Professional Documents
Culture Documents
Well Foundations
Well Foundations
By:
R. K. Shekhawat
Sr. Professor (Projects)
IRICEN
1. History of Well Foundations
• Origin in India. Have been used for hundreds of years.
• Masonry wells were sunk for drinking water in ancient
times. Later on same technique was used for
construction of foundation wells.
• Freely used during the Mughal period, many Mughal
monuments including the Taj Mahal have well
foundations. The Mughal used well foundations for
bridges across major rivers also.
• Used for Ganga Canal at Roorkee, in the middle of 19th
century.
• In India the largest well used for main towers of
Howrah bridge. Size 24.8m x 53.5m, with maximum
depth of sinking as 31.4m below ground level.
• On Rajendra Pul across the Ganga at Mokamah:
Double D wells, 16.3m x 9.7m size and 50.3m deep.
2. Components of Well Foundation
3. Well v/s Pile Foundations
Wells Piles
Massive, Large carrying Slender is size (Normally used
capacity, Size governed by maximum size is 1.5m)
sinking consideration, Large
reserve strength
Concrete in dry condition. Bored Piles: Concrete under
Better quality achieved. Strata water.
can be inspected. Driven Piles: Though concrete is
controlled, damage during
driving cannot be inspected.
Can overcome obstruction. Driving is difficult in case of
obstruction.
Can be provided upto any depth, Theoretically no limitation, but
if open sinking to be done. not economical for depth more
Pneumatic sinking upto 33m than 30m or so.
depth.
Size cannot be reduced beyond Length of pre-cast piles cannot
a limit, as dredge hole has to be changed, numbers can be
accommodate the grab. increased.
Founding level can be changed.
Wells Piles
Large section modulus with Section modulus of individual
minimum cross section area. pile in a cluster is small and
Can resist large horizontal cannot resist large horizontal
forces. forces.
Durability high due to large size Durability low due to slender
and low stress. size and high slump concrete.
Speed of construction very Very quick construction process.
slow.
Except sinking, generally low Large diameter piles, driven
technology work with simple piles, augured piles, RMC piling
equipment. etc. require special equipment.
Suitable for alluvial rivers with Suitable for locations where
high scour, very weak strata, free standing height is low (e.g.
high loads or where there are Flyovers, ROBs, Shallow rivers
chances of hitting by floating etc.).
trees/boulders.
Generally, Piles are more economical for small loads and at less
depths.
4. Types of Well Foundations
Ordinary Wells
These are constructed in their final position
either on dry bed or after making an island in
the river at construction site.
Caissons
These are fabricated outside the flowing
channel and floated to the final position.
When velocity of water is high, making it
difficult to construct either an island or
cofferdam to construct a well, caisson type
construction are used.
5. Common Shapes
Multiple
Dredge Hole
6. Depth of Well Foundations
(Provisions of sub-structure Code)
6.9.1 Shall be taken to such a depth as to provide
adequate grip below the deepest anticipated
scour. The depth below HFL shall not be less than
1.33 times of the maximum scour depth.
Well depth can be reduced if inerodible strata is met
with at a shallow depth. Clay is not such a strata.
The foundation shall not normally rest on sloping
rock strata.
6.9.3 The depth shall be adequate to provide stability
against foundation pressure, overturning and
sliding.
Only 50% of passive earth pressure, below
maximum scour level, shall be considered while
considering stability against overturning.
Design and Analysis should be done as Appendix-V.
Gale’s Table
1. Layout of Wells
2. Making of Island (if required)
3. Fabrication of Cutting Edge
4. Well Curb Construction and Pitching
5. Construction of Steining
6. Well Sinking
7. Bottom Plug, Sand Filling, Top Plug and Well
Cap
7.1 Layout
MS Angles
MS Plate
Fillet Weld
Gauge Marks
Cutting Edge
Fabrication
7.4 Well Curb – Construction and Pitching
The slope of well curb is 1H:2V. But it depends on
type of soil strata.
RDSO Manual for Wells: Slope to Vertical not to be
more than 300 (Up to 450 in Sandy soil).
Offset of about 50mm on outside to ease sinking.
It is generally of minimum M-25 grade RCC.
May be precast or cast in situ.
Using steel liner on outer face is optional.
Centre of the well curb should be carefully marked.
If the site is dry, the curb should be assembled on
wooden blocks or sand bags placed at spacing of
about 1.5m.
If the river is full of water, the curb is generally
pitched at about 15cm above the water level.
Fabrication of
Well Curb
Well Curb
Reinforcement
7.5 Construction of Steining
Chisels
Breaking hard strata by chiseling
Important Points in Open sinking
• Dredged material should not be dumped close to the
well and on one side only.
• When the wells are to be sunk close to each other and
the distances between them is not greater than D,
they should be sunk alternately i.e. one sunk D/2 in
advance of the other.
• In case of abutment, where there is high bank on one
side, dig the pit of sufficiently larger sizes leaving
about 6-8 m clear distance round the well.
• If sinking is obstructed by stray boulders/rock/logs of
wood, resistance increases suddenly and well starts
tilting. Overcome the obstruction by loading the well
on that side and carrying out heavy dredging on that
side. The obstruction either rolls into the dredge hole
or the cutting edge is able to cut it. If this does not
succeed, obstruction is removed by sending divers or
using explosives.
Sinking in Clay
Steining should be made as thick as possible.
Excavation can be carried out much more conveniently and
speedily by dewatering it completely once it has gone into
clay by 1 to 1.5m.
Permissible Limits:
Tilt – 1 in 80
Precautions
Outer surface of well curb and steining must be regular
and smooth.
Radius of the curb is kept about 25 - 40mm larger than
the outside radius of the well steining.
Dredging should be done carefully.
Correction of Tilt and Shift
Pushing
the Well
Water Jetting or
Digging Pit
7.6.2 Pneumatic Sinking of Wells
Required when open sinking cannot be done.
Complete dewatering is also not possible:
• Due to sand blowing, or
• Due to heavy inflow of water, making pumping
prohibitive in cost.
Pneumatic sinking is 5 to 6 times costlier.
The depth to which pneumatic sinking may be done
without undue risk to lives of the men is about 33.5m.
In this, sinking is done under compressive air by
fixing covers on the dredge hole and pumping
compressed air into it.
All the water is pushed out up to the level of cutting
edge.
Men are then sent inside the well to carry out
excavation.
Pneumatic Sinking of Wells
VIDEO
7.6.3 Jacking Down Method
VIDEO
7.7.1 Bottom Plugging
It makes the well behave as well,
otherwise the well will keep on
sinking under loads.
Desirable to give a spherical shape.
Done using Tremie concreting.
Top kept 300mm above the top
edge of the inclined face of the
curb.