Hi-Flo ​ FX2​ U.S.

Facility Requirements
If you have questions regarding these requirements please contact
Customer Service (​cs@edenlabs.com​) for more information.

I. INTRODUCTION
In order for your Hi-Flo FX2 CO2 Extraction System to perform as designed, the facility where the unit will be
installed must meet electrical supply, temperature, humidity, and ventilation requirements as specified by Eden
Labs.

II. INSTRUCTIONS
The project manager, and/ or primary stakeholder, that will be responsible for the installation and management of
your Hi-Flo FX2 unit must read and sign this document. Please ​initial each item​ below indicating that you have
read and understand the requirements as specified.
The requested information in Section V is to be provided by a ​licensed electrical contractor​.
This information will be used by Eden Labs to purchase appropriately configured components for your
Hi-Flo FX2 extraction unit. ​Some components may have a four to six week lead-time and ​cannot be
ordered until this form is completed and returned to Eden Labs​.

III. ENVIRONMENTAL REQUIREMENTS​ (INITIAL)


      Temperature:​ Maximum environmental temperature - 22​°​C / 72​°​F
      Humidity:​ 30-60%
      Ventilation (general dilution):​ 10 – 15 air exchanges per hour or as required by regulation.
      Ventilation (local):​ sufficient to remove gas released from vent points on the Hi-Flo FX2 system.

IV. ELECTRICAL REQUIREMENTS​ (INITIAL)


      Facility Electrical Supply Standard:​ must meet United States National Electrical Code (NEC)
standards and supply power at a frequency of 60 hertz.
     ​ ​Facility​ ​Electrical Supply Non-standard:​ such as a generator, phase converter, power inverter,
etc. ​may void the warranty​ for all electrical components supplied with the Hi-Flo FX2 system.
     ​ ​Facility Electrical Supply Confirmation:​ must be verified by a licensed electrical contractor.
The results of the verification must be filled in below for completion of this form.

V. FACILITY ELECTRICAL SUPPLY CONFIRMATION


​ ​TO BE COMPLETED BY LICENSED ELECTRICAL CONTRACTOR
Total current available: ​     ​ amps
Voltage and Phase available (fill in all available):
     ​ volts / ​     ​ phase (single or three) ​     ​ volts / ​     ​ phase (single or three)
     ​ volts / ​     ​ phase (single or three) ​     ​ volts / ​     ​ phase (single or three)

FX2 Facility Requirements Form Page 1 of 3


Hi-Flo ​ FX2​ U.S. Facility Requirements
If you have questions regarding these requirements please contact
Customer Service (​cs@edenlabs.com​) for more information.

VI. Electrical Demand - Hi-Flo FX2 CO2 Extractors ​(INITIAL BY ORDERED SYSTEM SIZE)

​__________ Initial Size (inches) Weight (lbs) Power Plug

FX2 20L2K 68 x 48 x 107 2,200 n/a n/a

4500 watt heat bath (extractor) 31 x 12 x 13 24 240V/1P/60hz 18.5 FLA Nema L6-30 plug (heater)
Nema 5-15 (pump)

4500 watt heat bath 2 ea. 31 x 12 x 13 35 240V/1P/60hz 18.5 FLA Nema L6-30 plug (heater) x2
(separator) Nema 5-15 (pump)

Chiller 26 x 51.6 x 55.1 721 230v/3P/60hz 26.5 FLA Service Disconnect


(cooling capacity 13.8kw)

Compressor (10hp) 76 x 25 x 58 775 230v/3P/60hz 29.9 FLA Service Disconnect

Scales (3) 12 x 12 x 1 1/4 45 200ma Nema 5-15 x3

​__________ Initial Size (inches) Weight (lbs) Power Plug

FX2 20L5K 106 x 58 x 126 2,200 n/a n/a

Chiller 26 x 51.6 x 55.1 721 230v/3P/60hz 26.5 FLA Service Disconnect


(cooling capacity 13.8kw)

Compressor (15hp) 76 x 25 x 58 672 230v/3P/60hz 39.3 FLA Service Disconnect

Scales (3) 12 x 12 x 1 1/4 45 200ma Nema 5-15 x3

​__________ Initial Size (inches) Weight (lbs) Power Plug

FX2 2x20L2K 21’ x 6’ x 10’ 2,800 n/a n/a

Pump and Driver (4LPM) Mounted on Unit n/a 230v/3P/60 26.5 running amps 600v 60 amp disconnect

Chiller 58.6 x 46.5 x 30.9 650 208-230v/3P/60hz 47.5 MCA Service Disconnect
(cooling capacity 41.8kw) MOP 80

Recirculating Heat Bath Cart Mounted on Unit n/a 6 each. @ 240v/1P/60hz Service Disconnect
18.5a115v/1P/60hz 0.84 FLA

Scales (3) 12 x 12 x 1 1/4 45 200ma Nema 5-15 x3

FX2 Facility Requirements Form Page 2 of 3


Hi-Flo ​ FX2​ U.S. Facility Requirements
If you have questions regarding these requirements please contact
Customer Service (​cs@edenlabs.com​) for more information.

​__________ Initial Size (inches) Weight (lbs) Power Plug

FX2 2x20L5K 21’ x 6’ x 10’ 2,800 n/a n/a

Pump and Driver Mounted on Unit n/a 230/3P/60 600v 60 amp disconnect

Chiller 58.6 x 46.5 x 30.9 650 208-230v/3P/60hz 47.5 MCA Service Disconnect
(cooling capacity 41.8kw) MOP 80

Scales (3) 12 x 12 x 1 1/4 45 200ma Nema 5-15 x3

​Attention! Compressor orders have a ​four to six week lead-time


AFTER​ Eden Labs receives this information.

VII. Ship to Address – Please include site contact and telephone number:

VIII. Confirmation​ (​SIGNATURE​)


By providing a signature below I certify that I have read and provided information as requested in this form.

Buyer’s Company Name Contact Telephone / Email


     

Contact Name / Title Signature Date


         
  

FX2 Facility Requirements Form Page 3 of 3