Professional Documents
Culture Documents
SMP For Slurry Pump
SMP For Slurry Pump
FOR
SLURRY PUMP
OBJECTIVE
The purpose of this work instruction is to explain the procedure for carrying out Overhaul of
Slurry Pump.
1. Slurry Pump
The details of the Slurry Pump are as follows
Make: Shijiazhuang Kingda Pump Industries Ltd.; Model:200ZGB; Capacity: 160 cum/hr;
Max Working Pressure: 6kg/sqcm; Head: 60 Meter; Motor Speed: 2950RPM
DETAILED INSTRUCTION
Sr. Activity Responsibility
No.
I Overhaul to be done as per Checklist
2 Dismantling
1. Cover volute plate 2. Impeller 3.volute 4. Frame body 5. Shaft 6. Set nut B 7.
Set nut A 8. Access hole cover 9. Expeller gland 10. Expeller 11. Casing volute
plate 12. Casing 13. Cover
Note: Always replace the bearings once they have been removed from
the shaft with new ones.
Unnecessary removal of the bearings should be avoided because
removal of the bearing can damage it and cause deterioration of the
interference fit. Except where removal is necessary to give access to
the other parts, bearing should be removed only if they need close
inspection. Symptoms, which will indicate the state of bearing, are the
condition of the lubricant, the bearing running temperature, noise level
and vibration during operation.
Shaft Sleeves
Impeller
Bearings
a. Clean all the components using clean white spirit. Do not use
chlorinated solvents such as trichloroethylene and carbon
tetrachloride because they introduce a corrosion risk when used
on ferrous materials.
b. Visually inspect the bearing. The balls, the inner and outer tracks
must all be free from chipping cracks, abrasions or discoloration.
c. Check that the parts of the cage are firmly fixed together.
d. Visually inspect the bore for any sign of damage. Burrs or any
scratches caused during bearing withdrawal should be carefully
removed by hand application of a fine oilstone, the treatment
being confined to the minimum possible area.
Bearing Housing
5 Reassembly
REVIEW DATE:-
SMP WILL BE REVIEWED IN EVERY SIX MONTH FROM THE DATE OF ISSUE BASED
ON ACTUAL PROBLEM FACED AND SHALL BE UPDATED ACCORDINGLY.
MECHANICAL MAINTANENCE TEAM WILL VISIT THE EQUIPMENT TWICE IN A WEEK
& IF ANY ABNORMALITY NAMELY (VIBRATION, ABNORMAL SOUND, TEMPERATURE
RISE, BELT TIGHTNESS ETC) OF EQUIPMENT IS OBSERVED AND THEN THE SAME
WILL BE RECTIFIED WITHIN PRESCRIBED TIME PERIOD.
DO’s :
2. Ensure relevant equipment/system is electrically isolated before starting the work, if applicable.
3. Ensure relevant air/water valves are fully closed for the equipment/system before starting the work.
4. Provide Danger Boards before starting the work involving dismantling of any equipment/system.
6. Ensure proper follow-up of all plant practices, existing regulations, prescribed procedures & general
safety prior to carry out any work.
7. While replacing any spares/oil, ensure that the same must be as per OEM recommendation.
9. Always use the special tools as recommended by OEM for certain equipments like HCSD Pump.
DONT’s :
1. Don’t start the work without presence of Safety Personnel in case fire / other hazards are involved.
3. Don’t use tools & tackles which are not calibrated / certified by relevant authority.
4. Don’t start the work in Pressure Vessels/Pressure Line/Water Line, unless it is completely de-
pressurised.