Daily Report 24-11-19
Daily Report 24-11-19
Daily Report 24-11-19
Shop
C. Construction Equipment Number of Worker by Area Total
No. Function, Type, Model WW RF PUE PUW CT OXE OXW OXB BU GE Unit-Day
1 Welding Machine Miller 3
2 Welding Machine Inverter 400 A 7
3 TMC 8 Tons 1
4 Trailer 0
5 Compressor PDS 185S 1
6 Genset 100 KVA 1
8. Area of Concern
No. Description Area
1 Plan :
Piping installation for TP is completed 19 TP from 19 TP Site
Actual :
Piping installation for TP is completed 19 TP from 19 TP Site
2 Test Package 016 & TP 019 DWG FE-6300-S1A3 #1703. Installation will be perform after catalyst ware house available Site
3 Fabrication WW line is finish. Intsallation will be pospone as per site condition (waiting area available) Site
DAILY REPORT
for
PT. NIPPON SHOKUBAI INDONESIA
i-III Project