Professional Documents
Culture Documents
Construction Methodology For Il Corso
Construction Methodology For Il Corso
ARRANGEMENT, PROTECTION,
MARIÑAS & CO. BUILDERS, INC ERECTION AND STORAGE OF
MATERIALS WORK METHODOLOGY
INDEX
CONTENTS PAGE
NO.
INDEX (i)
1.0 PURPOSE 1
4.0 MATERIALS 1
7.0 RESPONSIBILITIES 2
1. PURPOSE
The purpose of this Work Methodology is to define the work operation, quality
control and safety activities involved safely unloading of steel structures, sorting &
arrangement, protection and storage of materials and Erection Steel Structure
including installation and fixing of Roof and Wall Sheets.
2. LOCATION OF WORKS
3. SEQUENCE OF EVENTS
This procedure shall apply to all activities and actions undertaking for the following:
Steel Structure Erection, including Tubular beams, Fascia, C-Purlins, roofings and
Accessories
4. MATERIALS
All Structural steel works to form a sound and complete structure, consisting of
Tubular steel, steel C-purlins, sagrods threaded w/ washers, THK stiffener plates.
6. SAFETY REQUIREMENTS
6.1 Tools and equipment should be made operational and available for use.
6.3 Safety officer shall implement surveillance to help and protect all assigned
workers against exposure to safety hazards.
6.6 When working at height, body harness shall be fixed to safety line, fixed on
beams or a rigid steel element.
7. RESPONSIBILITIES
The Project Manager shall be responsible for the overall implementation of this
procedure and execution works in accordance with the requirements.
The Project In-Charge / Site Engineer shall be responsible in carrying out all the
activities mentioned in this methodology in accordance with the approved
construction drawings.
The Safety Officer is responsible for monitoring and assessing hazardous and
unsafe situations and developing measures to assure personnel safety.
The QA/QC Engineer shall be responsible for monitoring the works, attending
inspections at various stages of the works defined herein, and the efficient
recording and reporting of results.
8. WORK PROCEDURE
8.1.1. Place the fabricated rigid A-frame beside the truck with container.
8.1.2. Set the rigid A-frame to be the same level or elevation with the truck bed.
8.1.3. Discharge/Sliding tracks are provided in the container for withdrawing the skid.
Remove the discharge/sliding tracks from container.
8.1.4. Align the assembled discharge/sliding track to the inside track. The level of the
discharge/sliding track is the same level with the inside track.
8.1.5. Once the level of inside and discharge/sliding track is aligned, fix the discharge
track to the rigid A-Frame.
8.1.6. Grease the discharge/sliding track. Attach cables(or chains) to the front of the skid
frame, and then attach to the pulling vehicle.
8.1.7. Pull the skid from the container using an even pull speed. Safety should always be
observed. Do not jerk the skid by accelerating discharge vehicle. Cables(or
chains) should always be tight during the entire discharge pull.
8.1.8. After pulling out the contents form inside the container remove the inside tracks
form the container by removing out the fasteners. When the inside track has
been removed from the container closed the door, the container is ready to
returned to the terminal.
8.2.1. Members should be checked parkmark as packing list enclosed before unloading
for best unloaded positions.
8.2.4. Girts, purlins, eave struts and bracing are divided according to the
8.2.6. Small components (nuts, bolts, clips, fasteners etc.) area stored in a given area
convenient to all parts of the building.
8.3.2. The material shall be stored above ground level with timber packing. They shall
not be stacked directly on top of each other but must be separated by 50mm
thick timber.
8.3.3. The materials should be placed in minimum 5% slope to avoid water pond.
8.3.4. The materials shall be kept free from dirt, grease, and other foreign materials and
shall be protected from road splash.
8.3.6. All bolts, nuts, washers, screws, small plates and articles generally shall be
suitably packed and identified.
8.8.1 The eave gutter is attached to gutter strap with gutter support and shall be
fixed.
8.8.2 Insert the downspout to the cut valley of the gutter.
Health and Safety hazards / Risks associated with the covered by this Work
Methodology are:
Personal Protective Equipment (PPE) such as safety boots and helmet would be
provided with workers. In addition, adequate PPE (e.g. ear and eye protectors)
should also be available for construction work as required.
First Aide Facilities such as first aide box would be made available for in case of
minor injury treatment.
Workers used PPE / Gloves / suitable for the work being carried out and as
recommended by the Safety Officer in charge / Engineer in charge.