FIRE FIGHTING SYSTEM

Installation Checklist for Pump House - Piping,


Equipment & Instrument

PROJECT:

Location / Area :

Drawing No.

SR NO. Activities / Items to be inspected

Check the pump for approved make, model no, flow and head as per technical
1 submittal.

2 Check pumps are installed as per approved drawings.

Check pumps are installed on foundations with pads or on inertia base frame with
3 vibration springs or mountings as applicable.

Check adequate space available for the installation of valves, flexible connections /
4 Strainer, Meters, Gauges etc.

Verify that pressure gauges, test points, drain points are provided as per the
5 approved drawing.

Check the piping is supported independently and the load is not transferred to
6 pumps.

Check provisions with sockets are made for BMS peripheral like DP switch as per
7 data point schedule

Check adequate access available for maintenance of pumps including removal of


8 motor, pump impellers, couplings and other accessories.
Ensure strainers are installed correctly and sufficient space available for removal
9 and cleaning of strainers.

10 Check all nuts, bolts, etc. are tightened as required

11 Check all electrical wiring and grounding is completed and tightened as required.

Check the coupling alignment in accordance with the manufacturer’s instructions /


12 specifications.

13 Check that coupling guards are provided as per the requirement.

1 of 10
FIRE FIGHTING SYSTEM

Installation Checklist for Pump House - Piping,


Equipment & Instrument

PROJECT:

Location / Area :

Drawing No.

SR NO. Activities / Items to be inspected

14 Check pumps and motor bearings are lubricated and rotating freely.

Check that there is no rust formation on the equipment and touch up painting
15 completed, if required.

16 Check the identification, flow directions and valve tags are provided as approved.
Comments / Remarks :

Checked By:

Signature :

Name :

Date:

2 of 10
G SYSTEM
Document No:

Revision No: 0

Date of Issue:

Page No: 1

Ref No:

Date:
Verified
Yes No N/A

3 of 10
G SYSTEM
Document No:

Revision No: 0

Date of Issue:

Page No: 1

Ref No:

Date:
Verified
Yes No N/A

Approved By:

Signature :

Name :

Date :

4 of 10
FIRE FIGHTING SYSTEM

Installation Checklist for Pipe Works Hydrant &


Sprinkler Line

PROJECT:

Location / Area :

Drawing No.

SR NO. Activities / Items to be inspected

1 Check all pipes used are as per approved material submittal and make.

2 Check pipes are installed as per approved drawings.

3 Check all piping is painted with one coat of primer and two coat of PO red

Check the spacing of supports, size of threaded rod is as per specifications and
4 approvals.

Check M S angle supports are coated with red oxide primer and subsequently with
5 enamel paint as per approval.

6 Check welded joints are welded properly

7 Check flange joints are joined with good quality gasket.

Check that only eccentric reducers with level side up are used for reduction in
8 pipe sizes in horizontal run and concentric reducers are used in vertical runs.

9 Check that installed piping is free of sags and bends


Check that gap is maintained between two parallel pipes to permit valve
10 servicing etc.

Flexible connectors are installed at equipment connections as per requirements /


11 approved drgs.
Check drains are installed as per specifications at the lowest point of risers,
12 branches and main lines.

5 of 10
FIRE FIGHTING SYSTEM

Installation Checklist for Pipe Works Hydrant &


Sprinkler Line

PROJECT:

Location / Area :

Drawing No.

SR NO. Activities / Items to be inspected


Check provisions for air vents, pressure gauges, thermometers are made as per
13 approved drawing.

14 Check strainers, valves etc. are installed correctly and as per approved drawings.

15 Check sleeves are installed for pipes passing through walls / partitions as required.

16 Check nuts, bolts, screws, brackets drop rods etc. are tight and aligned properly.

Installed piping is protected from damages for the remainder of the


17 construction period.
Comments / Remarks :

Checked By:

Signature :

Name :

Date:

6 of 10
G SYSTEM
Document No:

Revision No: 0

Date of Issue:

Page No: 1

Ref No:

Date:
Verified
Yes No N/A

7 of 10
G SYSTEM
Document No:

Revision No: 0

Date of Issue:

Page No: 1

Ref No:

Date:
Verified
Yes No N/A

Approved By:

Signature :

Name :

Date :

8 of 10
FIRE FIGHTING SYSTEM

Installation Checklist for Under Ground Pipe


Works Hydrant Line

PROJECT:

Location / Area :

Drawing No.

SR NO. Activities / Items to be inspected

1 Check all pipes used are as per approved material submittal and make.

2 Check pipes are installed as per approved drawings.

3 Check all piping is with one coat of primer with Wrapping Coating

4 Check that installed piping is free of sags and bends


Check that gap is maintained between two parallel pipes to permit valve
5 servicing etc.

6 Check nuts, bolts, screws, brackets etc. are tight and aligned properly.
Comments / Remarks :

Checked By:

Signature :

Name :

Date:

9 of 10
G SYSTEM
Document No:

Revision No: 0

Date of Issue:

Page No: 1

Ref No:

Date:
Verified
Yes No N/A

Approved By:

Signature :

Name :