Professional Documents
Culture Documents
Fire Fighting Checklist
Fire Fighting Checklist
PROJECT:
Location / Area :
Drawing No.
Check the pump for approved make, model no, flow and head as per technical
1 submittal.
Check pumps are installed on foundations with pads or on inertia base frame with
3 vibration springs or mountings as applicable.
Check adequate space available for the installation of valves, flexible connections /
4 Strainer, Meters, Gauges etc.
Verify that pressure gauges, test points, drain points are provided as per the
5 approved drawing.
Check the piping is supported independently and the load is not transferred to
6 pumps.
Check provisions with sockets are made for BMS peripheral like DP switch as per
7 data point schedule
11 Check all electrical wiring and grounding is completed and tightened as required.
1 of 10
FIRE FIGHTING SYSTEM
PROJECT:
Location / Area :
Drawing No.
14 Check pumps and motor bearings are lubricated and rotating freely.
Check that there is no rust formation on the equipment and touch up painting
15 completed, if required.
16 Check the identification, flow directions and valve tags are provided as approved.
Comments / Remarks :
Checked By:
Signature :
Name :
Date:
2 of 10
G SYSTEM
Document No:
Revision No: 0
Date of Issue:
Page No: 1
Ref No:
Date:
Verified
Yes No N/A
3 of 10
G SYSTEM
Document No:
Revision No: 0
Date of Issue:
Page No: 1
Ref No:
Date:
Verified
Yes No N/A
Approved By:
Signature :
Name :
Date :
4 of 10
FIRE FIGHTING SYSTEM
PROJECT:
Location / Area :
Drawing No.
1 Check all pipes used are as per approved material submittal and make.
3 Check all piping is painted with one coat of primer and two coat of PO red
Check the spacing of supports, size of threaded rod is as per specifications and
4 approvals.
Check M S angle supports are coated with red oxide primer and subsequently with
5 enamel paint as per approval.
Check that only eccentric reducers with level side up are used for reduction in
8 pipe sizes in horizontal run and concentric reducers are used in vertical runs.
5 of 10
FIRE FIGHTING SYSTEM
PROJECT:
Location / Area :
Drawing No.
14 Check strainers, valves etc. are installed correctly and as per approved drawings.
15 Check sleeves are installed for pipes passing through walls / partitions as required.
16 Check nuts, bolts, screws, brackets drop rods etc. are tight and aligned properly.
Checked By:
Signature :
Name :
Date:
6 of 10
G SYSTEM
Document No:
Revision No: 0
Date of Issue:
Page No: 1
Ref No:
Date:
Verified
Yes No N/A
7 of 10
G SYSTEM
Document No:
Revision No: 0
Date of Issue:
Page No: 1
Ref No:
Date:
Verified
Yes No N/A
Approved By:
Signature :
Name :
Date :
8 of 10
FIRE FIGHTING SYSTEM
PROJECT:
Location / Area :
Drawing No.
1 Check all pipes used are as per approved material submittal and make.
3 Check all piping is with one coat of primer with Wrapping Coating
6 Check nuts, bolts, screws, brackets etc. are tight and aligned properly.
Comments / Remarks :
Checked By:
Signature :
Name :
Date:
9 of 10
G SYSTEM
Document No:
Revision No: 0
Date of Issue:
Page No: 1
Ref No:
Date:
Verified
Yes No N/A
Approved By:
Signature :
Name :
Date :
10 of 10