtain the stresses in the discontinuity areas
Limit moment of the elbow Wf more accurately due to irregular geometry and also discrete
0.2 anchorage forces because of prestress cable, the IC ring beam is
⫽ 1⫹ (68.1) modeled using 8-noded 3D solid brick elements. The effect of the
h1.028⫹0.95rb /R
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 16

16 • Chapter 68

1.9

1.7 rb/R = 6
rb/R = 3 rb/R = 18
R/t = 5 R/t = 10 rb/R = 12
R/t = 20 R/t = 30
l = 0.6 l = 0.6
l = 0.6 l = 0.6
Collapse Load of Eqv. Pipe
Collapse Load of Elbow
1.5
rb/R = 9
R/t = 15
l = 0.6
1.3

1.1 Elastic Perfectly Plastic FEM Solution


Propsed Equation

0.9
Iso 'λ' Lines ASME B2-Index [1]
forλ = 0.6
Calladine [2]
Touble [3]
0.7
Chattopadhaya [4]
Y. J. Kim [5]
0.5
0 5 10 15 20
Elbow Bend Radius / Mean radius (rb/R )

FIG. 68.13 COMPARISON OF FEM AND PROPOSED EQUATION WITH THE


LITERATURE EQUATIONS [29]

duct openings and the reinforcing/prestressing steel is accounted loads under construction stage. Working stress method of design
for appropriately at the design stage. is adopted for this.
The design of the prestressed concrete inner containment struc- In order to control cracking of concrete, the radial stresses are
ture is checked both under limit state of serviceability as well as limited to 0.67 times the tensile strength of concrete. The allowable
under limit state of strength (also called as ultimate limit state) as radial tensile stress is further reduced in order to take into account
per the provisions of RCC-G. It is ensured that a membrane com- the effect of membrane compressive stress field. The radial tensile
pressive stress of at least 1 MPa is available under accident condi- stress generated due to all the phenomena are considered for lim-
tion. Presence of voids in the concrete section due to cable duct iting the concrete tensile stress except that due to the effect of
openings led to development of special computer programs for stress concentration, since the radial stress generated due to this
carrying out the design check under limit state of serviceability phenomenon is secondary in nature and is balanced by the adja-
and limit state of strength. cent compressive stress field.
The entire inner containment is checked against the require- The radial reinforcements in the IC dome are designed to carry
ment of limit state of strength. In general, the load factor for the the radial tensile force resulting from the curvature effect and
permanent loads is 1.35 and that for the variable loads 1.5. transition effect where the cable spacing is sufficiently large.
However, where the cable spacing is close, reinforcements are
68.5.4.2 Design Against Radial Stress in IC Dome The nor- provided to take care of the local tensile force due to stress con-
mal stress in the thickness direction, also called as radial stress, is centration effect also.
generated in the inner containment structure due to (i) Curvature A reduced value of permissible stress is considered while
effect, in which the curved prestressed cables embedded inside the designing the reinforcements to limit cracking in the concrete.
concrete exert pressure toward the center of curvature at the bot- The deflection and strains at certain locations in the IC are
tom of the cable sheath leading to development of radial stress, (ii) recorded during proof testing mainly to compare the deflection as
Transition effect, arising at locations where the shell thickness well as strains obtained from analytical study. The strain mea-
changes rapidly within a short distance, and (iii) Stress concentra- surements are also necessary to monitor the development of stress-
tion effect, in which the in-plane membrane compressive stresses es in the IC structure at different stages of prestressing during
in the IC dome also generate radial tensile stress around the cable construction.
duct openings. The strains are measured using vibrating wire strain gauges
Normally, the radial stresses in the prestressed concrete inner (VWSG) connected to automatic data-logger at locations covering
containment structure are maximum during the construction period the entire IC in order to capture both membrane as well as radial
since the prestress forces are maximum. With time, long-term stresses. Based on the recorded data the stresses developed in the
losses take place and thus, the residual prestress is reduced. In IC are compared with the specified allowable stress limits of the
view of this, the design against radial stress is carried out for the design code RCC-G.
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 17

COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 17

68.5.4.3 Equivalence Study with Respect to ASME Code structures design is by consultants such as M/s. STUP, Develop-
Section III, Division 2 As discussed in the preceding sections, ment Consultants Private Limited, Tata Consulting Engineers, and
the design of containment structures of Indian PHWRs has been others and quality assessment is done by NPCIL.
based on the methodology evolved considering the Indian con- NPCIL has developed a very high expertise in design of small-
struction practices. The design methodology is mainly based on and medium- sized PHWRs. It has its own R&D facilities where
the principles of the French Code RCC-G as the containment new and innovative designs are developed and tested. Besides this,
system adopted for the Indian PHWRs is a double containment NPCIL gets support from its sister concerns such as Bhabha
without metallic liner, similar to the one adopted in the French Atomic Research Centre (BARC), Indira Gandhi Centre for Atomic
containments of PWRs. However, an attempt has been made to Research (IGCAR), and Raja Ramanna Centre for Advanced
study the equivalence of the various provisions of design of pri- Technology (RRCAT) in the field of research and development. It
mary (inner) containment structure being followed in India with has a strong team of design engineers who look after all the design
respect to those adopted in various international standards in aspects starting from conceptual design to detailed structural design
order to assess the level of its safety under design basis accident and analysis, process design, and electrical, civil, and instrumenta-
scenario. The study has been carried out to establish the equiva- tion design of NPPs. International codes such as ASME, IEEE,
lent partial safety factor for accident pressure (Pa) in factored RCC, and others are followed for design of nuclear power plants.
load combination under limit state of strength. For this purpose, Further, safety codes and guides issued by IAEA, USNRC, and
a detailed design check has been carried out for some typical ele- AERB are also followed.
ments located in different regions of inner containment structure, Design of fast breeder reactors (FBRs) is done by IGCAR.
such as (i) IC dome thickened area near SG opening, (ii) IC dome They have all the facilities for design, analysis and R&D of FBRs.
general area, (iii) IC wall raft junction, (iv) IC wall general area, FBRs are totally looked after by IGCAR with the help of other
and (v) IC dome springing area under accidental load combina- sister organizations such as BARC, NPCIL, RRCAT and others.
tion as per the provisions of various international standards, One fast breeder test reactor is under operation. One Prototype
namely, Canadian Standard,ASME Section III, Division 2 and Fast Breeder Reactor of 500 MWe capacity is under construction
RCC-G. by Bhartiya Vidyut Nigam (BHAVINI).
Based on the equivalence study, the following conclusions are Design and development of thorium-based reactors, including
drawn: all the engineering, analysis, and related R&D activities, is done
by BARC. A 300-MWe Advanced Heavy Water Reactor (AHWR)
(i) Though the design philosophy and partial safety factors for is being designed by BARC.
material and loads, prestress loss computation, and others
are different in various international standards (such as 68.6.2 Fabrication
Canadian, ASME and RCC-G), the design provisions and India is one of the few countries in the world that has acquired
the associated design parameters suggested by various expertise in the entire range of nuclear fuel cycle activities. As
international codes pertaining to design of containment these activities are of special nature and did not form a part of
structure are laid down in such a balanced way that the the general industrial domain of the country, Department of
final design lies in the same range. Atomic Energy (DAE) established facilities for carrying them out
(ii) In general, it is noticed that the load combination involving in a proper phased manner. Over the years, significant efforts
accident pressure along with the design philosophy sug- were put by DAE/NPCIL to develop indigenous manufacturing
gested in RCC-G is equivalent to the design provisions capability to fabricate various equipment/components conform-
adopted in the Canadian standard as well as the ASME ing to stringent quality standard of nuclear power plants.
Code. Indigenous industrial infrastructure for nuclear power plants is
well developed. Indian industry has gained valuable experience
and reached a stage of maturity in manufacturing components for
68.6 ORGANIZATION OF DESIGN, these reactors. Indian industries are fully capable of manufactur-
FABRICATION, CONSTRUCTION, ing all the components, including large-size components such as
OPERATION, AND ISI OF NPPS calandria, end shields, steam generators, turbine, condenser, and
IN INDIA others. These Indian industries have developed capabilities to
manufacture all the nuclear as well as secondary side compo-
68.6.1 Design nents. All the Class I, II, and III nuclear components are fabricat-
India started its nuclear power program with two BWRs, which ed, inspected, and tested as per applicable ASME Codes. Raw
were constructed on turnkey basis by General Electric, USA materials are procured to meet the ASME specifications.
in 1969. Later on, India had collaboration with Canada for two Inspection is done by the Quality Assurance Group of these
220 MWe PHWRs. First PHWR was designed and constructed by industries. NPCIL has its own QA group, which does the surveil-
Canadians. However, during the construction of second reactor, lance job at the shops of manufacturers. Expertise for carrying
the collaboration ended and India took over the remaining con- out all the nondestructive examinations has been developed by
struction work. Subsequent to the end of collaboration with NPCIL as well as the manufacturers.
Canada, India has built 11 ⫻ 220 MWe PHWRs and 2 ⫻ 540
MWe PHWRs. Three more 220 MWe PHWRs are in the final 68.6.3 Construction
stages of completion. Design, construction and operation of Over the years, India has developed expertise in the construc-
all these reactors are totally done in India. All the PHWRs tion of nuclear power plants. At present India is constructing
are being designed, constructed, and operated by Nuclear nuclear power plants in less than five years. Advanced project
Power Corporation of India Limited (NPCIL), a Government of management techniques are being followed to cut down the
India Enterprise, under the Department of Atomic Energy. Civil gestation period. Further, the following improvements have been
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 18

18 • Chapter 68

made in the construction methodology to cut down the gestation Indian PHWRs have very high availability factor over the entire
period. lifetime. This is made possible by strict scheduled outage for main-
tenance and in-service inspections. Biennial shutdown is taken only
• Concept of mega packages has been introduced for 18– 20 days. All the in-service inspections, containment testing,
• Vendor’s participation in analysis and decision making has and so on are done within this time. Unscheduled outages have
been increased. totally reduced and downtime is very much controlled. On redun-
• Integrated action plans are evolved to resolve issues related to dant systems, preventive maintenance is performed on power.
design, material, and construction activities. Radiological protection is enhanced by choosing cobalt-free materi-
• Targets and expectations are fully defined. als, providing adequate shielding thickness, and by optimized
• Open top construction, increased mechanization, and parallel design and layout of components and systems.
civil and mechanical erection are implemented. A comprehensive radiological surveillance program around
• Round the clock construction work is practiced. each NPP is pursued by well-equipped environmental survey lab-
• Use of project management tools, increased use of informa- oratories (ESLs). The basic objective of these laboratories is to
tion technology for prompt decision making and timely mid- assess the radiation doses to the public due to operation of NPPs
course corrections and revision of construction sequence have and to demonstrate the compliance with the applicable regulatory
been successfully implemented. limits set by national and international authorities.
The environmental survey laboratories at site periodically col-
There are a large number of civil construction companies in lect and analyze various environmental matrices, including
India, which take care of full construction of civil structures. dietary items such as water, cereals, pulses, meat, fish, milk, eggs
Prominent among them are M/s. Engineering Construction and and others for their radioactivity contents. Environmental sam-
Contracts (ECC), M/s. Gammon India Ltd., M/s Hindustan ples are collected on regular basis from various locations sur-
Construction Co., and others. In the early reactors, mechanical rounding the nuclear facility up to a distance of 30 km. The sam-
erection was done by NPCIL. But now there are many companies pling locations are selected on the basis of wind pattern,
that undertake engineering, procurement, and construction (EPC) utilization of environment, and population clusters around the
contracts. Now, the construction of NPPs is being carried out facility. The type of samples are selected on the basis of potential
through mega packages. On the secondary side, mostly, there are pathways to man. Annually about 2500 environmental samples
EPC packages. On the nuclear side, there are PC packages. This are being collected and analyzed by ESL at each nuclear site.
has reduced the construction time drastically. The samples are analyzed for various biologically important
radionuclides. The data thus obtained are processed statistically
68.6.4 Operation and used to evaluate the dose annually to the members of public
At present India has 2 ⫻ 200 MWe BWRs, 13 ⫻ 220 MWe residing around NPPs.
PHWRs, and 2 ⫻ 540 PHWR NPPs in operation. All operations The well-defined and executed environmental radiological sur-
are done indigenously by NPCIL. Each twin station unit has veillance program around each nuclear power plant shows that
around 600 operating manpower, including Operation and radioactive contamination is insignificant. It also demonstrates
Maintenance (O&M) personnel. At each station, there are four that the NPP releases are well within the prescribed regulatory
operating crews, one for each operating shift and one extra crew limits. It is observed that the annual radiation doses at the site
for exigencies. All the engineers are trained and licensed and their boundary of the respective nuclear power plant are less than 7%
licenses are periodically updated. All the reactors are operated as of the annual regulatory limit of 1000 µSv during the period of
per their operating technical specifications, which cover all the operations. On comparing with the naturally occurring back-
operating limits as per IAEA safety standards. The technical spec- ground radiation of 2400 µSv/yr, it is almost negligible.
ifications are duly reviewed and approved by Atomic Energy The release of radioactivity to environment from the nuclear
Regulatory Board. power stations is in very small quantities and in any case well
NPCIL is a member of World Association of Nuclear Operators within the limits stipulated by AERB. For monitoring the compli-
(WANO), CANDU Owners Group (COG), and International ance to the prescribed regulatory requirements, environmental
Atomic Energy Agency. The peer reviews by expert teams of survey and meteorological laboratories are set up at each plant
WANO has been recognized internationally as major tool for site. These laboratories analyze samples of food, air, water,and so
sharing the best practices in operation and performance improve- on up to an area of 30-km radius from the plant to assure environ-
ment. Such reviews have been completed for all the reactors. mental security.
These reviews indicate that the condition and performance of sta-
tions matched with those at the world level. WANO members reg- 68.6.5 In-Service Inspection
ularly visit our plants and review the operation and safety aspects. In-service Inspection at all the operating plants is carried out peri-
In the recent reactors, even preoperation reviews have been car- odically as per station ISI program. Based on ISI documents, ISI
ried out by WANO before the criticality of newly constructed program is finalized, which meet the intent of ASME Section XI.
reactors. Regular seminars/meetings are held among members of India has developed all the special tools required for ISI of coolant
COG, during which the challenges faced in various PHWRs are channels and steam generators. BARCIS and Sliver sampling scrap-
shared and discussed. This helps in upgrading the safety standards ing tools are some of the important tools developed for ISI for pres-
further. sure tubes. Life management of coolant channels, flow accelerated
India has experience of 265 reactor operating years. Till now corrosion mainly on secondary side, and feeder thinning are the
there has not been any significant event wherein radioactivity is major challenges faced by the Indian PHWRs. These challenges
released to the public domain and no nuclear accident, as defined have been successfully met through ISI and maintenance.
by International Nuclear Event Scale (INES) of IAEA, has India has successfully completed en masse coolant channel
occurred. replacement in four reactors where Zircaloy-2 pressure tubes
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 19

COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 19

were used. All the tools and techniques were developed indige- 68.8 ACKNOWLEDGMENTS
nously. Also, feeder replacement has been successfully completed
in three reactors. The authors gratefully acknowledge the contribution of Vivek
During the evolution of main circuit design, effort has been Bhasin, Rohit Rastogi, P.K. Singh, Suneel K. Gupta, and Imran
made at minimizing the weld joints and in turn the in-service Ali Khan of Reactor Safety Division of BARC, and K.P. Dwivedi,
requirement of such joints. This has been achieved by adopting A.G. Chhatre, Raghupati Roy, and Santosh Kumar of Nuclear
integral forging for the headers with pullout nozzles, main circuit Power Corporation (NPC).
piping with hockey stick combination for large pipe spools. The
steam generator shells have also been specified as ring forging to
eliminate longitudinal joints. 68.9 REFERENCES
1. Bajaj, S.S. and Gore, A.R., The Indian PHWR, Nuclear Engineering
68.6.6 Development of Codes, Guides, and and Design, Vol. 236, Nos 7–8, pp. 701–722, April 2006.
Standards 2. ASME Boiler & Pressure Vessel Code, Section III; also, Appendix G,
In order to fulfill its mission of stipulating and enforcing rules 1995.
and regulations concerned with nuclear and radiological safety,
3. ASME Boiler & Pressure Vessel Code, Section XI, American Society
AERB is in the process of developing codes and guides for vari- of Mechanical Engineers, 1995.
ous aspects of nuclear reactor design. These guides will borrow
appropriate elements from ASME, ASCE, ACI, Canadian and 4. RCC-G (English Translation), Vols I & II, Design and Construction
French Codes and incorporate India’s experience in their usage, Rules for Civil Works of PWR Nuclear Islands, Drawn-up by
Electricite De France (EDF), July 1988.
Indian materials, and construction practices. One such effort aims
at developing a safety standard for “Design of Nuclear Power 5. BPEL-83 (English Translation by AFNOR, Association Francaise de
Plant Containment Structures” and is currently in draft stage [37]. Normalisation), Technical Rules for the Design of Prestressed
This is based on ASME Code Section III, Division 2 [38], ACI Concrete Structure Using the Limit State Method. 1983.
349 [39], RCC-G [4], CSA-N287.3 [40], and the Indian Code IS 6. BAEL-83 (English Translation by AFNOR, Association Francaise de
456 [41]. Another guide in draft stage is the one for “Seismic Normalisation), Technical Rules for the Design and Calculation of
Qualification of Structures, Systems and Components of Reinforced Concrete Structures and Buildings Using Limit State
Pressurised Heavy Water Reactors” [42]. This guide builds on the Method. 1983.
Indian experience gained during seismic design of reactor struc- 7. Koley, J., Harikumar, S., Ashraf, S.A.H., Chande, S.K., and Sharma,
tures and is based on ASCE [43], IEEE [44] JAEG 4601 [45], S.K., Regulatory Practices for Nuclear Power Plants in India, Nuclear
IAEA NS-G-1.6 [46], and IS 1893 [10]. Engineering and Design, Vol. 236, Nos 7–8, pp. 894–913, April 2006.
8. AERB/SG/D-1, Safety Classification and Seismic Categorization for
Pressurized Heavy Water Reactors, Atomic Regulatory Board,
Mumbai, India, 2000.
68.7 CONCLUSIONS
9. AERB/SG/S-11, Seismic Studies and Design Basis Ground Motion
1. Design of Indian PHWRs is based on ASME B&PV Code for Nuclear Power Plants Sites, Atomic Regulatory Board, Mumbai,
Section III. India,1990.
2. In those cases where the code rules could not be met in let- 10. IS: 1893, Criteria for Earthquake Resistance Design of Structures,
ter, they have been met in spirit by carrying out the required BIS, New Delhi, 1984.
material characterization and component qualification tests.
3. Indian PHWR program depends on leak-before-break crite- 11. Reddy, G.R., Kushwaha, H.S., and Kakodkar, A., Seismic Analysis of
Calandria End shield Assembly of 500 MWe Pressurised Water
rion for eliminating pipe whip restraints. Leak-before-
Reactor, Proceedings of ASME Pressure Vessel and Piping
break has been demonstrated by carrying out extensive tests Conference, Vol. 237, pp. 115–120,1992.
on specimens, pipes, and elbows.
4. The tests have demonstrated adequate margins with respect 12. Reddy, G.R., Kushwaha, H.S., Mahajan, S.C., Kelkar, S.P., and
to failure by fracture even when leakage size crack is present. Karandikar; G.V., Development of 3-D Beam Model for Seismic
Analysis of 500 MWe Reactor Building, BARC/1996/I/004, 1996.
5. The R&D program has explored effects of cyclic loading
and presence of connected piping on fracture behavior of 13. Reddy, G.R., Vaze, K.K., Kushwaha, H.S., Tandale, J.V.,
piping. Subramanian, K.V., and Kelkar, S.P., Procedure of Applying
6. A new B2 index is proposed which eliminates undesirable Decoupling Criteria for a Complex Primary and Secondary System,
conservatism in the present ASME B2 index equation and it Proceedings of ASME Pressure Vessel and Piping Conference, Vol.
272, No.1, pp.129–139, 1994.
can be used for elbows of any bend radius.
7. In-service program follows a combined philosophy of ASME 14. Neelwarne, A., Kushwaha, H.S, and Kakodkar, A., Seismic
Code Section XI and the Canadian Code CSA/ N281.5-05. Qualification of Nuclear Equipment under Multiple Support
8. Design of concrete containment is based on French Code Excitations, Proceedings of 11th SMiRT, Japan, 1991.
RCC-G. 15. Reddy, G.R., Kohei, S., Kushwaha, H.S., and Mahajan, S.C.,
9. In order to avoid a mixture of codes, a need has been felt to Decoupling Criteria for Multi-Connected Equipment, Journal of
write our own codes and a beginning has been made in this Pressure Vessel Technology, Vol.120:, pp. 93–98, 1999.
respect. AERB has published 5 Safety Codes and 45 Safety 16. ASME Boiler & Pressure Vessel Code, Code Case N-411-1,
Guides concerning various aspects of NPPs and 51 other Alternative Damping Values for Response Spectra Analysis of Class
safety support documents. A few others are in various stages 1, 2 and 3 Piping, Section III, Division 1, American Society of
of preparation. Mechanical Engineers, New York, February 20, 1986.
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 20

20 • Chapter 68

17. AERB Safety Guide AERB/SG/O-2, In-Service Inspection of Nuclear Vernon C. Matzen], Civil Engineering Department, North Carolina
Power Plants. State University, Raleigh, 2001.
18. IAEA Safety Guide 50-SG-02 entitled In-Service Inspection for 31. Spence, J. and Findley, G.E., Limit Load for Pipe Bends under In-
Nuclear Power Plants. Plane Bending Proceedings of 2nd International Conference on
Pressure Vessel Technology, San Antonio, Texas, pp. 393–399,1976.
19. CAN/CSA N285.4-05, Periodic Inspection of CANDU Nuclear
Power Plant Components, Canadian Standard Association, 2005. 32. Dodge, W.G. and Moore, S.E., Stress Indices and Flexibility Factors
for Moment Loadings on Elbows and Curved Pipes, Welding
20. CAN/CSA N285.8-05, Technical Requirements for In-Service
Research Council Bulletin No. 179, December 1972.
Evaluation of Zirconium Alloy Pressure Tubes in CANDU Reactors,
Canadian Standard Association, 2005. 33. Caladine, C.R., Limit Analysis of Curved Tubes, Journal of
Mechanical Engineering Science, Vol. 16, pp. 85–87,1974.
21. Report of the United States Nuclear Regulatory Commission Piping
Review Committee, Evaluation of Potential for Pipe Breaks, 34. Touboul, F., Ben Djedidia, M., and Acker, D., Design Criteria for
NUREG/CR-1061, Vol.3, 1984. Piping Component Against Plastic Collapse: Application to Pipe Bend
Experiments, Proceedings of 6th International Conference on
22. International Atomic Energy Agency, Applicability of Leak-Before-
Pressure Vessel Technology, Beijing, China, pp.73–84,1989.
Break Concept, Report of the IAEA Extra Budgetary Programme
on the Safety of WWER-440 Model 230 Nuclear Plants, IAEA 35. Chattopadhyay, J., Tomar, A.K.S., Dutta, B.K., and Kushwaha, H.S.,
TECDOC-710, 1993. Closed Form Collapse Moment Equation of Through Wall
Circumferentially Cracked Elbows Subjected to In-Plane Bending
23. Singh, P.K., Vaze, K.K., Bhasin, V., Kushwaha, H.S., Gandhi, P., and
Moment, ASME Journal of Pressure Vessel Technology, Vol.126, pp.
Murthy, D.S.R., Crack Initiation and Growth Behaviour of
307–317,2004.
Circumferentially Cracked Pipes under Cyclic and Monotonic
Loading, International Journal of Pressure Vessel and Piping, Vol. 80, 36. Kim, Y.J. and Chang, S.O., Closed Form Plastic Collapse Loads of
No. 9, pp. 629–640, September 2003. Pipe Bends under Combined Pressure and In-Plane Bending, Journal
of Engineering Fracture Mechanics. Vol. 73, Issue 11, pp. 1437–1454,
24. Gupta, S.K., Bhasin, V., Vaze, K.K., Ghosh, A.K., and Kushwaha,
July 2006.
H.S., Experimental Investigations on Effects of Simulated Seismic
Loading on LBB Assessment of High Energy Piping, ASME- 37. AERB/SS/CSE-3, Design of Nuclear Power Plant Containment
Journal of Pressure Vessel and Technology, Vol.129, February Structures (draft).
2007.
38. ASME Code Section III, Division 2.
25. Miura, N., Fujioka, T., Kashima, K., Kanno, S., Hayashi, M.,
39. ACI 349, Code Requirements for Nuclear Safety Related Concrete
Ishiwata, M., and Gotohm, N., Low Cycle Fatigue and Ductile
Structures.
Fracture for Japanese Carbon Steel under Dynamic Loading, Nuclear
Engineering and Design, Vol.153, pp. 57–69, 1994. 40. CSA-N287.3-1983, Design Requirements for Concrete Containment
Structures for CANDU Nuclear Power Plant, Canadian Standard
26. Gupta, S.K., Bhasin, V., Vaze, K.K., and Kushwaha, H.S., Ductile
Association.
Fracture Assessment of Piping Systems Including the Compliance
Effects, Paper # 1427, SMiRT 16, Washington DC, August 2001 41. IS 456-2000, Plain and Reinforced Concrete – Code of Practice.
Transactions.
42. AERB Safety Guide No. AERB/SG/D-23, Seismic Qualification of
27. Khan, I.A., Bhasin, V., Vaze, K.K., Ghosh, and A.K., Kushwaha, H.S., Structures, Systems and Components of Pressurised Heavy Water
Significance of Finite Compliance of a Connected Piping System on Reactors (draft).
Fracture Integrity Assessment, American Society of Engineering
43. American Society of Civil Engineers, Seismic Analysis of Safety-
Pressure Vessel and Piping Conference (ASME-PVP-2005),
Related Nuclear Structures and Commentary, ASCE 4-98, Virginia,
Colorado, USA, July 2005.
USA, 2000.
28. Rastogi, R., Bhasin, V., and Kushwaha H.S., Qualification of PHT Piping
44. IEEE Standard 344-1987, IEEE Recommended Practice for Seismic
of Indian 500MW PHWR for LBB, Using R-6 method, Bhabha Atomic
Qualification of Class 1E Equipment for Nuclear Generating
Research Centre, External Report, BARC/1997/E/026, India, 1997.
Stations,1987.
29. Gupta, S.K., Bhasin, V.,. Vaze, K.K, Ghosh, A.K., and Kushwaha,
45. Japan Electric Association, Technical Guidelines for Aseismic Design
H.S., General Limit Load and B2 Stress Index Equation for Pipe
of Nuclear Power Plants, JEAG-4601, 1987.
Bends under In-Plane Bending, Paper # B04/5, SMiRT-19, Toronto,
Canada, August 12–17, 2007. 46. International Atomic Energy Agency, Seismic Design and Component
Qualification for Nuclear Power Plants, IAEA Safety Guide NS-G-1.6,
30. Tan, Y., Experimental and Nonlinear FEA Investigation of Elbow
Vienna, Austria, 2003.
Leading to a new definition of the B2 Stress Index, [PhD Thesis, with
ASME_Ch68_p001-021.qxd 7/28/08 4:33 PM Page 21

You might also like