Tunnelling - Section 1
1. Which one of the following statements is not correct for heading and benching method of
tunnelling ?
A. Drilling and mucking can be done simultaneously
D. None of these.
Answer: Option C
2. The difference of heights of the tunnels above rail tops of BG and MG tracks is kept
A. 0.30 m
B. 0.45 m
C. 0.60 m
D. 0.75 m
Answer: Option C
B. the bottom
C. the top
D. the side
4. A tunnel is found more advantageous as compared to the alternate routes because it:
A. remains free from snow
5. For B.G. single track railway, the height of the tunnel above top of rails should be
A. 5.5 m to 5.8 m
B. 5.8 m to 6.2 m
C. 6.7 m to 7.3 m
D. 7.3 m to 7.5 m
Answer: Option C
6. Pick up the correct statement regarding drilling a tunnel from the following:
A. Holes are drilled by pneumatically operated rock drills
The diameter of the bore hole at the deepest point should be 6 mm more than the
C.
diameter of the cartridge
7. For tunnels exceeding 300 m in length, the grade should be provided below
A. 50% of the ruling gradient
B. dewatering
C. permanent drainage
9. Pick up the correct statement from the following during tunnel excavation,
A. Oxygen should not be less than 19.5%
B. trimmers
C. cut holes
D. chisels.
Answer: Option B
B. pyramid cut
C. fan cut
D. V-cut
12. Which one of the following linings is suitable for shield driven tunnels particularly in the
subaqueous regions :
A. Brick lining
B. stone lining
C. timber line
E. concrete lining.
Answer: Option D
14. The following tunnels were constructed in different countries for different purposes :
1. Emperor Claudius built the first Roman tunnel
2. The first highway tunnel was constructed in Hungary
3. The first underground railway tunnel was constructed in Great Britain
4. The first navigational tunnel was constructed in France.
The correct chronological development of these tunnels is:
A. 4 1 3 2
B. 1 4 2 3
C. 2 3 1 4
D. 3 2 4 1
Answer: Option B
15. The following operations are generally employed for tunnelling in hard rock.
1. Removing ground water,
2. Loading holes and firing the explosive
3. Setting up and drilling
4. Grouting and lining
5. Removing muck
6. Ventilation and removing explosion dust
The correct sequence is :
A. 3 2 6 5 1 4
B. 3 4 6 1 5 2
C. 4 1 2 3 6 5
D. 5 4 2 1 3 6
Answer: Option A
16. Pick up the mechanical ventilation method used for tunnels from the following:
A. blowing fresh air by ducts to the face of tunnel
exhausting foul air by ducts from the face of the tunnel and permitting fresh air
B.
through the tunnel
B. Shield method
B. 15 metres depth
C. 20 metres depth
D. 25 metres depth.
Answer: Option B
19. The following operations are required for tunnelling in rocky terrain :
1. Removing the foul gases
2. Marking the tunnel profile
3. Setting up and drilling
4. Checking misfire
5. Mucking
The correct sequence is :
A. 1 2 3 4 5
B. 2 3 5 4 1
C. 4 2 1 3 5
D. 2 3 1 4 5
Answer: Option D
20. The advantages of providing a pair of tunnels as compared to only one large highway tunnel
is :
A. economy in cost of construction
21. Which one of the following statements is not correct in respect of setting of an inclined
tunnel:
A. Reference points are constructed at every 300 m.
B. firm ground
C. running ground
D. None of these.
Answer: Option A
23. Concrete lining is provided concurrently with the driving operation in case of
A. rock terrain
B. soft rock
C. running soil
D. none of these.
Answer: Option A
24. The concentration of the dust particles of the size 0.5 to 5 microns adjacent to the working
face should not be more than
A. 200 particles/cm3
B. 250 particles/cm3
C. 300 particles/cm3
D. 450 particles/cm3
E. 400 particles/cm3
Answer: Option D
C. After driving the top portion 3 m to 3.5 m holes are drilled into the head and bench.
D. The holes in head and bench are loaded together with explosive for blasting.
E. Firing of head holes is done just before the bench holes are fired.
Answer: Option E
26. Which one of the following methods is generally used for the layout of the muck-car tracks
A. the grass hopper method
27. For transferring the tunnel alignment through shafts, we adopt the following steps :
1. Hanging two or more plumb lines in the shaft
2. Determining the bearing of the plumb lines i.e. plumb plane
3. Suspending a 35 kg weight by each plumb line
4. Immersing the weights of both the plumb lines in the buckets containing water.
The correct sequence of steps is :
A. 1 2 3 4
B. 4 3 2 1
C. l 3 2 4
D. 2 1 4 3
Answer: Option A
28. For initial surveys of tunnels, the following activities are involved:
1. Marking portal point with concrete pillars on the ground
2. Marking tunnel obligatory points on the topographical maps
3. Preliminary setting of the tunnel on the topographical Survey of India maps
3. Driving lines between the fixed obligatory points.
The correct sequence of the activities is :
A. 3 2 4 1
C. 4 3 1 2
D. 2 4 3 1
Answer: Option A
29. For full face method, the excavation to be done is generally divided into
A. two sections
B. three sections
C. four sections
D. five sections.
Answer: Option B
30. The tunnels, the artificial underground passages are constructed for :
A. highways
B. railways
C. sewerage
31. In the wooded bulk-head, used for mucking in steep grade tunnels,
A. one opening is provided
D. no opening is provided.
Answer: Option B
B. rectangular
C. parabolic
D. circular
33. Pick up the explosive used for tunnelling in soft rocks from the following :
A. blasting gelatine
B. special gelatine
C. ammonia dynamite
D. semi-gelatine.
Answer: Option C
34. The cut of a tunnel face is shown in given figure. This is called
A. Michigan cut
B. Burn cut
C. Fan cut
D. Horizontal cut.
Answer: Option A
35. For B.G. single track, the section of the tunnel must have a width
A. 4.2 m to 4.5 m
B. 4.5 m to 4.8 m
C. 4.9 m to 5.5 m
D. 5.5 m to 5.8 m
Answer: Option C
36. Which one of the following methods is generally adopted for tunnelling in firm ground
A. Full face method
C. Drift method
37. An overhead track on a large truss frame is required in case of car changer by
A. the grass hopper method
B. The height point on the ridge is fixed with the help of reciprocal ranging
39. In the given figure drill holes, heading, mucking and benching are mumbered as 1, 2, 3, 4
The correct sequence is :
A. 4 1 2 3
B. 1 2 3 4
C. 4 1 3 2
D. 3 4 1 3
Answer: Option C
40. The length of the needle beam used in needle beam method of tunnelling is usually
A. 2 m to 4 m
B. 2.5 m to 6 m
D. 5 m to 6 m
Answer: Option D
41. High pressure grouting is generally restored for concreting in the lining if the rock strata is:
A. highly fissured
B. poor
42. For hauling muck from the tunnel, the following type of muck-car is used :
A. muck box
B. balle-ship
D. U-bottom
E. All of these.
Answer: Option E
43. Which one of the following methods is adopted for permanent drainage of tunnels :
A. provision of longitudinal drains
C. concrete lining
20. Question
Which one of the following statements is not correct for heading and benching method of
tunnelling ?
19. Question
The advantages of providing a pair of tunnels as compared to only one large highway tunnel
is :
1. 7.3 m to 7.5 m
2. 5.5 m to 5.8 m
3. 6.7 m to 7.3 m
4. 5.8 m to 6.2 m
Ans 3
17. Question
A tunnel is found more advantageous as compared to the alternate routes because it:
16. Question
Pick up the correct statement from the following during tunnel excavation,
56. Question
For highways, tunnelling is preferred to if the open cut exceeds :
1. 10 metres depth
2. 15 metres depth
3. 20 metres depth
4. 25 metres depth.
Ans2
1. pyramid cut
2. fan cut
3. V-cut
4. all
Ans4
12. Question
Which one of the following linings is suitable for shield driven tunnels particularly in the
subaqueous regions :
1. Brick lining
2. stone lining
3. timber line
4. cast iron lining
Ans4
11. Question
The difference of heights of the tunnels above rail tops of BG and MG tracks is kept
1. 0.30 m
2. 0.45 m
3. 0.60 m
4. 0.75 m
Ans3
9. Question
To attain the required shape of the tunnel section, we use :
1. trimmers
2. easers
3. cut holes
4. chisels.
Ans1
1. exhausting foul air by ducts from the face of the tunnel and permitting fresh air
through the tunnel
2. all
3. blowing fresh air and exhausting foul air by ducts
4. blowing fresh air by ducts to the face of tunnel
Ans2
7. Question
In case of drift method of tunnelling, the drift may be excavated at
1. the bottom
2. the side
3. the top
4. all
Ans4
6. Question
The method of draining in the tunnels, is generally known as
1. foredrainage
2. dewatering
3. permanent drainage
4. all
5. Question
Pick up the correct statement regarding drilling a tunnel from the following:
2. Question
In case of railways,
3. Question
Concrete lining is provided concurrently with the driving operation in case of
1. none of these.
2. rock terrain
3. running soil
4. soft rock
Ans2
6. Question
For hauling muck from the tunnel, the following type of muck-car is used :
1. circular
2. rectangular
3. parabolic
4. polycentric
Ans4
1. firm ground
2. soft ground
3. running ground
4. None of these.
Ans2
10. Question
In the wooded bulk-head, used for mucking in steep grade tunnels,
1. no opening is provided.
2. two openings are provided
3. one opening is provided
4. three openings are provided
Ans2
11. Question
High pressure grouting is generally restored for concreting in the lining if the rock strata is:
1. poor
2. likely to get seepage of water
3. highly fissured
4. all
Ans4
12. Question
Pick up the explosive used for tunnelling in soft rocks from the following :
1. special gelatine
13. Question
The tunnels, the artificial underground passages are constructed for :
1. sewerage
2. railways
3. water supply project
4. all
Ans4
15. Question
Which one of the following methods is generally adopted for tunnelling in firm ground
16. Question
An overhead track on a large truss frame is required in case of car changer by
18. Question
Which one of the following methods is adopted for permanent drainage of tunnels :
1. concrete lining
2. grouting with cement or chemicals
3. continuous open drains
19. Question
Which one of the following methods is generally used for the layout of the muck-car tracks
21. Question
For full face method, the excavation to be done is generally divided into
1. two sections
2. four sections
3. three sections
4. five sections.
Ans3