Annexure-1

Project Name :- Muradnagar230/132 kV and 132/33 kV Sub-Station, (New).

(Wenner's Four Electrode Method as per IEEE Std 80)


Name of the Substation Date of Recording:-
Measured
Direction of Probe Resistivity (ρ=2
Point No. Resistance
Measurement Spacing (a) π a R)
(R)
m Ω Ω-m

E-W 0.2 28.50


22.67
E-W 5 1.21 38.03
E-W 10 0.67 42.11
E-W 20 0.6 75.43
E-W 50 0.53 166.57
ERT-1
N-S 0.2 22.11 27.80
N-S 5 1.27 39.91
N-S 10 0.72 45.26
N-S 20 0.68 85.49
N-S 50 0.55 172.86
72.20

E-W 0.2 0.00


E-W 5 0.00
E-W 10 0.00
E-W 20 0.00
E-W 50 0.00
ERT-2
N-S 0.2 0.00
N-S 5 0.00
N-S 10 0.00
N-S 20 0.00
N-S 50 0.00

0.00
Average Resistivity of Soil in Ohm-m

References:

1. IEEE Std 80 - Guide for Safety in AC Substation Grounding cl. 13.3 Soil Resistivity Measurement &
cl.13.4.1 Uniform Soil Consideration.

Page 1 of 1