Professional Documents
Culture Documents
Blasting & Painting Procedure
Blasting & Painting Procedure
1.0 OBJECTIVES
The objective of this document is to ensure the blasting & painting works are
being done as per the customer specifications & requirements.
2.0 SCOPE
This procedure is applicable to the blasting & painting works of steel materials
for any projects.
3.0 REFERENCES
3.1. Paint manufacturer procedures
1
5.0 RESPONSIBILTY
5.1. Project manager & his team are responsible for the effective
implementation of this work procedure
6.0 PROCEDURE
6.1. BLASTING PROCEDURE
6.1.1. INCOMING INSPECTION
6.1.1.1. Inspection shall be done as per the work instructions.
6.1.2. INDENTIFICATION
6.1.2.1. All the identifications of the materials without ID Tag, shall be
transferred to Material Traceability Report before blasting and
the materials shall be identified accordingly.
6.1.2.2. The areas not to be blasted are clearly identified and protected
with appropriate means of protection prior to blasting.
2
6.1.3.3. Compressed air used must be dry and free from oil. Water and
oil traps to be present and in working condition in the
compressor.
6.1.4.2. Either Copper Slag, Garnet or iron grits abrasives or any other
abrasive grits approved by the customer shall be used for
blasting.
6.1.5.1. After blasting, the surface area shall be air blown to remove
abrasive residues and dust.
3
6.1.5.2. Air used for the blowing of the grit from the surface of the
prepared steel to be free of oil and water.
6.1.6. INSPECTION
6.1.8. DOCUMENTATION
4
6.1.8.1. All data of process shall to be recorded on the prescribed
forms.
6.2.2.2. All brush / rollers are to be thoroughly cleaned and dry before
use in the paint application. Rollers shall not be reused.
6.2.2.3. Proper spray equipment and spray tip sizes to be used as per
the paint manufacturer’s recommendation.
5
6.2.3.1. Temperature of steel surface prior to the application of paint is
to be checked to ensure that the required temperature is
achieved.
6
regulated pot life. Partial mixing of paints should be
discouraged.
6.2.4.5. The owner shall appoint the inspector of the paint supplier to
perform quality check to ensure its compliance with the painting
specification proposed.
6.2.5. INSPECTION
7
6.2.7. REPAIR PAINTING
6.2.8. DOCUMENTATION
8
6.3.1. Prior to delivery, the owner or their representative shall inspect the
painted product. After inspection steels shall be packed or bundled. Rag
shall be placed on the contact surface of the painted steels.
6.3.2. Lifting belts shall be used when lifting. If using lifting chain, rags shall
be placed between the painted steel and chain to avoid damage of the
painted surface.
6.3.3. Columns, beams, bracing, trusses and girders will be stacked properly
and securely fastened on the trailer. Loose items will be packed as
bundles.
6.4.1. The containers (Tin, Cans, Drums, Etc) in which paints are to be stored
should be sealed tightly in order to prevent paint from thickening.
Skinning and evolving solvent vapors giving rise to fire hazard. All
paints shall be stored, mixed, thinned, applied and cured strictly in
accordance with manufacturer’s recommendations.
6.4.2. Containers should be filled completely and sufficient room (Free space
between paint surface and lid) should be kept to allow the paint to be
stirred without the risk of spillage.
9
6.4.4. Excess humidity of the air in the storage area likely to cause paint
container to corrode and in order to prevent corrosion, metal container
should not be placed directly on the ground but on platform of racks.
6.4.5. When paint is taken from the store, the earlier batch should always be
taken first and paint which have become excessively thick or which
contain a sediment that cannot be re-suspended by stirring, should
never be used.
7.0 RECORD
10