Current MasterFormat Divisions (April 2014)

The current MasterFormat Divisions are:

PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP

 Division 00 — Procurement and Contracting Requirements

SPECIFICATIONS GROUP

General Requirements Subgroup

 Division 01 — General Requirements

Facility Construction Subgroup

 Division 02 — Existing Conditions (Ex. Alterations to existing natural


conditions)
 Division 03 — Concrete (Ex. Footings)
 Division 04 — Masonry (Ex. Concrete block and brick work)
 Division 05 — Metals (Ex. Steel framing)
 Division 06 — Wood, Plastics, and Composites (Ex. House framing)
 Division 07 — Thermal and Moisture Protection (Ex. Insulation and water
barriers)
 Division 08 — Openings (Ex. Doors, windows, and louvers)
 Division 09 — Finishes
 Division 10 — Specialties
 Division 11 — Equipment
 Division 12 — Furnishings
 Division 13 — Special Construction
 Division 14 — Conveying Equipment
 Division 15 — RESERVED FOR FUTURE EXPANSION
 Division 16 — RESERVED FOR FUTURE EXPANSION
 Division 17 — RESERVED FOR FUTURE EXPANSION
 Division 18 — RESERVED FOR FUTURE EXPANSION
 Division 19 — RESERVED FOR FUTURE EXPANSION

Facility Services Subgroup:

 Division 20 — RESERVED FOR FUTURE EXPANSION


 Division 21 — Fire Suppression
 Division 22 — Plumbing
 Division 23 — Heating, Ventilating, and Air Conditioning (HVAC)
 Division 24 — RESERVED FOR FUTURE EXPANSION
 Division 25 — Integrated Automation
 Division 26 — Electrical
 Division 27 — Communications
 Division 28 — Electronic Safety and Security
 Division 29 — RESERVED FOR FUTURE EXPANSION

Site and Infrastructure Subgroup:

 Division 30 — RESERVED FOR FUTURE EXPANSION


 Division 31 — Earthwork
 Division 32 — Exterior Improvements
 Division 33 — Utilities
 Division 34 — Transportation
 Division 35 — Waterway and Marine Construction
 Division 36 — RESERVED FOR FUTURE EXPANSION
 Division 37 — RESERVED FOR FUTURE EXPANSION
 Division 38 — RESERVED FOR FUTURE EXPANSION
 Division 39 — RESERVED FOR FUTURE EXPANSION
Process Equipment Subgroup:

 Division 40 — Process Interconnections


 Division 41 — Material Processing and Handling Equipment
 Division 42 — Process Heating, Cooling, and Drying Equipment
 Division 43 — Process Gas and Liquid Handling, Purification and Storage
Equipment
 Division 44 — Pollution and Waste Control Equipment
 Division 45 — Industry-Specific Manufacturing Equipment
 Division 46 — Water and Wastewater Equipment
 Division 47 — RESERVED FOR FUTURE EXPANSION
 Division 48 — Electrical Power Generation
 Division 49 — RESERVED FOR FUTURE EXPANSION