5 STOCKYARD
5.06 Area Lighting 14,573.99 0.715%
Ducting and Cabling - install 12,002.11 0.588% 1-Oct-09 26-Feb-10
Fixtures - install 2,571.88 0.126% 1-Oct-09 27-Feb-10
Sub Total 5 14,573.99 0.71%
10 EXISTING JETTY DL-1, DL-2
10.01 Area Lighting 22,598.96 1.108%
Ducting and Cabling - install 18,610.91 0.912% 31-Aug-09 29-Nov-09
Fixtures - install 3,988.05 0.196% 31-Aug-09 29-Nov-09
10.02 Wash Down and Treatment
10.03 Repairs to Plinth Columns
Sub Total 10 22,598.96 1.11%
11 MISCELLANEOUS
11.01 Control Centre Building 71,984.99 3.529%
h Electrical Works 71,984.99 3.529% 31-Aug-09 29-Oct-09
11.04 Electrical Sub-stations 1,852,618.87 90.829% 8.32% 9.16% 0.00% 0.00% 8.32% 9.16%
b Substructure and Floor Slabs 342,331.75 16.784% 30-Mar-09 27-Jun-09 8.32% 49.57% 0.000% 0.00% 8.32% 49.57% On Progress (Should be complete)
c Superstructure 513,497.62 25.176% 28-Jun-09 25-Sep-09 Should be started
d Finished 342,331.75 16.784% 28-Jun-09 25-Sep-09 Should be started
e Ducting and Cabling 513,497.62 25.176% 26-Sep-09 24-Dec-09
Equipment - install 140,960.13 6.911% 1-Oct-09 28-Jan-10
11.08 Standby power generation 77,892.64 3.819%
Enclosure - Install 41,380.47 2.029% 3-Aug-09 31-Oct-09
Diesel Tank - install 2,434.15 0.119% 3-Aug-09 31-Oct-09
Equipment - install 34,078.03 1.671% 3-Nov-09 31-Jan-10
Subtotal 11 2,002,496.49 98.18% 8.32% 8.47% 0.00% 0.00% 8.32% 8.47%
TOTAL 2,039,669.44 100.00%
SCHEDULE 8.32% 0.00% 8.32%
Page 1 of 24
DESIGN, CONSTRUCTION AND COMMISSIONING OF
COAL HANDLING FACILITIES AT CIGADING INTERNATIONAL BULK TERMIN
STEEL STRUCTURE WORK PROGRE
PT. KRAKATAU ENGINEERING PT. CIGADING INTERNATIONAL BULK TERMINAL
WEEK / PERIOD OF
CONTRACT SCHEDULE
ITEM No. DESCRIPTION
WEIGHT
VALUE (US$) START FINISH
FACTOR
Page 2 of 24
DESIGN, CONSTRUCTION AND COMMISSIONING OF
COAL HANDLING FACILITIES AT CIGADING INTERNATIONAL BULK TERMIN
STEEL STRUCTURE WORK PROGRE
PT. KRAKATAU ENGINEERING PT. CIGADING INTERNATIONAL BULK TERMINAL
WEEK / PERIOD OF
CONTRACT SCHEDULE
ITEM No. DESCRIPTION
WEIGHT
VALUE (US$) START FINISH
FACTOR
7 OUTGOING CONVEYOR CV-05 AND TRANSFER TOWER TT-4
7.02 Structures and Enclosures to CV-05, Transfer Tower TT-4 23,051.68 2.293%
Structures for Supporting Towers - install 4,852.99 0.483% 2-Aug-09 1-Dec-09
Structures for Conveyors (CV-05) - install 13,345.71 1.327% 2-Aug-09 1-Dec-09
Enclosures for Conveyors (CV-05) - install 4,852.99 0.483% 3-Oct-09 1-Dec-09
7.03 Structural Modification, Refurbishment to existing conveyor structure 21,277.21 2.116%
a Existing Conveyor Structure : Demolition TT-04 12,158.41 1.209% 30-Jan-09 31-May-09
b Existing Conveyor Structure : install 9,118.80 0.907% 30-Aug-09 27-Nov-09
Sub Total 7 44,328.89 4.41%
8 OUTGOING CONVEYORS CV-06, CV-07, TRANSFER TOWER TT-5
Structural Modification, Re-Furbishment and Re-Finishing of Existing
8.01 244,815.58 24.352%
Conveyor Structures and Towers
a Demolition of Existing Conveyors 77,203.25 7.679% 30-Jan-09 31-May-09
b Demolition of Existing Structures 96,504.07 9.599% 30-Jan-09 31-May-09
c Removal of Debris 38,601.63 3.840% 2-Apr-09 30-Jun-09
d Refurbishment : Installation 32,506.63 3.233% 1-Jun-09 30-Sep-09
8.02 Structures and Enclosures to CV-06, CV-07, Transfer Tower TT-5 157,939.30 15.710%
a Structures for Supporting Towers - install 33,250.38 3.307% 2-Jul-09 30-Oct-09
b Structures for Conveyors (CV-6) - install 66,500.76 6.615% 2-Aug-09 30-Nov-09
c Structures for Conveyors (CV-7) - install 24,937.78 2.481% 2-Jul-09 30-Oct-09
d Enclosures for Conveyors (CV-6) - install 24,937.78 2.481% 1-Aug-09 29-Nov-09
e Enclosures for Conveyors (CV-7) - install 8,312.59 0.827% 2-Jul-09 30-Oct-09
Sub Total 8 402,754.88 40.06%
TOTAL 1,005,329.20 100.00%
SCHEDULE
ACCUMULATIVE SCHEDULE
PROGRESS
ACCUMULATIVE PROGRESS
Page 3 of 24
DESIGN, CONSTRUCTION AND COMMISSIONING OF
COAL HANDLING FACILITIES AT CIGADING INTERNATIONAL BULK TERMIN
STEEL STRUCTURE WORK PROGRE
PT. KRAKATAU ENGINEERING PT. CIGADING INTERNATIONAL BULK TERMINAL
WEEK / PERIOD OF
CONTRACT SCHEDULE
ITEM No. DESCRIPTION
WEIGHT
VALUE (US$) START FINISH
FACTOR
VARIANCE
VARIANCE
Page 4 of 24
DESIGN, CONSTRUCTION AND COMMISSIONING OF
COAL HANDLING FACILITIES AT CIGADING INTERNATIONAL BULK TERMIN
PIPING WORK PROGRESS
PT. KRAKATAU ENGINEERING PT. CIGADING INTERNATIONAL BULK TERMINAL
WEEK / PERIOD OF
CONTRACT SCHEDULE
ITEM No. DESCRIPTION
WEIGHT
VALUE (US$) START FINISH
FACTOR
1 BARGE WHARF
1.06 Fire Fighting 4,992.94 1.928%
a Piping Works Install 3,524.43 1.361% 1-May-09 29-Jun-09
b Fixtures Installation 1,468.51 0.567% 1-May-09 29-Jun-09
Provide attendance on and all necessary coordination with barge Wharf
1.11 28,211.42 10.892%
contract contruction supervision personnel
Sub total 1 33,204.36 12.820%
BARGE UNLOADING, WHARF CONVEYOR CV-01 AND TRANSFER
2
TOWER TT-1
2.09 Fire Protection 4,954.93 1.913%
a Piping Works- install 3,497.60 1.350% 30-Nov-09 28-Feb-10
b Fixtures- install 1,457.33 0.563% 15-Jan-10 28-Feb-10
2.12 Sundries 382.57 0.148%
a Sundries - install 382.57 0.148% 1-Jan-10 1-Mar-10
Sub Total 2 5,337.50 2.06%
INCOMING CONVEYORS CV-02A,CV-02B AND TRANSFER
3
TOWERS TT-2A, TT-2B
3.06 Dust Supression 291.30 0.112%
c Dust Supression : Installation 291.30 0.112% 2-Nov-09 30-Jan-10
3.07 Fire Protection 1,459.56 0.564%
c Piping Works - install 1,030.28 0.398% 2-Nov-09 30-Jan-10
e Fixtures - install 429.28 0.166% 1-Jan-10 30-Jan-10
3.08 Sundries 564.53 0.218%
c Sundries - install 564.53 0.218% 2-Dec-09 30-Jan-10
Sub Total 3 2,315.39 0.89%
STACKER CONVEYORS CV-03A, CV-03B, TRESTLES AND
4
TRIPPERS
4.06 Fire Protection 2,527.84 0.976%
Page 5 of 24
DESIGN, CONSTRUCTION AND COMMISSIONING OF
COAL HANDLING FACILITIES AT CIGADING INTERNATIONAL BULK TERMIN
PIPING WORK PROGRESS
PT. KRAKATAU ENGINEERING PT. CIGADING INTERNATIONAL BULK TERMINAL
WEEK / PERIOD OF
CONTRACT SCHEDULE
ITEM No. DESCRIPTION
WEIGHT
VALUE (US$) START FINISH
FACTOR
c Piping Works - install 1,784.36 0.689% 29-Sep-09 28-Feb-10
e Fixtures - install 743.48 0.287% 29-Oct-09 28-Feb-10
Sub Total 4 2,527.84 0.98%
5 STOCKYARD
5.02 Drainage Channels, Piping 24,007.45 9.269%
d Piping Works 24,007.45 9.269% 3-Jun-09 31-Aug-09
5.03 Settling Pond 73,692.82 28.453%
c Piping and Lining 73,692.82 28.453% 1-Jun-09 2-Sep-09
5.05 Fire Fighting 16,630.41 6.421%
Piping and Pumps : Installation 16,630.41 6.421% 1-Oct-09 28-Feb-10
5.07 Sundries 5,365.59 2.072%
a Sundries - install 5,365.59 2.072% 2-Aug-09 29-Dec-09
Sub Total 5 119,696.28 46.21%
6 RECLAIM SYSTEM, CONVEYOR CV-04 AND TRANSFER TOWER TT-3
6.06 Dust Supression 107.58 0.042%
Dust Supression : Installation 107.58 0.042% 29-Aug-09 26-Feb-10
6.07 Fire Protection 2,010.95 0.776%
Piping Works - install 1,419.49 0.548% 30-Sep-09 27-Feb-10
Fixtures - install 591.46 0.228% 30-Nov-09 27-Feb-10
Sub Total 6 2,118.53 0.82%
7 OUTGOING CONVEYOR CV-05 AND TRANSFER TOWER TT-4
7.07 Dust Supression 71.72 0.028%
Dust Supression : Installation 71.72 0.028% 1-Oct-09 27-Feb-10
7.08 Fire Protection 1,034.47 0.399%
Piping Works - install 730.21 0.282% 1-Oct-09 27-Feb-10
Fixtures - install 304.25 0.117% 1-Oct-09 27-Feb-10
7.09 Sundries 309.87 0.120%
Sundries - install 309.87 0.120% 1-Oct-09 27-Feb-10
Sub Total 7 1,416.06 0.55%
Page 6 of 24
DESIGN, CONSTRUCTION AND COMMISSIONING OF
COAL HANDLING FACILITIES AT CIGADING INTERNATIONAL BULK TERMIN
PIPING WORK PROGRESS
PT. KRAKATAU ENGINEERING PT. CIGADING INTERNATIONAL BULK TERMINAL
WEEK / PERIOD OF
CONTRACT SCHEDULE
ITEM No. DESCRIPTION
WEIGHT
VALUE (US$) START FINISH
FACTOR
8 OUTGOING CONVEYORS CV-06, CV-07, TRANSFER TOWER TT-5
8.04 Dust Supression 757.43 0.292%
Dust Supression : Installation 757.43 0.292% 1-Oct-09 27-Feb-10
8.05 Fire Protection 3,660.51 1.413%
Piping Works - install 2,583.89 0.998% 1-Oct-09 27-Feb-10
Fixtures - install 1,076.62 0.416% 1-Oct-09 27-Feb-10
8.06 Sundries 2,117.92 0.818%
Sundries - install 2,117.92 0.818% 1-Oct-09 27-Feb-10
Sub Total 8 6,535.86 2.52%
9 SHIP LOADER
9.05 Sundries 8,688.29 3.355%
Sundries - install 8,688.29 3.355% 1-Oct-09 27-Feb-10
Sub Total 9 8,688.29 3.35%
11 MISCELLANEOUS
11.01 Control Centre Building 47,989.99 18.529%
g Plumbing Works 47,989.99 18.529% 31-Aug-09 29-Oct-09
11.03 Water Storage, Pumps and Connections 29,171.85 11.263%
Piping Works - install 12,011.94 4.638% 31-Aug-09 29-Nov-09
Storage Tank - install 8,579.96 3.313% 31-Aug-09 29-Nov-09
Water Pumps - Install 5,147.97 1.988% 5-Oct-09 2-Jan-10
Pipe Connections - install 3,431.98 1.325% 31-Aug-09 29-Nov-09
Subtotal 11 77,161.84 29.79%
TOTAL 259,001.94 100.00%
SCHEDULE
ACCUMULATIVE SCHEDULE
PROGRESS
ACCUMULATIVE PROGRESS
VARIANCE
Page 7 of 24
DESIGN, CONSTRUCTION AND COMMISSIONING OF
COAL HANDLING FACILITIES AT CIGADING INTERNATIONAL BULK TERMINAL - STAGE 1
MECHANICAL WORK PROGRESS
PT. KRAKATAU ENGINEERING PT. CIGADING INTERNATIONAL BULK TERMINAL
WEEK / PERIOD OF : 43 DATE AS : Aug 11 - Aug 17, 2009
Page 8 of 24
DESIGN, CONSTRUCTION AND COMMISSIONING OF
COAL HANDLING FACILITIES AT CIGADING INTERNATIONAL BULK TERMINAL - STAGE 1
MECHANICAL WORK PROGRESS
PT. KRAKATAU ENGINEERING PT. CIGADING INTERNATIONAL BULK TERMINAL
WEEK / PERIOD OF : 43 DATE AS : Aug 11 - Aug 17, 2009
Page 9 of 24
DESIGN, CONSTRUCTION AND COMMISSIONING OF
COAL HANDLING FACILITIES AT CIGADING INTERNATIONAL BULK TERMINAL - STAGE 1
CIVIL WORK PROGRESS
PT. KRAKATAU ENGINEERING PT. CIGADING INTERNATIONAL BULK TERMINAL
WEEK / PERIOD OF : 43 DATE AS : Aug 11 - Aug 17, 2009
Page 10 of 24
DESIGN, CONSTRUCTION AND COMMISSIONING OF
COAL HANDLING FACILITIES AT CIGADING INTERNATIONAL BULK TERMINAL - STAGE 1
CIVIL WORK PROGRESS
PT. KRAKATAU ENGINEERING PT. CIGADING INTERNATIONAL BULK TERMINAL
WEEK / PERIOD OF : 43 DATE AS : Aug 11 - Aug 17, 2009
Page 11 of 24
DESIGN, CONSTRUCTION AND COMMISSIONING OF
COAL HANDLING FACILITIES AT CIGADING INTERNATIONAL BULK TERMINAL - STAGE 1
PT. KRAKATAU ENGINEERING PT. CIGADING INTERNATIONAL BULK TERMINAL Baseline Schedule & S - Curve for Physical Progress CONSTRUCTION
CONTRACT SCHEDULE 2008 2009 2010 2011
ITEM No. DESCRIPTION AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL August SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC JAN FEB Total
WEIGHT PLAN / DUR 9
START FINISH
FACTOR ACTUAL (MONTH) 0 1 2 3 4 5 6 7 8 10 11 10/8 17/8 24/8 31/8 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
3/5 10/5 17/5 24/5 31/5
1 BARGE WHARF
Design Only of :
1.06 Fire Fighting 0.095% PLAN 8 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.09%
ACTUAL 0.00% 0.00%
a Piping Works Install 0.067% 1-May-09 29-Jun-09 PLAN 2 0.007% 0.007% 0.007% 0.007% 0.007% 0.008% 0.008% 0.008% 0.008% 0.067%
ACTUAL
b Fixtures Installation 0.028% 1-May-09 29-Jun-09 PLAN 2 0.003% 0.003% 0.003% 0.003% 0.003% 0.003% 0.003% 0.003% 0.003% 0.028%
ACTUAL
Provide attendance on and all necessary coordination with barge Wharf
1.11 0.315% PLAN 1 0.063% 0.063% 0.063% 0.063% 0.063% 0.315%
contract contruction supervision personnel
ACTUAL
Sub total 1 0.410% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.07% 0.07% 0.07% 0.07% 0.07% 0.01% 0.01% 0.01% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.41%
ACTUAL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2.02 Hoppers 1.461% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.07% 0.07% 0.54% 0.54% 0.08% 0.08% 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.46%
ACTUAL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
a Structural Supports for Hoppers-install 0.261% 1-Sep-09 31-Dec-09 PLAN 4 0.065% 0.065% 0.065% 0.065% 0.261%
ACTUAL
b Material Hoppers-install 1.199% 2-Nov-09 31-Mar-10 PLAN 5 0.473% 0.473% 0.084% 0.084% 0.084% 1.199%
ACTUAL
2.03 Skid-Steer Loaders ( Omitted )
2.04 Equipment foundations 1.691% PLAN 12 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.18% 0.18% 0.04% 0.04% 0.04% 0.04% 0.04% 0.09% 0.09% 0.09% 0.09% 0.09% 0.31% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.69%
ACTUAL
a Piling Works 0.534% 1-Mar-09 31-May-09 PLAN 3 0.178% 0.178% 0.036% 0.036% 0.036% 0.036% 0.036% 0.534%
ACTUAL
b Reinforcement Bars 0.356% 1-Jun-09 30-Jun-09 PLAN 1 0.089% 0.089% 0.089% 0.089% 0.356%
ACTUAL
c Form Work 0.178% 1-Jul-09 30-Aug-09 PLAN 2 0.089% 0.178%
ACTUAL
d Reinforced Concrete 0.623% 1-Aug-09 30-Sep-09 PLAN 2 0.312% 0.623%
ACTUAL
2.05 Foundations to CV-01, TT-1 0.645% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.08% 0.02% 0.02% 0.02% 0.02% 0.02% 0.01% 0.01% 0.01% 0.01% 0.16% 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.65%
ACTUAL
a Pilling Works 0.170% 1-Mar-09 29-May-09 PLAN 2 0.085% 0.017% 0.017% 0.017% 0.017% 0.017% 0.170%
ACTUAL
b Excavation 0.020% 30-May-09 29-Jun-09 PLAN 1 0.005% 0.005% 0.005% 0.005% 0.020%
ACTUAL
c Learn Concrete 0.014% 31-May-09 30-Jun-09 PLAN 1 0.003% 0.003% 0.003% 0.003% 0.014%
ACTUAL
d Reinforcement Bars 0.136% 1-Jul-09 31-Jul-09 PLAN 1 0.136% 0.136%
ACTUAL
e Form Work 0.054% 1-Jul-09 31-Aug-09 PLAN 2 0.027% 0.054%
ACTUAL
f Reinforced Concrete 0.238% 1-Aug-09 30-Sep-09 PLAN 2 0.119% 0.238%
ACTUAL
g Backfilling 0.014% 1-Sep-09 30-Sep-09 PLAN 1 0.014% 0.014%
ACTUAL
2.06 Structures and Enclosures to CV-01, TT-1 0.414% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.09% 0.09% 0.11% 0.11% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.41%
ACTUAL
a Structures for Transfer Tower TT-01-install 0.109% 1-Sep-09 31-Dec-09 PLAN 4 0.027% 0.027% 0.027% 0.027% 0.109%
ACTUAL
b Structures for Supporting Towers-install 0.022% 1-Sep-09 31-Dec-09 PLAN 4 0.005% 0.005% 0.005% 0.005% 0.022%
ACTUAL
c Structures for Conveyor (CV-01)-install 0.240% 3-Oct-09 29-Jan-10 PLAN 4 0.060% 0.060% 0.060% 0.060% 0.240%
ACTUAL
d Enclosure for Conveyor (CV-01)-install 0.044% 1-Nov-09 29-Jan-10 PLAN 3 0.015% 0.015% 0.015% 0.044%
ACTUAL
2.07 Conveyor CV-01 0.475% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.12% 0.12% 0.12% 0.12% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.47%
ACTUAL
a Mechanical Component : Installation 0.335% 1-Dec-09 31-Mar-10 PLAN 4 0.084% 0.084% 0.084% 0.084% 0.335%
ACTUAL
b Belt Conveyors (CV-02A,CV-02B) : Installation 0.140% 1-Jan-10 31-Mar-10 PLAN 4 0.035% 0.035% 0.035% 0.035% 0.140%
ACTUAL
2.08 Dust Supression
2.09 Fire Protection 0.055% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.02% 0.02% 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.06%
ACTUAL
a Piping Works- install 0.039% 30-Nov-09 28-Feb-10 PLAN 3 0.013% 0.013% 0.013% 0.039%
ACTUAL
b Fixtures- install 0.016% 15-Jan-10 28-Feb-10 PLAN 3 0.005% 0.005% 0.005% 0.016%
ACTUAL
2.10 Metal Detector 0.010% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.010%
ACTUAL
a Metal Detector - installation 0.010% 30-Nov-09 27-Feb-10 PLAN 4 0.003% 0.003% 0.003% 0.003% 0.010%
ACTUAL
2.11 Magnetic Separator 0.074% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.02% 0.02% 0.02% 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.074%
ACTUAL
a Magnetic Separator : Installatio 0.074% 30-Nov-09 27-Feb-10 PLAN 4 0.019% 0.019% 0.019% 0.019% 0.074%
ACTUAL
2.12 Sundries 0.004% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.004%
ACTUAL
a Sundries - install 0.004% 1-Jan-10 1-Mar-10 PLAN 3 0.001% 0.001% 0.001% 0.004%
ACTUAL
Sub Total 2 13.22% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.18% 0.26% 0.05% 0.05% 0.05% 0.05% 0.05% 0.10% 0.10% 0.10% 0.10% 0.25% 0.60% 0.16% 0.67% 0.80% 0.26% 0.24% 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.10% 2.10% 2.10% 2.10% 0.00% 13.22%
ACTUAL
4.06 Fire Protection 0.028% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.01% 0.01% 0.01% 0.01% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.03%
ACTUAL
c Piping Works - install 0.020% 29-Sep-09 28-Feb-10 PLAN 5 0.004% 0.004% 0.004% 0.004% 0.004% 0.020%
ACTUAL
e Fixtures - install 0.008% 29-Oct-09 28-Feb-10 PLAN 5 0.002% 0.002% 0.002% 0.002% 0.002% 0.008%
ACTUAL
4.07 Sundries
Sub Total 4 8.77% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.45% 0.12% 0.12% 0.12% 0.12% 0.12% 0.10% 0.10% 0.10% 0.10% 0.51% 0.71% 1.01% 1.37% 1.37% 1.12% 0.25% 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 8.77%
5 STOCKYARD
5.01 Ground Improvement ( Omitted )
5.02 Drainage Channels, Piping 1.273% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.67% 0.06% 0.01% 0.01% 0.01% 0.01% 0.01% 0.04% 0.04% 0.04% 0.04% 0.15% 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.27%
ACTUAL
b Earthworks 0.670% 2-Mar-09 31-Mar-09 PLAN 1 0.670% 0.670%
ACTUAL
c Drainage Works 0.335% 1-Apr-09 31-Aug-09 PLAN 6 0.056% 0.011% 0.011% 0.011% 0.011% 0.011% 0.014% 0.014% 0.014% 0.014% 0.056% 0.056% 0.335%
ACTUAL
d Piping Works 0.268% 3-Jun-09 31-Aug-09 PLAN 3 0.022% 0.022% 0.022% 0.022% 0.089% 0.268%
ACTUAL
5.03 Settling Pond 1.421% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.12% 0.02% 0.02% 0.02% 0.02% 0.02% 0.10% 0.10% 0.10% 0.10% 0.39% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.42%
b Earthworks 0.598% 1-Apr-09 31-Aug-09 PLAN 5 0.120% 0.024% 0.024% 0.024% 0.024% 0.024% 0.030% 0.030% 0.030% 0.030% 0.120% 0.598%
ACTUAL
c Piping and Lining 0.823% 1-Jun-09 2-Sep-09 PLAN 3 0.069% 0.069% 0.069% 0.069% 0.274% 0.823%
ACTUAL
5.04 Dust Supression
5.05 Fire Fighting 0.186% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.04% 0.04% 0.04% 0.04% 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.19%
ACTUAL
Piping and Pumps : Installation 0.186% 1-Oct-09 28-Feb-10 PLAN 5 0.037% 0.037% 0.037% 0.037% 0.037% 0.186%
ACTUAL
5.06 Area Lighting 0.163% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.03% 0.03% 0.03% 0.03% 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.16%
ACTUAL
Ducting and Cabling - install 0.134% 1-Oct-09 26-Feb-10 PLAN 5 0.027% 0.027% 0.027% 0.027% 0.027% 0.134%
ACTUAL
Fixtures - install 0.029% 1-Oct-09 27-Feb-10 PLAN 5 0.006% 0.006% 0.006% 0.006% 0.006% 0.029%
ACTUAL
5.07 Sundries 0.509% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.07% 0.01% 0.01% 0.01% 0.01% 0.01% 0.02% 0.02% 0.02% 0.02% 0.07% 0.09% 0.01% 0.01% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.51%
ACTUAL
b Sundries - Proc 0.449% 1-Apr-09 30-Sep-09 PLAN 6 0.075% 0.015% 0.015% 0.015% 0.015% 0.015% 0.019% 0.019% 0.019% 0.019% 0.075% 0.075% 0.449%
ACTUAL
Sundries - install 0.060% 2-Aug-09 29-Dec-09 PLAN 5 0.012% 0.012% 0.012% 0.012% 0.060%
ACTUAL
Sub Total 5 3.55% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.67% 0.25% 0.05% 0.05% 0.05% 0.05% 0.05% 0.15% 0.15% 0.15% 0.15% 0.61% 0.14% 0.08% 0.08% 0.08% 0.07% 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 3.55%
Sub Total 6 6.36% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.04% 0.21% 0.10% 0.10% 0.10% 0.10% 0.10% 0.09% 0.09% 0.09% 0.09% 0.75% 0.97% 0.43% 0.49% 0.49% 0.45% 0.36% 0.33% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 6.36%
0.12%
7 OUTGOING CONVEYOR CV-05 AND TRANSFER TOWER TT-4
7.01 Foundation to CV-05, TT-4 0.322% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.04% 0.01% 0.01% 0.01% 0.01% 0.01% 0.00% 0.00% 0.00% 0.00% 0.08% 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.32%
ACTUAL 0.05%
b Pilling Works for TT-4 0.085% 3-Apr-09 1-Jun-09 PLAN 2 0.042% 0.008% 0.008% 0.008% 0.008% 0.008% 0.085%
ACTUAL 0.054%
c Excavation 0.010% 2-Jun-09 1-Jul-09 PLAN 1 0.003% 0.003% 0.003% 0.003% 0.010%
ACTUAL
d Learn Concrete 0.007% 2-Jun-09 1-Jul-09 PLAN 1 0.002% 0.002% 0.002% 0.002% 0.007%
ACTUAL
e Reinforcement Bars 0.068% 2-Jul-09 31-Jul-09 PLAN 1 0.068% 0.068%
ACTUAL
f Form Work 0.027% 2-Jul-09 30-Aug-09 PLAN 2 0.014% 0.027%
ACTUAL
g Reinforced Concrete 0.119% 1-Aug-09 29-Sep-09 PLAN 2 0.059% 0.119%
ACTUAL
h Backfilling 0.007% 31-Aug-09 29-Sep-09 PLAN 1 0.007% 0.007%
ACTUAL
7.02 Structures and Enclosures to CV-05, Transfer Tower TT-4 0.245% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.05% 0.07% 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.24%
ACTUAL
Structures for Supporting Towers - install 0.051% 2-Aug-09 1-Dec-09 PLAN 4 0.013% 0.013% 0.013% 0.051%
ACTUAL
Structures for Conveyors (CV-05) - install 0.142% 2-Aug-09 1-Dec-09 PLAN 4 0.035% 0.035% 0.035% 0.142%
ACTUAL
Enclosures for Conveyors (CV-05) - install 0.051% 3-Oct-09 1-Dec-09 PLAN 2 0.026% 0.026% 0.051%
ACTUAL
7.03 Structural Modification, Refurbishment to existing conveyor structure 0.238% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.03% 0.03% 0.03% 0.01% 0.01% 0.01% 0.01% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.03% 0.03% 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.24%
19-Jan-09 ACTUAL 0.06% 0.05% 0.03%
b Existing Conveyor Structure : Demolition 0.136% 30-Jan-09 31-May-09 PLAN 4 0.034% 0.034% 0.034% 0.007% 0.007% 0.007% 0.007% 0.007% 0.136%
19-Jan-09 ACTUAL 0.059% 0.050% 0.026% 0.136%
Existing Conveyor Structure : install 0.102% 30-Aug-09 27-Nov-09 PLAN 4 0.025% 0.025% 0.025% 0.102%
7.04 Conveyor CV-05 0.380% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.38%
Mechanical Component : Installation 0.268% 3-Oct-09 2-Apr-10 PLAN 6 0.045% 0.045% 0.045% 0.045% 0.045% 0.045% 0.268%
Belt Conveyors (CV-05) : Installation 0.112% 1-Oct-09 31-Mar-10 PLAN 6 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.112%
7.05 Belt Weight Station 0.057% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.01% 0.01% 0.01% 0.01% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.06%
Belt Weight Station : Installation 0.057% 3-Oct-09 1-Mar-10 PLAN 5 0.011% 0.011% 0.011% 0.011% 0.011% 0.057%
7.06 Sampling Station 0.598% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.12% 0.12% 0.12% 0.12% 0.12% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.60%
Sampling Station : Installation 0.598% 30-Sep-09 26-Feb-10 PLAN 5 0.120% 0.120% 0.120% 0.120% 0.120% 0.598%
7.07 Dust Supression 0.001% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Dust Supression : Installation 0.001% 1-Oct-09 27-Feb-10 PLAN 5 0.000% 0.000% 0.000% 0.000% 0.000% 0.001%
7.08 Fire Protection 0.012% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.01%
Piping Works - install 0.008% 1-Oct-09 27-Feb-10 PLAN 5 0.002% 0.002% 0.002% 0.002% 0.002% 0.008%
Fixtures - install 0.003% 1-Oct-09 27-Feb-10 PLAN 5 0.001% 0.001% 0.001% 0.001% 0.001% 0.003%
7.09 Sundries 0.003% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.003%
Sundries - install 0.003% 1-Oct-09 27-Feb-10 PLAN 5 0.001% 0.001% 0.001% 0.001% 0.001% 0.003%
Sub Total 7 1.85% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.03% 0.03% 0.08% 0.02% 0.02% 0.02% 0.02% 0.02% 0.00% 0.08% 0.14% 0.30% 0.30% 0.20% 0.20% 0.20% 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.85%
0.06% 0.05% 0.08%
Sub Total 8 5.91% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.48% 0.48% 0.63% 0.13% 0.13% 0.13% 0.13% 0.13% 0.06% 0.26% 0.66% 0.59% 0.46% 0.25% 0.25% 0.25% 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.91%
ACTUAL 0.92% 0.46% 0.61%
9 SHIP LOADER
9.01 Shiploader 10.273% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 3.42% 3.42% 3.42% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.27%
ACTUAL
c Installation 10.273% 1-May-10 30-Jul-10 PLAN 3 3.424% 3.424% 3.424% 10.273%
ACTUAL
9.02 Modification to rails and buffers 0.030% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.03%
ACTUAL
b Modification Works 0.030% 29-May-09 29-Nov-09 PLAN 6 0.001% 0.001% 0.001% 0.001% 0.005% 0.005% 0.005% 0.005% 0.030%
9.03 Tie-downs
9.04 Dust Supression
9.05 Sundries 0.097% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.02% 0.02% 0.02% 0.02% 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.10%
ACTUAL
Sundries - install 0.097% 1-Oct-09 27-Feb-10 PLAN 5 0.02% 0.02% 0.02% 0.02% 0.02% 0.097%
ACTUAL
Sub Total 9 10.40% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.02% 0.02% 0.02% 0.02% 0.02% 0.00% 0.00% 3.42% 3.42% 3.42% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.40%
Sub Total 10 0.25% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.08% 0.08% 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.25%
11 MISCELLANEOUS
11.01 Control Centre Building 8.171% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.54% 0.11% 0.11% 0.11% 0.11% 0.11% 0.13% 0.13% 0.13% 0.13% 1.07% 1.61% 1.34% 0.67% 0.27% 0.27% 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 8.17%
ACTUAL
b Substructure works 1.072% 1-Apr-09 30-May-09 PLAN 2 0.54% 0.107% 0.107% 0.107% 0.107% 0.107% 1.072%
ACTUAL
c Superstructure 1.607% 31-May-09 30-Aug-09 PLAN 3 0.134% 0.134% 0.134% 0.134% 0.54% 1.607%
ACTUAL
d Roofing Works 1.072% 2-Jul-09 30-Aug-09 PLAN 2 0.54% 1.072%
ACTUAL
e Partitionings 0.938% 31-Aug-09 29-Sep-09 PLAN 1 0.94% 0.938%
ACTUAL
f Finishings 1.340% 30-Sep-09 28-Nov-09 PLAN 2 0.67% 0.67% 1.340%
ACTUAL
g Plumbing Works 0.536% 31-Aug-09 29-Oct-09 PLAN 2 0.27% 0.27% 0.536%
ACTUAL
h Electrical Works 0.804% 31-Aug-09 29-Oct-09 PLAN 2 0.40% 0.40% 0.804%
ACTUAL
j Equipment Install 0.804% 30-Nov-09 27-Feb-10 PLAN 3 0.27% 0.27% 0.27% 0.804%
ACTUAL
11.02 Stores 0.393% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.03% 0.07% 0.07% 0.03% 0.03% 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.39%
ACTUAL
b Substructure and Floor Slabs 0.083% 1-May-09 29-Jul-09 PLAN 3 0.006% 0.006% 0.006% 0.006% 0.006% 0.007% 0.007% 0.007% 0.007% 0.028% 0.083%
ACTUAL
c Superstructure 0.124% 30-Jul-09 27-Oct-09 PLAN 3 0.041% 0.041% 0.124%
ACTUAL
d Partitionings 0.083% 30-Jul-09 27-Oct-09 PLAN 3 0.028% 0.028% 0.083%
ACTUAL
e Finishes 0.103% 28-Oct-09 26-Dec-09 PLAN 3 0.03% 0.03% 0.03% 0.103%
ACTUAL
11.03 Water Storage, Pumps and Connections 0.326% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.09% 0.11% 0.11% 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.33%
ACTUAL
Piping Works - install 0.134% 31-Aug-09 29-Nov-09 PLAN 3 0.04% 0.04% 0.04% 0.134%
ACTUAL
Storage Tank - install 0.096% 31-Aug-09 29-Nov-09 PLAN 3 0.03% 0.03% 0.03% 0.096%
ACTUAL
Water Pumps - Install 0.057% 5-Oct-09 2-Jan-10 PLAN 3 0.02% 0.02% 0.02% 0.057%
ACTUAL
Pipe Connections - install 0.038% 31-Aug-09 29-Nov-09 PLAN 3 0.01% 0.01% 0.01% 0.038%
ACTUAL
11.04 Electrical Sub-stations 25.608% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.27% 0.25% 0.25% 0.25% 0.25% 0.25% 0.32% 0.32% 0.32% 0.32% 3.19% 4.62% 2.10% 2.10% 2.10% 4.49% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 25.61%
ACTUAL
b Substructure and Floor Slabs 3.822% 30-Mar-09 27-Jun-09 PLAN 3 1.27% 0.255% 0.255% 0.255% 0.255% 0.255% 0.319% 0.319% 0.319% 0.319% 3.822%
ACTUAL
c Superstructure 5.733% 28-Jun-09 25-Sep-09 PLAN 3 1.91% 1.91% 5.733%
ACTUAL
d Finished 3.822% 28-Jun-09 25-Sep-09 PLAN 3 1.27% 1.27% 3.822%
ACTUAL
e Ducting and Cabling 5.733% 26-Sep-09 24-Dec-09 PLAN 4 1.43% 1.43% 1.43% 1.43% 5.733%
ACTUAL
Equipment - install 2.676% 1-Oct-09 28-Jan-10 PLAN 4 0.67% 0.67% 0.67% 0.67% 2.676%
ACTUAL
g Testing and Commissioning 3.822% 30-Dec-09 28-Jan-10 PLAN 1 3.8% 3.822%
ACTUAL
11.05 Perimeter Walling and Gates 0.043% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.01% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.04%
ACTUAL
b Wailing Works 0.043% 28-Feb-09 30-Jul-09 PLAN 5 0.01% 0.01% 0.002% 0.002% 0.002% 0.002% 0.002% 0.002% 0.002% 0.002% 0.002% 0.01% 0.043%
ACTUAL
11.06 Access Road 9.672% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.76% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 1.78% 1.27% 0.76% 1.02% 1.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 9.67%
ACTUAL
b Preperation of Subgrade 1.527% 1-Apr-09 31-May-09 PLAN 2 0.76% 0.153% 0.153% 0.153% 0.153% 0.153% 1.527%
ACTUAL
c Sand Binding 0.509% 2-May-09 30-Jul-09 PLAN 1 0.102% 0.102% 0.102% 0.102% 0.102% 0.509%
ACTUAL
d Crusher Run 2.036% 1-Jul-09 28-Sep-09 PLAN 2 0.255% 0.255% 0.255% 0.255% 1.02% 2.036%
ACTUAL
e Drainage and Road Kerbs 1.527% 30-Aug-09 27-Nov-09 PLAN 2 0.76% 1.527%
ACTUAL
f Bitumen Tack Coat 0.509% 29-Sep-09 27-Dec-09 PLAN 1 0.51% 0.509%
ACTUAL
g Binding Course 1.527% 29-Oct-09 26-Jan-10 PLAN 2 0.76% 0.76% 1.527%
ACTUAL
h Wearing Course 2.036% 28-Nov-09 25-Feb-10 PLAN 2 1.02% 1.02% 2.036%
ACTUAL
11.07 Sundries
11.08 Standby power generation 0.785% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.07% 0.07% 0.22% 0.22% 0.22% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.79%
ACTUAL
Enclosure - Install 0.092% 3-Aug-09 31-Oct-09 PLAN 2 0.05% 0.05% 0.092%
ACTUAL
Diesel Tank - install 0.046% 3-Aug-09 31-Oct-09 PLAN 2 0.02% 0.02% 0.046%
ACTUAL
Equipment - install 0.647% 3-Nov-09 31-Jan-10 PLAN 3 0.22% 0.22% 0.22% 0.647%
ACTUAL
Subtotal 11 45.00% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.01% 2.58% 0.62% 0.62% 0.62% 0.62% 0.62% 0.72% 0.72% 0.72% 0.72% 6.07% 7.73% 4.45% 4.15% 3.66% 5.01% 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 45.00%
ACTUAL
SUB TOTAL 100.00% PLAN 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.52% 1.41% 4.67% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.28% 8.78% 11.64% 7.72% 8.22% 7.35% 7.72% 1.98% 1.05% 0.00% 3.42% 3.42% 3.42% 0.00% 0.00% 2.10% 2.10% 2.10% 2.10% 0.00% 100.00%
ACTUAL 0.00% 0.00% 0.00% 0.00% 0.00% 0.98% 0.51% 0.82% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SCHEDULE 100% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.52% 1.41% 4.67% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.22% 1.28% 8.78% 11.6% 7.7% 8.22% 7.35% 7.72% 1.98% 1.05% 0.00% 3.42% 3.42% 3.42% 0.00% 0.00% 2.10% 2.10% 2.10% 2.10% 0.00% 100%
ACCUMULATIVE SCHEDULE 0.0% 0.0% 0.0% 0.0% 0.0% 0.00% 0.52% 1.93% 6.60% 7.82% 9.0% 10.2% 11.5% 12.7% 13.9% 15.1% 16.3% 17.61% 26.4% 28.66% 30.93% 33.20% 35.5% 47.1% 54.8% 63.1% 70.4% 78.1% 80.1% 81.2% 81.2% 84.6% 88.0% 91.4% 91.4% 91.4% 93.5% 95.6% 97.7% 99.8% 100%
PROGRESS 100% 0.00% 0.00% 0.00% 0.00% 0.00% 0.98% 0.51% 0.82% #REF!
ACCUMULATIVE PROGRESS 0.0% 0.0% 0.0% 0.0% 0.0% 1.0% 1.5% 2.31% #REF!
VARIANCE 0.0% 0.0% 0.0% 0.0% 0.0% 1.0% 1.0% 0.37% #REF!
PT. KRAKATAU ENGINEERING PT. CIGADING INTERNATIONAL BULK TERMINAL CHART OF CONSTRUCTION PROGRESS COMPARISON
DATE AS : Aug 11 - Aug 17, 2009
CONTRACT SCHEDULE 2008 2009 2010 2011
AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC JAN FEB
ITEM No. DESCRIPTION WEIGHT PLAN / Total
START FINISH 9 10 11
FACTOR ACTUAL 0 1 2 3 4 5 6 7 8 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
3/5 10/5 17/5 24/5 31/5 7/6 14/6 21/6 28/6 5/7 12/7 19/7 26/7
1 BARGE WHARF
Design Only of :
1.06 Fire Fighting 0.095% PLAN 10% 20% 30% 40% 50% 63% 75% 88% 100% 0.09%
ACTUAL 0%
a Piping Works Install 0.067% 1-May-09 29-Jun-09 PLAN 10% 20% 30% 40% 50% 63% 75% 88% 100% 0.07%
ACTUAL 0%
b Fixtures Installation 0.028% 1-May-09 29-Jun-09 PLAN 10% 20% 30% 40% 50% 63% 75% 88% 100% 0.03%
ACTUAL
Provide attendance on and all necessary coordination with barge Wharf
1.11 0.315% PLAN 20% 40% 60% 80% 100% 0.31%
contract contruction supervision personnel
ACTUAL
Sub total 1 0.410% PLAN 18% 35% 53% 71% 88% 91% 94% 97% 100% 0.41%
ACTUAL 0.00%
2.02 Hoppers 1.461% PLAN 4% 9% 46% 83% 88% 94% 100% 1.46%
ACTUAL
a Structural Supports for Hoppers-install 0.261% 1-Sep-09 31-Dec-09 PLAN 25% 50% 75% 100% 0.26%
ACTUAL
b Material Hoppers-install 1.199% 2-Nov-09 31-Mar-10 PLAN 39% 79% 86% 93% 100% 1.20%
ACTUAL
2.03 Skid-Steer Loaders ( Omitted )
2.04 Equipment foundations 1.691% PLAN 11% 21% 23% 25% 27% 29% 32% 37% 42% 47% 53% 58% 82% 100% 1.69%
ACTUAL
a Piling Works 0.534% 1-Mar-09 31-May-09 PLAN 33% 67% 73% 80% 87% 93% 100% 0.53%
ACTUAL
b Reinforcement Bars 0.356% 1-Jun-09 30-Jun-09 PLAN 25% 50% 75% 100% 0.36%
ACTUAL
c Form Work 0.178% 1-Jul-09 30-Aug-09 PLAN 50% 100% 0.18%
ACTUAL
d Reinforced Concrete 0.623% 1-Aug-09 30-Sep-09 PLAN 50% 100% 0.62%
ACTUAL
2.05 Foundations to CV-01, TT-1 0.645% PLAN 13% 16% 18% 21% 24% 26% 28% 29% 30% 32% 57% 79% 100% 0.65%
ACTUAL
a Pilling Works 0.170% 1-Mar-09 29-May-09 PLAN 50% 60% 70% 80% 90% 100% 0.17%
ACTUAL
b Excavation 0.020% 30-May-09 29-Jun-09 PLAN 25% 50% 75% 100% 0.02%
ACTUAL
c Learn Concrete 0.014% 31-May-09 30-Jun-09 PLAN 25% 50% 75% 100% 0.01%
ACTUAL
d Reinforcement Bars 0.136% 1-Jul-09 31-Jul-09 PLAN 100% 0.14%
ACTUAL
e Form Work 0.054% 1-Jul-09 31-Aug-09 PLAN 50% 100% 0.05%
ACTUAL
f Reinforced Concrete 0.238% 1-Aug-09 30-Sep-09 PLAN 50% 100% 0.24%
ACTUAL
g Backfilling 0.014% 1-Sep-09 30-Sep-09 PLAN 100% 0.01%
ACTUAL
2.06 Structures and Enclosures to CV-01, TT-1 0.414% PLAN 22% 45% 71% 96% 100% 0.41%
ACTUAL
a Structures for Transfer Tower TT-01-install 0.109% 1-Sep-09 31-Dec-09 PLAN 25% 50% 75% 100% 0.11%
ACTUAL
b Structures for Supporting Towers-install 0.022% 1-Sep-09 31-Dec-09 PLAN 25% 50% 75% 100% 0.02%
ACTUAL
c Structures for Conveyor (CV-01)-install 0.240% 3-Oct-09 29-Jan-10 PLAN 25% 50% 75% 100% 0.24%
ACTUAL
d Enclosure for Conveyor (CV-01)-install 0.044% 1-Nov-09 29-Jan-10 PLAN 33% 67% 100% 0.04%
ACTUAL
2.07 Conveyor CV-01 0.475% PLAN 25% 50% 75% 100% 0.47%
ACTUAL
a Mechanical Component : Installation 0.335% 1-Dec-09 31-Mar-10 PLAN 25% 50% 75% 100% 0.34%
ACTUAL
b Belt Conveyors (CV-02A,CV-02B) : Installation 0.140% 1-Jan-10 31-Mar-10 PLAN 25% 50% 75% 100% 0.14%
ACTUAL
2.08 Dust Supression
PT. KRAKATAU ENGINEERING PT. CIGADING INTERNATIONAL BULK TERMINAL CHART OF CONSTRUCTION PROGRESS COMPARISON
DATE AS : Aug 11 - Aug 17, 2009
CONTRACT SCHEDULE 2008 2009 2010 2011
AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC JAN FEB
ITEM No. DESCRIPTION WEIGHT PLAN / Total
START FINISH 9 10 11
FACTOR ACTUAL 0 1 2 3 4 5 6 7 8 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
3/5 10/5 17/5 24/5 31/5 7/6 14/6 21/6 28/6 5/7 12/7 19/7 26/7
ACTUAL
d Reinforcement Bars 0.327% 2-Jun-09 1-Aug-09 PLAN 13% 25% 38% 50% 100% 0.33%
ACTUAL
e Form Work 0.131% 3-Jul-09 31-Aug-09 PLAN 50% 100% 0.13%
ACTUAL
f Reinforced Concrete 0.572% 2-Aug-09 30-Sep-09 PLAN 50% 100% 0.57%
ACTUAL
g Backfilling 0.033% 2-Aug-09 30-Sep-09 PLAN 50% 100% 0.03%
ACTUAL
3.02 Structures and Enclosures to CV-02A, CV-02B, TT-2A, TT-2B 1.205% PLAN 5% 30% 61% 93% 100% 1.20%
ACTUAL
c Structures for Supporting Towers - install 0.254% 1-Aug-09 30-Nov-09 PLAN 25% 50% 75% 100% 0.25%
ACTUAL
e Structures for Conveyors (CV-02A, CV-02B) - install 0.697% 2-Sep-09 30-Nov-09 PLAN 33% 67% 100% 0.70%
ACTUAL
g Enclosures for Conveyors (CV-02A, CV-02B) - install 0.254% 2-Oct-09 31-Dec-09 PLAN 33% 67% 100% 0.25%
ACTUAL
3.03 Conveyors CV-02A, CV-02B 0.825% PLAN 20% 40% 60% 80% 100% 0.83%
ACTUAL
c Mechanical Component : Installation 0.582% 30-Sep-09 1-Mar-10 PLAN 20% 40% 60% 80% 100% 0.58%
ACTUAL
e Belt Conveyors (CV-02A, CV-02B) :Installation 0.243% 1-Jan-10 1-Mar-10 PLAN 20% 40% 60% 80% 100% 0.24%
ACTUAL
3.04 Belt Weight Station 0.056% PLAN 25% 50% 75% 100% 0.06%
ACTUAL
c Belt Weight Station :Installation 0.056% 2-Dec-09 1-Mar-10 PLAN 25% 50% 75% 100% 0.06%
ACTUAL
3.05 Sampling Station 0.598% PLAN 8% 16% 49% 75% 100% 0.60%
ACTUAL
c Sampling Station : Enclosure - install 0.141% 1-Oct-09 29-Dec-09 PLAN 33% 67% 100% 0.14%
ACTUAL
e Sampling Station :Installation 0.457% 1-Dec-09 28-Feb-10 PLAN 33% 67% 100% 0.46%
ACTUAL
3.06 Dust Supression 0.003% PLAN 33% 67% 100% 0.00%
ACTUAL
c Dust Supression : Installation 0.003% 2-Nov-09 30-Jan-10 PLAN 33% 67% 100% 0.00%
ACTUAL
3.07 Fire Protection 0.016% PLAN 24% 47% 100% 0.02%
ACTUAL
c Piping Works - install 0.012% 2-Nov-09 30-Jan-10 PLAN 33% 67% 100% 0.01%
ACTUAL
e Fixtures - install 0.005% 1-Jan-10 30-Jan-10 PLAN 100% 0.00%
ACTUAL
3.08 Sundries 0.006% PLAN 50% 100% 0.01%
ACTUAL
c Sundries - install 0.006% 2-Dec-09 30-Jan-10 PLAN 50% 100% 0.01%
ACTUAL
Sub Total 3 4.26% PLAN 0% 5% 6% 7% 9% 10% 11% 12% 13% 14% 15% 21% 31% 45% 59% 73% 84% 92% 100% 100% 4.26%
ACTUAL 6.01% 6.01% 6.01% 6.01% 6.01% 6.01% 6.01% 10.39% 10.58% 10.58%
4.06 Fire Protection 0.028% PLAN 20% 40% 60% 80% 100% 0.03%
ACTUAL
c Piping Works - install 0.020% 29-Sep-09 28-Feb-10 PLAN 20% 40% 60% 80% 100% 0.02%
ACTUAL
e Fixtures - install 0.008% 29-Oct-09 28-Feb-10 PLAN 20% 40% 60% 80% 100% 0.01%
ACTUAL
4.07 Sundries
Sub Total 4 8.77% PLAN 5% 7% 8% 9% 11% 12% 13% 14% 15% 17% 22% 31% 39% 51% 66% 82% 95% 98% 100% 8.77%
### 6.42% 9.99% 9.99% 9.99% 9.99% 9.99% 9.99% 10.95% 10.95%
5 STOCKYARD
5.01 Ground Improvement ( Omitted )
5.02 Drainage Channels, Piping 1.273% PLAN 53% 57% 58% 59% 60% 61% 61% 64% 67% 70% 73% 84% 96% 100% 1.27%
ACTUAL
b Earthworks 0.670% 2-Mar-09 31-Mar-09 PLAN 100% 0.67%
ACTUAL
PT. KRAKATAU ENGINEERING PT. CIGADING INTERNATIONAL BULK TERMINAL CHART OF CONSTRUCTION PROGRESS COMPARISON
DATE AS : Aug 11 - Aug 17, 2009
CONTRACT SCHEDULE 2008 2009 2010 2011
AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC JAN FEB
ITEM No. DESCRIPTION WEIGHT PLAN / Total
START FINISH 9 10 11
FACTOR ACTUAL 0 1 2 3 4 5 6 7 8 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
3/5 10/5 17/5 24/5 31/5 7/6 14/6 21/6 28/6 5/7 12/7 19/7 26/7
c Drainage Works 0.335% 1-Apr-09 31-Aug-09 PLAN 17% 20% 23% 27% 30% 33% 38% 42% 46% 50% 67% 83% 100% 0.34%
ACTUAL
d Piping Works 0.268% 3-Jun-09 31-Aug-09 PLAN 8% 17% 25% 33% 67% 100% 100% 0.27%
ACTUAL
5.03 Settling Pond 1.421% PLAN 8% 10% 12% 13% 15% 17% 24% 31% 38% 45% 72% 100% 1.42%
b Earthworks 0.598% 1-Apr-09 31-Aug-09 PLAN 20% 24% 28% 32% 36% 40% 45% 50% 55% 60% 80% 100% 0.60%
ACTUAL
c Piping and Lining 0.823% 1-Jun-09 2-Sep-09 PLAN 8% 17% 25% 33% 67% 100% 0.82%
ACTUAL
5.04 Dust Supression
5.05 Fire Fighting 0.186% PLAN 20% 40% 60% 80% 100% 0.19%
ACTUAL
Piping and Pumps : Installation 0.186% 1-Oct-09 28-Feb-10 PLAN 20% 40% 60% 80% 100% 0.19%
ACTUAL
5.06 Area Lighting 0.163% PLAN 20% 40% 60% 80% 100% 0.16%
ACTUAL
Ducting and Cabling - install 0.134% 1-Oct-09 26-Feb-10 PLAN 20% 40% 60% 80% 100% 0.13%
ACTUAL
Fixtures - install 0.029% 1-Oct-09 27-Feb-10 PLAN 20% 40% 60% 80% 100% 0.03%
ACTUAL
5.07 Sundries 0.509% PLAN 15% 18% 21% 24% 26% 29% 33% 37% 40% 44% 59% 76% 93% 95% 98% 100% 0.51%
ACTUAL
b Sundries - Proc 0.449% 1-Apr-09 30-Sep-09 PLAN 17% 20% 23% 27% 30% 33% 38% 42% 46% 50% 67% 83% 100% 0.45%
ACTUAL
Sundries - install 0.060% 2-Aug-09 29-Dec-09 PLAN 20% 40% 60% 80% 100% 0.06%
ACTUAL
Sub Total 5 3.55% PLAN 15% 16% 18% 19% 20% 22% 26% 30% 35% 39% 56% 74% 78% 80% 83% 85% 87% 89% 3.55%
Sub Total 6 6.36% PLAN 1% 4% 6% 7% 9% 10% 12% 13% 15% 16% 18% 30% 45% 60% 67% 74% 82% 89% 95% 100% 6.36%
1.9% 2.3% 2.3% 3.2% 3.2% 3.2% 3.2% 4.3% 4.5% 4.9% 6.5%
PT. KRAKATAU ENGINEERING PT. CIGADING INTERNATIONAL BULK TERMINAL CHART OF CONSTRUCTION PROGRESS COMPARISON
DATE AS : Aug 11 - Aug 17, 2009
CONTRACT SCHEDULE 2008 2009 2010 2011
AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC JAN FEB
ITEM No. DESCRIPTION WEIGHT PLAN / Total
START FINISH 9 10 11
FACTOR ACTUAL 0 1 2 3 4 5 6 7 8 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
3/5 10/5 17/5 24/5 31/5 7/6 14/6 21/6 28/6 5/7 12/7 19/7 26/7
7 OUTGOING CONVEYOR CV-05 AND TRANSFER TOWER TT-4
7.01 Foundation to CV-05, TT-4 0.322% PLAN 0% 13% 16% 18% 21% 24% 26% 28% 29% 30% 32% 57% 79% 100% 0.32%
ACTUAL 16.9% 23% 23% 23% 23% 23% 25% 25% 84%
b Pilling Works for TT-4 0.085% 3-Apr-09 1-Jun-09 PLAN 50% 60% 70% 80% 90% 100% 0.08%
ACTUAL 64.3% 86% 86% 86% 86% 86% 86% 86% 86%
c Excavation 0.010% 2-Jun-09 1-Jul-09 PLAN 25% 50% 75% 100% 0.01%
ACTUAL 86% 86% 86% 86%
d Learn Concrete 0.007% 2-Jun-09 1-Jul-09 PLAN 25% 50% 75% 100% 0.01%
ACTUAL 29%
e Reinforcement Bars 0.068% 2-Jul-09 31-Jul-09 PLAN 100% 0.07%
ACTUAL
f Form Work 0.027% 2-Jul-09 30-Aug-09 PLAN 50% 100% 0.03%
ACTUAL
g Reinforced Concrete 0.119% 1-Aug-09 29-Sep-09 PLAN 50% 100% 0.12%
ACTUAL
h Backfilling 0.007% 31-Aug-09 29-Sep-09 PLAN 100% 0.01%
ACTUAL
7.02 Structures and Enclosures to CV-05, Transfer Tower TT-4 0.245% PLAN 20% 39% 70% 100% 0.24%
ACTUAL
Structures for Supporting Towers - install 0.051% 2-Aug-09 1-Dec-09 PLAN 25% 50% 75% 100% 0.05%
ACTUAL
Structures for Conveyors (CV-05) - install 0.142% 2-Aug-09 1-Dec-09 PLAN 25% 50% 75% 100% 0.14%
ACTUAL
Enclosures for Conveyors (CV-05) - install 0.051% 3-Oct-09 1-Dec-09 PLAN 50% 100% 0.05%
ACTUAL
7.03 Structural Modification, Refurbishment to existing conveyor structure 0.238% PLAN 14% 29% 43% 46% 49% 51% 54% 57% 57% 57% 57% 57% 57% 68% 79% 89% 100% 0.24%
19-Jan-09 ACTUAL 25.0% 46.0% 57.1% 57.14% 57.14% 57.14% 57.14% 57.14% 57.14% 57.14% 57.14% 57.14% 57.14%
b Existing Conveyor Structure : Demolition 0.136% 30-Jan-09 31-May-09 PLAN 25% 50% 75% 80% 85% 90% 95% 100% 0.14%
19-Jan-09 19-Apr-09 ACTUAL 43.7% 80.5% 99.9% 100% 100% 100% 524.040%
Existing Conveyor Structure : install 0.102% 30-Aug-09 27-Nov-09 PLAN 25% 50% 75% 100% 0.10%
7.04 Conveyor CV-05 0.380% PLAN 17% 33% 50% 67% 83% 100% 0.38%
Mechanical Component : Installation 0.268% 3-Oct-09 2-Apr-10 PLAN 17% 33% 50% 67% 83% 100% 0.27%
Belt Conveyors (CV-05) : Installation 0.112% 1-Oct-09 31-Mar-10 PLAN 17% 33% 50% 67% 83% 100% 0.11%
7.05 Belt Weight Station 0.057% PLAN 20% 40% 60% 80% 100% 0.06%
Belt Weight Station : Installation 0.057% 3-Oct-09 1-Mar-10 PLAN 20% 40% 60% 80% 100% 0.06%
7.06 Sampling Station 0.598% PLAN 20% 40% 60% 80% 100% 0.60%
Sampling Station : Installation 0.598% 30-Sep-09 26-Feb-10 PLAN 20% 40% 60% 80% 100% 0.60%
7.07 Dust Supression 0.001% PLAN 20% 40% 60% 80% 100% 0.00%
Dust Supression : Installation 0.001% 1-Oct-09 27-Feb-10 PLAN 20% 40% 60% 80% 100% 0.00%
7.08 Fire Protection 0.012% PLAN 20% 40% 60% 80% 100% 0.01%
Piping Works - install 0.008% 1-Oct-09 27-Feb-10 PLAN 20% 40% 60% 80% 100% 0.01%
Fixtures - install 0.003% 1-Oct-09 27-Feb-10 PLAN 20% 40% 60% 80% 100% 0.00%
7.09 Sundries 0.003% PLAN 20% 40% 60% 80% 100% 0.00%
Sundries - install 0.003% 1-Oct-09 27-Feb-10 PLAN 20% 40% 60% 80% 100% 0.00%
Sub Total 7 1.85% PLAN 2% 4% 8% 9% 9% 10% 11% 12% 12% 12% 12% 12% 17% 24% 32% 48% 64% 75% 85% 96% 99% 1.85%
3.2% 5.9% 10.2% 11.07% 11.07% 11.07% 11.07% 11.07% 11.07% 11.07% 11.63% 11.63% 11.73%
PT. KRAKATAU ENGINEERING PT. CIGADING INTERNATIONAL BULK TERMINAL CHART OF CONSTRUCTION PROGRESS COMPARISON
DATE AS : Aug 11 - Aug 17, 2009
CONTRACT SCHEDULE 2008 2009 2010 2011
AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC JAN FEB
ITEM No. DESCRIPTION WEIGHT PLAN / Total
START FINISH 9 10 11
FACTOR ACTUAL 0 1 2 3 4 5 6 7 8 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
3/5 10/5 17/5 24/5 31/5 7/6 14/6 21/6 28/6 5/7 12/7 19/7 26/7
ACTUAL
8.06 Sundries 0.024% PLAN 20% 40% 60% 80% 100% 0.02%
ACTUAL
Sundries - install 0.024% 1-Oct-09 27-Feb-10 PLAN 20% 40% 60% 80% 100% 0.02%
Sub Total 8 5.91% PLAN 8% 16% 27% 29% 31% 33% 36% 38% 38% 38% 38% 39% 43% 52% 63% 73% 80% 85% 89% 93% 97% 5.91%
ACTUAL 15.56% 23.32% #REF! 42.85% 43.43% 43.79% 44.03% 50.75% 51.57% 53.75% 53.98% 57.70% 58.15%
9 SHIP LOADER
9.01 Shiploader 10.273% PLAN 33% 67% 100% 10.27%
ACTUAL
c Installation 10.273% 1-May-10 30-Jul-10 PLAN 33% 67% 100% 10.27%
ACTUAL
9.02 Modification to rails and buffers 0.030% PLAN 4% 8% 13% 17% 33% 50% 67% 83% 100% 0.03%
ACTUAL
b Modification Works 0.030% 29-May-09 29-Nov-09 PLAN 4% 8% 13% 17% 33% 50% 67% 83% 100% 0.03%
9.03 Tie-downs
9.04 Dust Supression
9.05 Sundries 0.097% PLAN 20% 40% 60% 80% 100% 0.10%
ACTUAL
Sundries - install 0.097% 1-Oct-09 27-Feb-10 PLAN 20% 40% 60% 80% 100% 0.10%
ACTUAL
Sub Total 9 10.40% PLAN 0% 0% 0% 0% 0% 0% 0% 0% 1% 1% 1% 1% 1% 1% 34% 67% 100% 10.40%
11 MISCELLANEOUS
11.01 Control Centre Building 8.171% PLAN 7% 8% 9% 10% 12% 13% 15% 16% 18% 20% 33% 46% 66% 82% 90% 93% 97% 100% 8.17%
ACTUAL
b Substructure works 1.072% 1-Apr-09 30-May-09 PLAN 50% 60% 70% 80% 90% 100% 1.07%
ACTUAL
c Superstructure 1.607% 31-May-09 30-Aug-09 PLAN 8% 17% 25% 33% 67% 100% 1.61%
ACTUAL
d Roofing Works 1.072% 2-Jul-09 30-Aug-09 PLAN 0% 0% 0% 0% 50% 100% 1.07%
ACTUAL
e Partitionings 0.938% 31-Aug-09 29-Sep-09 PLAN 100% 0.94%
ACTUAL
f Finishings 1.340% 30-Sep-09 28-Nov-09 PLAN 50% 100% 1.34%
ACTUAL
g Plumbing Works 0.536% 31-Aug-09 29-Oct-09 PLAN 50% 100% 0.54%
ACTUAL
h Electrical Works 0.804% 31-Aug-09 29-Oct-09 PLAN 50% 100% 0.80%
ACTUAL
j Equipment Install 0.804% 30-Nov-09 27-Feb-10 PLAN 33% 67% 100% 0.80%
ACTUAL
11.02 Stores 0.393% PLAN 1% 3% 4% 6% 7% 9% 11% 12% 14% 21% 39% 56% 74% 82% 91% 100% 0.39%
ACTUAL
b Substructure and Floor Slabs 0.083% 1-May-09 29-Jul-09 PLAN 7% 13% 20% 27% 33% 42% 50% 58% 67% 100% 0.08%
ACTUAL
c Superstructure 0.124% 30-Jul-09 27-Oct-09 PLAN 33% 67% 100% 0.12%
ACTUAL
d Partitionings 0.083% 30-Jul-09 27-Oct-09 PLAN 33% 67% 100% 0.08%
ACTUAL
e Finishes 0.103% 28-Oct-09 26-Dec-09 PLAN 33% 67% 100% 0.10%
ACTUAL
11.03 Water Storage, Pumps and Connections 0.326% PLAN 27% 61% 94% 100% 0.33%
ACTUAL
Piping Works - install 0.134% 31-Aug-09 29-Nov-09 PLAN 33% 67% 100% 0.13%
ACTUAL
Storage Tank - install 0.096% 31-Aug-09 29-Nov-09 PLAN 33% 67% 100% 0.10%
ACTUAL
Water Pumps - Install 0.057% 5-Oct-09 2-Jan-10 PLAN 33% 67% 100% 0.06%
ACTUAL
Pipe Connections - install 0.038% 31-Aug-09 29-Nov-09 PLAN 33% 67% 100% 0.04%
ACTUAL
11.04 Electrical Sub-stations 25.608% PLAN 5% 6% 7% 8% 9% 10% 11% 12% 14% 15% 27% 40% 58% 66% 74% 82% 100% 25.61%
ACTUAL
b Substructure and Floor Slabs 3.822% 30-Mar-09 27-Jun-09 PLAN 33% 40% 47% 53% 60% 67% 75% 83% 92% 100% 3.82%
ACTUAL
c Superstructure 5.733% 28-Jun-09 25-Sep-09 PLAN 33% 67% 100% 5.73%
ACTUAL
d Finished 3.822% 28-Jun-09 25-Sep-09 PLAN 33% 67% 100% 3.82%
ACTUAL
e Ducting and Cabling 5.733% 26-Sep-09 24-Dec-09 PLAN 25% 50% 75% 100% 5.73%
ACTUAL
Equipment - install 2.676% 1-Oct-09 28-Jan-10 PLAN 25% 50% 75% 100% 2.68%
ACTUAL
g Testing and Commissioning 3.822% 30-Dec-09 28-Jan-10 PLAN 100% 3.82%
ACTUAL
11.05 Perimeter Walling and Gates 0.043% PLAN 20% 40% 44% 48% 52% 56% 60% 65% 70% 75% 80% 100% 0.04%
ACTUAL
b Wailing Works 0.043% 28-Feb-09 30-Jul-09 PLAN 20% 40% 44% 48% 52% 56% 60% 65% 70% 75% 80% 100% 0.04%
ACTUAL
11.06 Access Road 9.672% PLAN 0% 8% 11% 13% 16% 18% 21% 24% 26% 29% 32% 50% 58% 71% 79% 89% 100% 9.67%
ACTUAL
b Preperation of Subgrade 1.527% 1-Apr-09 31-May-09 PLAN 50% 60% 70% 80% 90% 100% 1.53%
ACTUAL
c Sand Binding 0.509% 2-May-09 30-Jul-09 PLAN 20% 40% 60% 80% 100% 0.51%
ACTUAL
d Crusher Run 2.036% 1-Jul-09 28-Sep-09 PLAN 13% 25% 38% 50% 100% 2.04%
ACTUAL
e Drainage and Road Kerbs 1.527% 30-Aug-09 27-Nov-09 PLAN 50% 100% 1.53%
ACTUAL
f Bitumen Tack Coat 0.509% 29-Sep-09 27-Dec-09 PLAN 100% 0.51%
ACTUAL
PT. KRAKATAU ENGINEERING PT. CIGADING INTERNATIONAL BULK TERMINAL CHART OF CONSTRUCTION PROGRESS COMPARISON
DATE AS : Aug 11 - Aug 17, 2009
CONTRACT SCHEDULE 2008 2009 2010 2011
AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV DEC JAN FEB
ITEM No. DESCRIPTION WEIGHT PLAN / Total
START FINISH 9 10 11
FACTOR ACTUAL 0 1 2 3 4 5 6 7 8 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
3/5 10/5 17/5 24/5 31/5 7/6 14/6 21/6 28/6 5/7 12/7 19/7 26/7
g Binding Course 1.527% 29-Oct-09 26-Jan-10 PLAN 50% 100% 1.53%
ACTUAL
h Wearing Course 2.036% 28-Nov-09 25-Feb-10 PLAN 50% 100% 2.04%
ACTUAL
11.07 Sundries
11.08 Standby power generation 0.785% PLAN 9% 18% 45% 73% 100% 0.79%
ACTUAL
Enclosure - Install 0.092% 3-Aug-09 31-Oct-09 PLAN 50% 100% 0.09%
ACTUAL
Diesel Tank - install 0.046% 3-Aug-09 31-Oct-09 PLAN 50% 100% 0.05%
ACTUAL
Equipment - install 0.647% 3-Nov-09 31-Jan-10 PLAN 33% 67% 100% 0.65%
ACTUAL
Subtotal 11 45.00% PLAN 0% 6% 7% 9% 10% 11% 13% 14% 16% 18% 19% 33% 44% 61% 71% 80% 88% 100% 45.00%
ACTUAL
TOTAL 100.00% PLAN 0.0% 0.5% 1.9% 6.3% 7.5% 8.7% 9.9% 11.1% 12.4% 13.9% 15.1% 16.3% 17.6% 26.4% 35.5% 47.1% 54.8% 63.1% 70.4% 78.1% 80.1% 81.2% 81.2% 84.6% 88.0% 91.4% 91.4% 91.4% 93.5% 95.6% 97.7% 100% 100.00%
ACTUAL 0.00% 0.00% 0.00% 0.00% 0.00% 0.98% 1.49% 2.31% 3.49% 3.76% 4.15% 4.17% 4.40% 4.68% 5.15% 5.46% 5.74% 5.91% 3.49%
SCHEDULE 4.35% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.52% 1.41% 4.35% 1.22% 1.22% 1.22% 1.22% 1.22% 1.53% 1.22% 1.22% 1.28% 8.78% 9.08% 11.64% 7.72% 8.22% 7.35% 7.72% 1.98% 1.05% 0.00% 3.42% 3.42% 3.42% 0.00% 0.00% 2.10% 2.10% 2.10% 2.10% 100%
ACCUMULATIVE SCHEDULE 6.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.52% 1.93% 6.29% 7.50% 8.72% 9.93% 11.15% 12.36% 13.90% 15.11% 16.33% 17.61% 26.39% 35.48% 47.11% 54.83% 63.06% 70.40% 78.12% 80.11% 81.15% 81.15% 84.58% 88.00% 91.42% 91.42% 91.42% 93.52% 95.62% 97.72% 100%
PROGRESS 1.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.98% 0.51% 0.82% 1.19% 0.27% 0.40% 0.01% 0.23% 0.28% 0.47% 0.31% 0.28% 0.17%
ACCUMULATIVE PROGRESS 3.49% 0.00% 0.00% 0.00% 0.00% 0.00% 0.98% 1.49% 2.3% 3.49% 3.76% 4.15% 4.17% 4.40% 4.68% 5.15% 5.46% 5.74% 5.91%
VARIANCE -2.79% 0.0% 0.0% 0.0% 0.0% 0.0% 0.98% 1.0% 0.37% -2.79% -3.74% -4.56% -5.76% -6.75% -7.68% -8.75% -9.65% -10.6% -11.7%
1 BARGE WHARF
1.06 Fire Fighting #REF! #REF!
a Piping Works Install #REF! #REF! 1-May-09 29-Jun-09
b Fixtures Installation #REF! #REF! 1-May-09 29-Jun-09
Provide attendance on and all necessary
1.11 coordination with barge Wharf contract contruction #REF! #REF!
supervision personnel
Sub total 1 #REF! #REF!
BARGE UNLOADING, WHARF CONVEYOR CV-
2
01 AND TRANSFER TOWER TT-1
2.04 Equipment foundations 151,456.23 5.89% 125
a Piling Works 47,828.28 1.86% 1-Mar-09 31-May-09 125 Additional Work for KE (Ext MOM Monthly) Proposal already Issued to CIBT Waiting for CIBT Approve
b Reinforcement Bars 31,885.52 1.24% 1-Jun-09 30-Jun-09 33 Additional Work for KE (Ext MOM Monthly) Proposal already Issued to CIBT Waiting for CIBT Approve
2.05 Foundations to CV-01, TT-1 57,788.90 2.25% 125
Purchasing Order for Pile Type-2 still not yet, Drawing must be quickly approve, Order New Material as
Engineering, Procurement,
a Pilling Works 15,207.61 0.59% 1-Mar-09 29-May-09 125 No Approval Drawing Material Delivery by 1 month soon as posible, Issued Const. Method for Piling as soon
QA/QC & Project Managerment
as posible for working permit from KBS
b Excavation 1,824.91 0.07% 30-May-09 29-Jun-09 35 No Approval / IFC Drawing Drawing IFC must be quickly issued Engineering
c Learn Concrete 1,216.61 0.05% 31-May-09 30-Jun-09 34 No Approval / IFC Drawing Drawing IFC must be quickly issued Engineering
Sub Total 2 209,245.13 8.13%
INCOMING CONVEYORS CV-02A,CV-02B AND
3
TRANSFER TOWERS TT-2A, TT-2B
3.01 Foundation to CV-02A, CV-02B, TT-2A, TT-2B 138,992.67 5.40% 0.29% 18.48% 2.96% 54.84% 3.25% 60.17% 94
There are any pile was broke in
underground, need approval drawing for add Drawing IFC for additional Pile must be quickly issued to
a Pilling Works 36,577.02 1.42% 1-Apr-09 31-May-09 9-Feb-09 0.26% 62.7% 1.16% 37% 1.42% 100.0% 94
new pile. And need drawing for piling at near
Engineering
Construction/Subcont
of TT-01
b Excavation 4,389.24 0.17% 2-May-09 31-May-09 27-May-09 0.03% 62.70% 0.14% 37% 0.17% 100.0% 63
Drawing IFC must be quickly issued to
c Learn Concrete 2,926.16 0.11% 2-May-09 1-Jul-09 0.11% 100% 0.11% 100.0% 63 Weather Engineering
Construction/Subcont
Drawing IFC must be quickly issued to
d Reinforcement Bars 29,261.61 1.14% 2-Jun-09 1-Aug-09 1.10% 97% 1.10% 97.0% 32 Weather Engineering
Construction/Subcont
e Form Work 11,704.65 0.45% 3-Jul-09 31-Aug-09 0.44% 97.0% 1
Sub Total 3 138,992.67 5.40% 0.29% 6.73% 2.96% 54.84% 3.25% 60.17%
STACKER CONVEYORS CV-03A, CV-03B,
4 -
TRESTLES AND TRIPPERS
4.01 Foundation to CV-03A, CV-03B 308,316.58 11.98% 0.88% 25.46% 2.65% 4.0% 3.53% 29.47% 94
There are any pile was broke in Change with new pile, need Engineering Approval,
b Pilling Works 81,135.94 3.15% 1-Apr-09 30-May-09 9-Feb-09 0.88% 96.74% 2.27% 3% 3.15% 100.00% 94 Engineering, Procurement
underground, Additional Pile 56 point Purchasing Additional Pile
Drawing IFC must be quickly issued to
c Excavation 9,736.31 0.38% 1-May-09 30-May-09 27-May-09 0.38% 100.00% 0.00% 0.00% 0.38% 100.00% Engineering
Construction/Subcont
Drawing IFC must be quickly issued to
d Learn Concrete 6,490.88 0.25% 1-May-09 29-Jun-09 64 Engineering
Construction/Subcont
Drawing IFC must be quickly issued to
e Reinforcement Bars 64,908.75 2.52% 31-May-09 30-Jul-09 34 Engineering
Construction/Subcont
f Form Work 25,963.50 1.01% 1-Jul-09 30-Aug-09
Sub Total 4 308,316.58 11.98% 0.88% 9.99% 2.65% 22.13% 3.53% 29.47%
5 STOCKYARD
5.01 Ground Improvement ( Omitted )
5.02 Drainage Channels, Piping 90,027.95 3.50% 124
Engineering shoul be Issued IFC Drawing, Find Sub
b Earthworks 60,018.64 2.33% 2-Mar-09 31-Mar-09 124 No IFC Drawing No Subcont Engineering, Procurement
Contractor As soon as Possible
Engineering shoul be Issued IFC Drawing & Find Sub
c Drainage Works 30,009.32 1.17% 1-Apr-09 31-Aug-09 94 No IFC Drawing No Subcont Engineering, Procurement
Contractor As soon as Possible
Engineering shoul be Issued IFC Drawing, Find Sub
d Piping Works #REF! #REF! 3-Jun-09 31-Aug-09 31 No IFC Drawing No Subcont, No Material Piping Engineering, Procurement
Contractor & Purchasing Material As soon as Possible
5.03 Settling Pond 53,594.78 2.08% 94
Engineering shoul be Issued IFC Drawing As soom as
b Earthworks 53,594.78 2.08% 1-Apr-09 31-Aug-09 94 No Subcont Engineering, Procurement
Possible
Engineering shoul be Issued IFC Drawing, Find Sub
c Piping and Lining #REF! #REF! 1-Jun-09 2-Sep-09 33 No Subcont Engineering, Procurement
Contractor & Purchasin Material As soon as Possible
Sub Total 5 143,622.73 5.58%
6 RECLAIM SYSTEM, CONVEYOR CV-04 AND TRA -
6.01 Foundation, Slabs and Walling to Apron Feeders 223,036.16 8.67% 0.06% 2.37% 5.43% 60.9% 5.49% 63.32% -
b Excavation 7,043.25 0.27% 2-Mar-09 30-Apr-09 27-May-09 0.27% 100.00% 0.00% 0.00% 0.27% 100.00%
c Learn Concrete 4,695.50 0.18% 1-Apr-09 30-Apr-09 0.14% 75.00% 0.00% 0.00% 0.14% 75.00% 94 IFC Drawing should be issued as soon as possible Engineering
d Hardcore 35,216.24 1.37% 1-May-09 30-May-09 1.03% 75.00% 0.00% 0.00% 1.03% 75.00% 64 IFC Drawing should be issued as soon as possible Engineering
e Reinforcement Bars 46,954.98 1.82% 31-May-09 30-Jul-09 34 IFC Drawing should be issued as soon as possible Engineering
f Form Work 35,216.24 1.37% 1-Jul-09 30-Aug-09 3
6.02 Foundation to CV-04, TT-3 79,706.74 3.10% 0.23% 25.90% 2.37% 58.2% 2.60% 84.06% 94
b Pilling Works for TT-3 20,975.46 0.82% 1-Apr-09 1-Jun-09 9-Feb-09 0.8% 100.0% 0.0% 0.0% 0.8% 100.0% 94 Additonal Material taken from CV-01 Already Started
c Excavation 2,517.05 0.10% 2-Jun-09 1-Jul-09 27-May-09 0.1% 100.0% 0.0% 0.0% 0.1% 100.0% 32
d Learn Concrete 1,678.04 0.07% 2-Jun-09 1-Jul-09 0.0% 0.0% 0.0% 0.0% 0.1% 85.0% 32 IFC Drawing should be issued as soon as possible Engineering
e Reinforcement Bars 16,780.37 0.65% 2-Jul-09 31-Jul-09 0.0% 0.0% 0.6% 85.0% 2
f Form Work 6,712.15 0.26% 2-Jul-09 30-Aug-09 0.0% 0.0% 0.2% 82.0% 2
g Reinforced Concrete 29,365.64 1.14% 1-Aug-09 30-Aug-09 0.0% 0.0% 0.9% 76.0% (28)
h Backfilling 1,678.04 0.07% 31-Aug-09 29-Sep-09 0.0% 0.0% 0.0% 0.0% (58)
Sub Total 6 302,742.89 11.77% 0.29% 4.55% 7.80% 66.31% 8.09% 68.78%
OUTGOING CONVEYOR CV-05 AND TRANSFER
7 -
TOWER TT-4
Page 23 of 24
DESIGN, CONSTRUCTION AND COMMISSIONING OF
COAL HANDLING FACILITIES AT CIGADING INTERNATIONAL BULK TERMINAL - STAGE 1
RECOVERY FOR CONSTRUCTION PROGRESS
PROBLEM & SOLVING
WEEK / PERIOD OF : 43 DATE AS : Jun 28 - Jul 04, 2009
Page 24 of 24